Alabama State Portion 110 questions

Business Organization 1 Q · 1%
Business legal structures (sole proprietorship, partnership, corporation, LLC) — characteristics, advantages, and disadvantagesLiability exposure by business structure typeTaxation differences among business entity typesFormation documents required for each business structure (DBA filing, partnership agreement, articles of incorporation, operating agreement)Joint ventures — formation, management, and licensing considerationsBusiness naming, fictitious names/DBA registration, and trademark basicsBusiness plan elements and purpose (planning, loan/investor, benchmarking tool)New business startup checklist — organizational steps and professional advisors
Risk Management 2 Q · 2%
Risk assessment fundamentals and probability of lossTypes of property insurance for contractors (builder's risk, inland marine, equipment floater)Commercial general liability (CGL) insurance coverage and exclusionsSurety bonds: types, qualifying requirements, and bond languageEmployment-related insurance (workers' compensation, unemployment, Social Security)Insurance coverage requirements for subcontractorsMiller Act and Little Miller Acts bonding requirements for federal projectsCoverage gaps, overlaps, and business owner's policies (BOPs)
Project Management 2 Q · 2%
Scheduling methods: calendar, bar chart, and critical path method (CPM)Scheduling process elements: sequence of tasks, activity duration, contingency time, and float timeScheduling and cash flow managementProject manager and supervisory team roles (superintendent, foreman, materials expediter)Budget tracking and cost overrun controlsMaterials management: just-in-time delivery, purchase orders, and receivingCustomer communication, change order handling, and negotiation basicsSubcontractor selection, site rules, and employee vs. independent contractor classification
Estimating 4 Q · 4%
Bid documents and bid package componentsEthics in bidding (bid shopping, bid peddling, bid rigging)Estimate planning and site visit considerationsEstimating framework and quantity take-off methodDetermining direct costs (labor, materials, equipment)Labor burden and overhead calculationsMarkup, profit margin, and cost-based pricingJob cost recording system and estimating technology tools
Safety and Environmental 2 Q · 2%
OSHA standards and recordkeeping requirements (Forms 300, 300A, 301)OSHA penalty types and violation classificationsEmergency action plan requirementsSafety Data Sheets (SDS) and Hazard Communication StandardUnderground utility and overhead power line safetyEnvironmental laws and EPA regulatory frameworkAsbestos and lead-based paint regulations and renovation requirementsHazardous and non-hazardous solid waste identification and disposal
Labor Laws 3 Q · 3%
Alabama Workers' Compensation coverage requirements and employer exemptionsSecuring workers' compensation payment: insurance vs. self-insurance optionsEmployer reporting obligations for injuries and compensation settlementsDrug-free workplace program requirements and workers' compensation premium discountsFair Labor Standards Act: minimum wage, overtime, and recordkeeping requirementsHiring minors: working hour restrictions and prohibited hazardous tasks in constructionEmployment eligibility verification: Form I-9 requirements and documentationAnti-discrimination laws: ADA, Title VII, ADEA, and Equal Pay Act applicability
Payroll and Employment Taxes 4 Q · 4%
Federal Employer Identification Number (EIN) requirements and applicationSocial Security and Medicare taxes (FICA) — calculation and employer/employee withholdingFederal income tax withholding — W-4 and W-2 formsFederal Unemployment Tax (FUTA) — rates, thresholds, deposit schedules, and Form 940Alabama Unemployment Compensation (UC) employer liability and registration — Form SR-2Alabama UC taxable wage base, contribution rates, and experience ratingAlabama quarterly contribution and wage report filing — Form UC-CR4, deadlines, penalties, and interestAlabama new-hire reporting requirements and procedures
Financial Management 4 Q · 4%
Bookkeeping practices and the accounting cycleFinancial statements (balance sheet, income statement, statement of cash flows)Financial ratio analysis (liquidity, quick, activity, debt, profitability, return on assets)Cash and accrual methods of accountingContract accounting methods (completed contract, percentage of completion, cost comparison)Cash flow management, accounts receivable collection, and progress paymentsEquipment depreciation methods (straight-line and accelerated/MACRS)Payroll accounting (gross pay, deductions, net pay, payroll journal)
Contracts 3 Q · 3%
Required elements of a binding contract (offer, acceptance, consideration, competent parties, legal purpose)Types of construction contracts (lump-sum, unit-price, cost-plus, turnkey, fast-track)Contracting methods (single prime, multiple prime, design/build, construction management, partnering)Contract provisions (payment terms, progress payments, retainage, final payment, obligations of parties)Breach of contract (material vs. immaterial breach, liquidated damages, statute of limitations)Change orders and contract modificationsAlternative dispute resolution (negotiation, mediation, collaborative law, arbitration)Subcontractor agreements and employee vs. independent contractor classification
