Exam Cheat Sheet · Quick Reference
Alabama Carpentry and Framing Contractor
Alabama · PSI Services Contractor
Alabama State Portion 60 questions
Key Distinctions
Per IBC 2301.2 lumber dimensions on documents are deemed nominal unless specifically designated as actual (a 2×4 is really 1½" × 3½"), but per IBC 2304.2 computations for required member sizes must be based on net/actual dimensions.
IBC 2021 Section 2301.2Board feet are always figured with nominal dimensions (a 2×6 counts as 2" × 6"), even though the dressed board actually measures 1½" × 5½".
IRC Section R602.1, R602.3; IRC 2018 Section R602.1A quantity takeoff is made after design is complete by counting and measuring actual material quantities from finished construction documents, while pre-design estimates are rough approximations made before drawings exist and parametric estimates use historical cost-per-unit data.
IRC Section R602.3, Table R602.3(1)In a unit-cost estimate interior partition walls are measured in lineal feet (LF), with the per-foot cost covering framing through finish, while floors and roofs are measured in square feet (SF).
Carpentry and Building Construction, Section 2.4, Pages 61-62Per IBC 1507.2.8.3 the underlayment goes over the drip edge along eaves, whereas the drip edge goes over the underlayment along rakes; drip edge is mechanically fastened at not more than 12 inches on center.
IBC 2021 Section 1507.2.8.3With a level, a higher rod reading means lower ground elevation, so a 6'6" reading at B versus 4'6" at A means point B is 2 feet lower than point A.
Carpentry and Building Construction, Chapter 9 — Measuring a Difference in ElevationPer IBC Table 2308.5.1, 2×6 studs in bearing walls are limited to a 10-foot laterally unsupported height, while 2×4 studs in nonbearing walls are permitted up to 14 feet at 24 inches on center (the 20-foot height applies only to nonbearing walls).
IBC 2021 Table 2308.5.1Per IBC 2308.5.9, a stud in a nonbearing partition carrying only its own weight may be cut or notched up to 40 percent of its depth, a less restrictive limit than the 25 percent maximum for exterior walls and bearing partitions.
IBC 2021 Section 2308.5.9At a 24-foot building width, IBC Table 2308.4.1.1(1) gives a 2-2×10 a 6'-10" span (so it is the minimum for a 6-foot opening at 30 psf ground snow), while IBC Table 2308.4.1.1(2) limits a 2-2×8 interior header supporting one floor to 5'-5".
IBC 2021 Table 2308.4.1.1(1)Hip and valley rafters should be 2 inches wider in nominal dimension than the common rafters (2×8 hips with 2×6 commons) to give full bearing to the ends of intersecting jack rafters.
Carpentry and Building Construction, Chapter 18, Page 504The ridge board is nominal 2" lumber slightly wider than the rafters it supports (2×10 ridge with 2×8 rafters) so the angled rafter end cuts bear fully on it.
Carpentry and Building Construction, Section 19.1, Page 530On a performance-rated panel, the first number is the maximum support spacing in inches for roof sheathing use and the second number is the maximum spacing for subflooring use.
Carpentry and Building Construction, Section 19.5, Pages 562-563Per Section R502.6.2, joists framed into the side of a wood girder must be supported by approved framing anchors or on ledger strips not less than nominal 2×2, rather than simply bearing on top.
IRC 2021 Section R502.6.2A builder's level is the least expensive instrument and a good model is accurate to about ±1/4" at 75', while a theodolite is a transit that reads horizontal and vertical angles electronically on an LCD screen with no vernier scale, used where extreme accuracy is required.
Carpentry and Building Construction, Chapter 9 — Types of Instruments / LevelsKey Terms
Formulas to Know
Board feet = (nominal thickness in inches × nominal width in inches × length in feet) ÷ 12; e.g., 2×10×22' = (2 × 10 × 22) ÷ 12 = 36.67 bd ft, × 24 pieces ≈ 880 bd ft; 2×4×10' = (2 × 4 × 10) ÷ 12 = 6.67 bd ft, × 35 = 233 bd ft; a 2×6×12' = 12 bd ft, × 50 = 600 bd ftBoard feet = (surface area ÷ 100) × table factor; 2×6 rafters at 16" OC = 102 bd ft per 100 sq ft, so 2,100 sq ft → 21 × 102 = 2,142 bd ft (includes rafters, hips/valleys, ridge, collar ties); 2×6 ceiling plank at 16" OC = 88 bd ft per 100 sq ft (63 at 24" OC; 2×4 at 16" OC = 42; 2×8 at 16" OC = 117)Add clearance to each side, then Volume (cu ft) = length × width × depth and cubic yards = cubic feet ÷ 27 (27 cu ft = 1 cu yd); e.g., 26'×40' house with 2' clearance each side and 7' depth → 30 × 44 × 7 = 9,240 cu ft ÷ 27 ≈ 342 cu ydCubic yards = excavation area (sq ft) × factor for depth (0.259 cu yd per sq ft at 7 ft deep); 44' × 30' = 1,320 sq ft × 0.259 = 341.88 ≈ 342 cu ydCubic yards = factor per 100 LF × (trench length ÷ 100); a 42" deep × 18" wide trench = 19.4 cu yd per 100 LF, so 30 ft → 19.4 × 0.30 = 5.82 cu ydStuds = (wall length in feet ÷ 1.333) + 1 (not counting extras for corners and openings); 48 ft → (48 ÷ 1.333) + 1 = 37 studsPanels = roof area ÷ 32 sq ft per panel, then add 5% for trim and waste; 72.19 × 0.05 = 3.6; 72.19 + 3.6 = 75.79 → 76 sheetsActual length = drawing measurement in inches ÷ 0.25 (each ¼ inch = 1 foot); a 3-inch measurement = 3 ÷ 0.25 = 12 feetMeasure 3 ft on one leg and 4 ft on the other; the diagonal must read exactly 5 ft for a 90° corner (a 5'-1" reading means adjust a layout line). In multiples: 9 ft and 12 ft legs must give a 15-ft diagonal.R = 5.2(ds + dh), where ds is the static head (depth of water up to the secondary drainage inlet with the primary system blocked) and dh is the hydraulic head above that inlet at design flowWhere building width perpendicular to the wall footing exceeds 32 ft, increase footing width by 2 inches and footing depth by 1 inch for every 4 ft of added building width; a 36-ft-wide building = +2" width and +1" depthStep 1: floor area = length × width per level (20' × 40' = 800 sq ft); then apply the board-feet-per-100-sq-ft factor from the table and multiply by cost per board foot