Key Distinctions
Bid shopping is the general contractor approaching subcontractors other than those who submitted bids to seek a lower offer than the original quotes, while bid peddling is a subcontractor approaching the general contractor after the project was awarded with the intent of lowering the price it submitted on bid day.
NASCLA Contractors Guide, Bidding and Estimating chapter — Bid Peddling sectionBid rigging is a form of collusion in which contractors coordinate their bids to fix the award outcome, whereas bid shopping (GC seeking lower sub bids after bids are in) and bid peddling (sub lowering its price after award) involve price-cutting rather than coordinated collusion.
NASCLA Contractors Guide, Bidding and Estimating chapter — Bid Rigging sectionIn mediation an independent third-party mediator only facilitates dialogue and the parties themselves set the conditions of any agreement, while in arbitration the arbitrator acts as a judge and renders a decision (arbitral award) by which all parties are legally bound.
NASCLA Contractors Guide, Contract Management chapter — Alternative Dispute Resolution sectionMediation and arbitration use a neutral third party, but collaborative law is a facilitative process with no neutral mediator or arbitrator in which parties use their advocates, most often lawyers, to negotiate a mutually beneficial result.
NASCLA Contractors Guide, Contract Management chapter — Alternative Dispute Resolution sectionA material breach is a serious violation (e.g., contractor refuses to perform or owner refuses to pay) that may void the contract and will most likely end in litigation, while an immaterial or partial breach usually does not terminate the contract and the injured party may only sue for the value of the damages.
NASCLA Contractors Guide, Contract Management chapter — Breach of Contract sectionThese are mutually exclusive remedies — an owner who sues for liquidated damages (e.g., $500/day × 20 days = $10,000) cannot also sue for actual damages.
NASCLA Contractors Guide, Contract Management chapter — Breach of Contract sectionAll-risk covers direct loss by those perils not specifically excluded by the policy (almost all risks), while named peril has narrower coverage and specifies which perils are covered, such as fire and lightning.
NASCLA Contractors Guide, Managing Risk chapter — Insurance sectionThe quantity take-off method individually estimates units of materials and labor for each task (generally the most accurate), while the unit price method bundles all cost factors — labor, materials, equipment, and subcontractors — into a single price for the entire task.
NASCLA Contractors Guide, Bidding and Estimating chapter — Quantity Take-off sectionProject overhead includes bonds, temporary storage, temporary office, security guard, utilities, dumpsters, and portable toilets (typically 5–10 percent of the total bid), while company overhead includes office rent, accounting fees, and legal fees.
NASCLA Contractors Guide, Bidding and Estimating chapter — Add Project Overhead sectionSmall tools and pickup trucks are indirect costs figured into project overhead rather than listed as direct project equipment costs in the estimate.
NASCLA Contractors Guide, Bidding and Estimating chapter — Determining Estimated Costs sectionLeasing offers no down payment, lower payments spread over a longer period, lease payments deductible as operating expenses, and return of obsolete equipment, but purchasing usually costs less in the long run and provides ownership/salvage value (leases generally cannot be cancelled).
NASCLA Contractors Guide, Bidding and Estimating chapter — Determining Estimated Costs sectionAn allowance covers items not specified in the plans (carpeting, fixtures, lighting) and represents the owner's budget for those items, while a contingency percentage protects the contractor if an unanticipated problem or condition arises and is based on the project's risk level.
NASCLA Contractors Guide, Bidding and Estimating chapter — Add Allowances sectionA conceptual estimate is generally prepared by the architect using cost models from previous projects, while the contractor may arrive at a much different cost because of the project's unique characteristics.
NASCLA Contractors Guide, Bidding and Estimating chapter — Other Methods of Estimating sectionKey Terms
Formulas to Know
Required Labor Hours per Task × Labor Rate = Labor Cost per Task (hours spent planning and scheduling must also be figured into labor cost)Price per Unit × Number of Units Needed = Total Material Unit Cost (obtain at least three supplier bids)Total Yearly Cost of Equipment ÷ Estimated Hours of Use per Year = Unit Cost per Hour; then Unit Cost per Hour × Project Hours = Project Equipment Cost. Examples: $12,000 ÷ 600 hrs = $20/hr; $30,000 ÷ 1,000 hrs = $30/hr, and $30 × 40 hrs = $1,200.Direct Costs ÷ (1 − Total Overhead %) = Bid Price. Example: project overhead 9% + company overhead 11% = 20% total, so direct costs are 80% of the bid; $100,000 ÷ 0.80 = $125,000.Project Costs Incurred ÷ Total Estimated Costs = % Complete; % Complete × Contract Amount = Cumulative Earnings. Example: $80,000 ÷ $160,000 = 50%; 50% × $200,000 = $100,000.Net Pay = Gross Pay − Taxes & Deductions. Example: $3,200 − ($384 + $198.40 + $46.40 + $160 + $96) = $2,315.20.Net Income ÷ Revenues = Profit Margin. Example: $46,300 ÷ $545,600 ≈ 8.5%. The higher the percentage, the more profitably the company is performing.(Current Assets − Inventory) ÷ Current Liabilities. Example: ($150,000 − $30,000) ÷ $100,000 = 1.20; a ratio of one or more is generally acceptable by most creditors.(Initial Asset Cost − Salvage Cost) ÷ Useful Life Years = Yearly Depreciation. Example: ($80,000 − $5,000) ÷ 5 = $15,000 per year.Total Labor Hours ÷ Hours per Day Available for the Task = Activity Duration in working days. Example: 16 hrs ÷ 4 hrs/day = 4 working days.