Lien Laws 1 Q · 1%
Who qualifies for a mechanic's or materialman's lien (eligible claimants and covered work)Filing requirements for verified lien statement (contents, form, and probate court recordation)Deadlines for filing lien statements by claimant type (original contractor, day laborer, other persons)Priority of mechanic and materialman liens relative to prior mortgages and subsequent encumbrancesNotice requirements for subcontractors and materialmen before filing a lien statementTime limitations for enforcement actions and consequences of failure to actTransfer of lien from real property to alternate security (bond or money deposit)Lien satisfaction, acknowledgment of release, and penalties for failure to release
Licensing Laws 4 Q · 4%
Alabama Board of Electrical Contractors composition, appointment, and termsQualifications and experience requirements for electrical contractor licensureQualifications and experience requirements for journeyman electrician licensureLicense application, examination administration, and passing standardsLicense fees, renewal, late renewal, and reinstatement proceduresInactive status certification requirements and reinstatement to active licenseLicense exemptions from state electrical licensing requirementsContinuing education requirements, approved providers, and contact hour computation
General Electrical Knowledge 10 Q · 9%
Ohm's Law and basic DC circuit calculations (voltage, current, resistance, power)Series, parallel, and combination circuit types and current/voltage distributionAC fundamentals: sine waves, frequency, electrical degrees, and phase relationshipsElectrical units and definitions (ampere, volt, ohm, watt, impedance, capacitance, inductance)NEC definitions and terminology for wiring systems (branch circuit, feeder, service, bonding, grounding)General installation requirements of NEC Article 110 (approval, listing, examination, terminations, deteriorating agents)Voltage drop and single-phase / three-phase power calculations
Grounding and Bonding 9 Q · 8%
Grounding electrode system types and selection (NEC 250.52)Grounding electrode conductor sizing using Table 250.66Equipment grounding conductor types, sizing, and identification (NEC 250.118–250.122)Main bonding jumper and system bonding jumper requirementsBonding of services, piping systems, and structural metal (NEC 250.92–250.104)Grounding of separately derived systems and generatorsEffective ground-fault current path requirements for grounded and ungrounded systemsGrounding electrode installation methods and connection requirements (NEC 250.53–250.70)
Conductors and Cables 10 Q · 9%
Conductor insulation types, temperature ratings, and type designations (e.g., THHN, XHHW, RHW, TW)Ampacity tables and correction/adjustment factors for conductors rated 0–2000 voltsConductor material, size, and stranding requirements (copper, aluminum, copper-clad aluminum; AWG and kcmil)Grounded conductor identification methods and color codingUses permitted and uses not permitted for specific cable types (NM, NMC, MC, AC, MI, SE, USE, UF, TC, ITC, FC, FCC, IGS, Type P)Securing, supporting, and bending radius requirements for cable assembliesFlexible cords and fixture wires — types, ampacities, permitted uses, and marking requirementsConductor marking requirements and conductor properties (Chapter 9 Table 8)
Raceways and Boxes 8 Q · 7%
Conduit fill calculations and conductor count limits (NEC Chapter 9 Tables)Raceway and conduit selection by wiring method type (RMC, IMC, EMT, FMC, LFMC, PVC, ENT, RTRC, LFNC)Securing and supporting requirements for conduits, tubing, and racewaysBox fill calculations and volume allowances (Article 314)Pull box and junction box sizing for conductors 4 AWG and largerUnderground installation requirements and minimum cover depths for racewaysWireway and auxiliary gutter conductor fill, splices, and ampacity rulesCable tray installation, fill requirements, and permitted wiring methods
Special Occupancies and Equipment 4 Q · 4%
Hazardous location classification (Classes I, II, and III; Divisions 1 and 2)Wiring methods and sealing requirements for hazardous locationsHealth care facility essential electrical systems (Type 1 and Type 2 EES)Patient care space grounding, bonding, and receptacle requirementsSwimming pools, spas, and fountains — GFCI protection, bonding, and underwater luminairesSolar PV systems — circuit sizing, overcurrent protection, rapid shutdown, and arc-fault protectionElectric vehicle power transfer system (EVSE) installation and overcurrent protectionFire pump power sources, disconnecting means, and continuity of power requirements
Electrical Power 3 Q · 3%
Transformer installation requirements and NEC Article 450 complianceTransformer overcurrent protection (primary and secondary, 1000 V and below)Transformer types, cooling methods, and insulation classesEmergency system power sources and automatic transfer equipment (NEC Article 700)Generator installation, marking, overcurrent protection, and disconnecting means (NEC Article 445)Legally required standby systems and critical operations power systems (NEC Articles 701 and 708)Energy storage systems and stationary standby batteries (NEC Articles 706 and 480)Interconnected electric power production sources and parallel operation requirements (NEC Article 705)
Motors 6 Q · 5%
Motor branch-circuit conductor sizing and ampacity requirementsMotor overload protection selection and settingsBranch-circuit short-circuit and ground-fault protective device ratingsMotor controller types, ratings, and enclosure classificationsDisconnecting means requirements for motors and controllersAC motor types and operating characteristics (squirrel-cage, wound-rotor, synchronous)DC motor types, speed control methods, and starting requirementsHermetic refrigerant motor-compressor circuit requirements
Low Voltage 2 Q · 2%
Class 1, Class 2, and Class 3 circuit classifications and power source limitationsSeparation requirements between low-voltage and power/light circuitsCable types and substitution hierarchy for power-limited circuits (CL2, CL3, CMP, CMR, PLTC, etc.)Installation of communications cables by building location (plenum, riser, general-purpose, dwelling)Grounding and bonding of communications systems, cable shields, and primary protectorsAntenna system installation, clearances, and grounding requirementsNetwork-powered and premises-powered broadband communications systems (Articles 830 and 840)Class 4 fault-managed power systems and energy management system controls
Lighting 3 Q · 3%
Luminaire installation requirements by location (wet, damp, corrosive, closets, bathtub/shower zones)Luminaire support methods and outlet box requirementsLuminaire grounding and wiring requirementsRecessed luminaire requirements (thermal protection, clearances, insulation contact, IC vs non-IC)Lighting track installation and restrictionsBallasts and auxiliary equipment for fluorescent and HID luminaires (thermal protection, disconnecting means)Low-voltage lighting systems (voltage limitations, secondary circuit isolation, branch circuit requirements)Lamp and light source types (incandescent, fluorescent, HID, LED) and their operating characteristics
Illuminated Signs 2 Q · 2%
Branch circuit requirements for signs (rating, dedicated circuit, and wiring methods)Disconnecting means location and lockout requirementsGrounding and bonding of sign equipment and metal partsListing, labeling, and marking requirements for signs and retrofit kitsTransformers and electronic power supplies (ratings, secondary voltage, ground-fault protection)Neon secondary-circuit wiring (≤1000V and >1000V methods, conductor types, spacing)Location restrictions (height above vehicles, combustible materials, wet location drain requirements)Portable and mobile sign requirements (cord types, GFCI, support)
Fire Detection and Alarm Systems 2 Q · 2%
Power-limited fire alarm (PLFA) circuit wiring methods and cable types (FPL, FPLR, FPLP)Non-power-limited fire alarm (NPLFA) circuit power source and overcurrent protection requirementsBranch circuit requirements and disconnecting means identification for fire alarm systemsSeparation of PLFA conductors from power, Class 1, and NPLFA circuit conductorsFire alarm cable applications in plenums, risers, and general building locationsCircuit integrity (CI) cable and fire-resistive cable system installation requirementsAbandoned fire alarm cable removal and circuit identification requirementsNPLFA and PLFA conductor materials, sizes, and insulation requirements
Safety Information 5 Q · 5%
Electrical Safety Program (ESP) components and requirementsLockout/tagout (LOTO) procedures and electrically safe work conditions (ESWC)Arc flash risk assessment and PPE selection methodsShock risk assessment and approach boundaries (limited and restricted)Personal protective equipment (PPE) selection, use, and inspectionQualified vs. unqualified person requirements and safety trainingArc flash hazard warning labels and equipment markings (NEC 110.16)Working space and guarding requirements for electrical equipment (NEC 110.26, 110.27)
Overcurrent Protection 6 Q · 5%
Types and classifications of fuses (plug, cartridge, Class H/J/K/L/R/T)Circuit breaker types and operating principles (thermal, magnetic, thermal-magnetic, electronic)Standard ampere ratings for fuses and circuit breakers (NEC Table 240.6(A))Overcurrent device location requirements and tap conductor rules (NEC 240.21)Ground-fault protection of equipment (GFPE) for services and feeders (230.95, 240.13)Arc energy reduction (NEC 240.87) and current-limiting overcurrent devicesInterrupting ratings and short-circuit current calculationsOvercurrent device installation requirements (accessibility, enclosures, prohibited locations)
Service, Feeders, and Branch Circuits 10 Q · 9%
Branch-circuit ratings, conductor sizing, and overcurrent protection requirementsGFCI and AFCI protection requirements by location and occupancy typeDwelling unit receptacle outlet placement and required branch circuitsService entrance conductor sizing, wiring methods, and clearancesService disconnecting means requirements, ratings, and locationFeeder conductor sizing, overcurrent protection, and identificationPanelboard, switchboard, and switchgear installation and overcurrent protectionSurge-protective device (SPD) types, installation, and connection requirements

Key Distinctions

AddendavsModifications

Addenda are contract changes made before the contract award, while modifications are changes made after the contract is signed and executed.

NASCLA Contractors Guide, Chapter 7 - Contract Management
ArbitrationvsMediation

In arbitration a third-party arbitrator acts as a judge and renders an arbitral award that legally binds all parties, while in mediation the neutral mediator only facilitates dialogue and the parties themselves set the terms of any agreement.

NASCLA Contractors Guide, Contract Management chapter — Alternative Dispute Resolution section
Collaborative lawvsMediation/arbitration

Collaborative law uses the parties' own advocates (usually lawyers) to negotiate a mutually beneficial result with no neutral mediator or arbitrator involved.

NASCLA Contractors Guide, Contract Management chapter — Alternative Dispute Resolution section
All-risk builders' risk insurancevsNamed peril builders' risk insurance

All-risk covers direct loss by any peril not specifically excluded by the policy (almost all risks), while named peril has narrower coverage and lists the perils covered, such as fire and lightning.

NASCLA Contractors Guide, Managing Risk chapter — Insurance section
Project overheadvsCompany overhead

Project overhead includes job-specific items such as bonds, temporary storage, temporary office, security guard, utilities, dumpsters and portable toilets, while company overhead includes office rent, accounting fees and legal fees.

NASCLA Contractors Guide, Bidding and Estimating chapter — Add Project Overhead section
Unit price estimating methodvsQuantity take-off method

The unit price method bundles labor, materials, equipment and subcontractors into a single price for an entire task, while the quantity take-off method estimates each component individually.

NASCLA Contractors Guide, Bidding and Estimating chapter — Other Methods of Estimating section
Bid riggingvsBid shopping / bid peddling

Bid rigging is collusion in which contractors coordinate bids to fix the award outcome; bid shopping is seeking lower subcontractor bids after original bids are submitted, and bid peddling is a subcontractor approaching the general contractor after award to lower the price.

NASCLA Contractors Guide, Bidding and Estimating chapter — Bid Rigging section
Leasing equipmentvsPurchasing equipment

Leasing requires no down payment, spreads lower payments over a longer period, makes payments deductible as operating expenses and returns obsolete equipment to the owner, while purchasing usually costs less in the long run and gives ownership and salvage value (leases generally cannot be cancelled).

NASCLA Contractors Guide, Bidding and Estimating chapter — Determining Estimated Costs section
Standard ampere ratings for fuses onlyvsStandard ratings for both fuses and inverse time circuit breakers

Ratings 1, 3, 6 and 601 amperes are additional standard ratings for fuses only, while values such as 15 through 6000 amperes listed in Table 240.6(A) (e.g., 110 A) apply to both fuses and inverse time circuit breakers.

NEC 2023 Section 240.6(A) and Table 240.6(A)
NFPA 70E tagout rulevsOSHA 29 CFR 1910.147 tagout rule

NFPA 70E prohibits tagout without a lock unless the isolating device is incapable of accepting a lock, whereas OSHA permits tagout where the employer demonstrates an equivalent level of safety.

American Electricians' Handbook, 17th ed., Division 13 (Electrical Safety), Sec. 49 — Application of Lockout or Tagout
Overload units for single-phase motor on 2-wire ungrounded circuitvsOverload units for 3-phase motor

A single-phase AC or DC motor on a 2-wire ungrounded supply needs only one running overload unit in either conductor, while a 3-phase motor requires three overload units, one in each phase.

NEC 2023 Table 430.37
Elevator raceway conductor fill (620.33)vsElevator wireway conductor fill (620.32)

In raceways, the sum of the cross-sectional area of the individual conductors shall not exceed 40 percent of the interior cross-sectional area of the raceway, except as permitted in 620.32 for wireways, where the limit is 50 percent.

NEC 2023 Section 620.33

Key Terms

Continuous load feeder sizing rule (215.2(A)(1)) NEC 2023 Section 215.2(A)(1)
Where a feeder supplies continuous loads or a combination of continuous and noncontinuous loads, the minimum conductor ampacity must be the noncontinuous load plus 125 percent of the continuous load.
Service-entrance conductor minimum ampacity (230.42(A)(1)) NEC Section 230.42(A)(1)
Service-entrance conductors supplying continuous loads must have ampacity not less than the noncontinuous loads plus 125 percent of the continuous loads.
One-family dwelling service disconnect rating (230.79(C)) NEC Section 230.79(C)
The service disconnecting means for a one-family dwelling must be rated not less than 100 amperes, 3-wire.
Optional dwelling calculation (220.82(A)) NEC 2023 Section 220.82(A)
The optional load calculation applies to a dwelling unit whose total connected load is served by a single 120/240-volt or 208Y/120-volt set of 3-wire service or feeder conductors with an ampacity of 100 or greater.
Free conductor length (300.14) NEC 2023 Section 300.14
At least 150 mm (6 in.) of free conductor, measured from where it emerges from the raceway or cable sheath, must be left at each outlet, junction and switch point for splices or connection of luminaires or devices.
Bored-hole clearance in wood members (300.4(A)(1)) NEC 2023 Section 300.4(A)(1)
Holes must be bored so the edge of the hole is not less than 32 mm (1 1/4 in.) from the edge of the wood member; where that distance cannot be maintained, a steel plate must protect the cable or raceway from nails or screws.
Steel protection plate for notches (300.4(A)(2)) NEC 2023 Section 300.4(A)(2)
Cables or raceways laid in notches in wood members must be protected from nail or screw penetration by a steel plate at least 1.6 mm (1/16 in.) thick of appropriate length and width covering the wiring area.
Straight pull box length (314.28(A)(1)) NEC 2023 Section 314.28(A)(1)
For conductors 4 AWG or larger in straight pulls, the box or conduit body length must be at least eight times the trade size of the largest raceway.
Angle or U pull spacing (314.28(A)(2)) NEC 2023 Section 314.28(A)(2)
Where splices or angle or U pulls are made, the distance from each raceway entry to the opposite wall must be at least six times the trade size of the largest raceway in the row.
Device (yoke) box-fill allowance (314.16(B)(4)) NEC 2023 Section 314.16(B)(4)
Each yoke or strap containing one or more devices or equipment requires a double volume allowance per Table 314.16(B)(1), based on the largest conductor connected to that yoke or strap.
Main/system bonding jumper screw identification (250.28(B)) NEC Section 250.28(B)
Where the main or system bonding jumper is a screw only, the screw must be identified with a green finish visible with the screw installed.
Supplemental grounding electrode spacing (250.53(A)(3)) NEC 2023 Section 250.53(A)(3)
Where multiple rod, pipe or plate electrodes are installed to meet the supplemental electrode requirement, they must be not less than 1.8 m (6 ft) apart.
Tap (tap circuit) American Electricians' Handbook, 17th ed., Division 3, Sec. 16 (A tap or tap circuit)
A set of conductors serving a single energy-utilizing device connected directly to a branch circuit without the interposition of a cutout/overcurrent device.
Stationary generator listing (445.6) NEC 2023 Section 445.6
Stationary generators must be listed, except one-of-a-kind or custom-manufactured generators, which are permitted to be field labeled.
Track lighting load (220.46(B)) NEC 2023 Section 220.46(B)
In other than dwelling units or hotel/motel guest rooms and suites, an additional 150 volt-amperes must be included for every 600 mm (2 ft) of lighting track or fraction thereof, with an exception permitting calculation based on a current-limiting device's rating.
Inactive status certification (Board Rule 303-X-2-.04) Alabama Supplement to the Contractors Guide (2014), Board Administrative Code 303-X-2-.04, Inactive Status Certification
A licensee may elect inactive status by written notice or the Board's online form, which must be received at least 30 days before the license expires; only active (not expired) licenses are eligible.
Mechanic's lien priority against a prior mortgage (Ala. Code § 35-11-211) Alabama Supplement to the Contractors Guide (2014), Excerpts from Alabama Lien Law — § 35-11-211 (Priority of lien)
A perfected mechanic's lien outranks liens and mortgages created after work commenced, but against a prior recorded mortgage it has priority only as to a building or improvement that is separable and removable without impairing the prior mortgage's value or security, and it must be enforced before that mortgage is foreclosed.
THHN insulation letters Conductor insulation type letters (THHN)
In THHN, T = thermoplastic insulation, HH = high heat resistance (90°C dry), and N = a nylon outer jacket adding abrasion and gasoline/oil resistance.

Formulas to Know

Minimum conductor ampacity / OCPD rating for continuous loads (branch, feeder, service)Minimum ampacity = noncontinuous load + (1.25 × continuous load); e.g., 80 A + (1.25 × 60 A) = 155 A, and 40 A + (1.25 × 60 A) = 115 A. For a branch OCPD with only continuous load: 1.25 × 16 A = 20 A (device and assembly not listed for 100% rating).
Series-parallel resistance and total current (Ohm's law)Equal parallel branches: R = R_branch ÷ n; two unequal: R = (R1×R2)/(R1+R2); add series resistances: R_total = R_series + R_parallel; then I = E ÷ R_total (e.g., 24 V ÷ 8 Ω = 3 A; 24 V ÷ 4 Ω = 6 A; 44 V ÷ 22 Ω = 2 A; 28 V ÷ 14 Ω = 2 A). Branch current = branch voltage ÷ branch resistance.
Three-phase voltage drop (circular-mil method)VD = (1.732 × K × I × L) ÷ CM; e.g., (1.732 × 12.9 × 24 A × 90 ft) ÷ 10,380 cmil = 4.65 V. Single-phase uses the factor 2 instead of 1.732.
Effective impedance at a power factor other than the tabulated one (Chapter 9, Table 9, Note 2)Effective Z = R cos(θ) + X sin(θ); for another circuit power factor, Ze = R × PF + XL sin[arccos(PF)].
Motor feeder conductor minimum ampacity (430.24)125% of the largest motor FLC + sum of the other motors' FLCs; e.g., (1.25 × 15.2 A) + 15.2 A + 15.2 A = 49.4 A.
Motor feeder overcurrent device maximum rating (430.62(A))Max = largest branch-circuit short-circuit/ground-fault device rating + sum of FLCs of the other motors; e.g., 90 A + 14 A + 10 A = 114 A; since it is a 'not greater than' maximum and 114 A is not a standard size, use the next LOWER standard size, 110 A.
A/C hermetic compressor branch-circuit short-circuit/ground-fault device (440.22(A) Exception No. 2)Normally 175% of rated-load current; where insufficient for starting, may be increased but not to exceed 225% of rated-load current or branch-circuit selection current, whichever is greater; e.g., 28 A × 2.25 = 63 A, so select the next LOWER standard size, 60 A (no round-up permitted).
Generator conductor ampacity (445.13)Conductor ampacity ≥ 115% of generator nameplate current rating; e.g., 80 A × 1.15 = 92 A.
Wye-start, delta-run controller-to-motor conductors (430.22(C))Ampacity ≥ 72% of motor full-load current (derived from 58% × 1.25 = 72%).
Dwelling general load before demand factors (Article 220)General lighting = area (sq ft) × 3 VA/sq ft; add 1,500 VA per small-appliance circuit and 1,500 VA per laundry circuit; multiply per-unit total by number of units (e.g., 1,200 sq ft × 3 + 2×1,500 + 1,500 = 8,100 VA per unit; × 4 units = 32,400 VA). Commercial occupancies use the Table 220.42(A) unit load instead (retail 1.9 VA/sq ft).