Exam Cheat Sheet · Quick Reference
Louisiana Foundations and Pile Driving
Louisiana · PSI Services Contractor
Louisiana State Portion 60 questions
Key Distinctions
A Type 1 condition exists when actual conditions differ materially from those indicated in the contract, while a Type 2 condition arises when actual conditions differ from what would reasonably be expected (neither clause relieves the contractor of the duty to thoroughly examine project conditions).
Construction Planning, Equipment, and Methods (9th ed.), Chapter 3 — Earthwork Planning sectionThe standard test compacts three equal layers with a 5.5-lb rammer dropped 12 in. 25 times, while the modified test uses a 10-lb rammer dropped 18 in. on each of five equal layers, delivering roughly five times the compactive energy and producing a higher maximum dry density at a lower optimum water content.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 4 — Compaction Tests sectionThe liquid limit is the water content at which the standard groove closes 1/2 in. (12.7 mm) along the bottom at exactly 25 blows of the cup, whereas the plastic limit is the lowest water content at which the soil can be rolled into a 1/8 in. (3.2 mm) diameter thread without crumbling.
Soils and Foundations, Pages 17-18 (Section 2-3, Soil Consistency—Atterberg Limits)A single-acting steam or air hammer strikes 40 to 60 blows per minute, while a double-acting hammer delivers 95 to 300 blows per minute (700 to 1,200 refers to optimal vibratory hammer frequency ranges).
Construction Planning, Equipment, and Methods (9th ed.), Chapter 17 — Single-Acting Hammers sectionCohesive soils swell about 40% between bank and loose states, while solid rock swells as much as 65% between bank and loose states and 20 to 40% from bank to placement in an embankment; the 10–30% figure is the separate shrinkage of cohesive soils from bank to compacted state.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 4 - Soil and Rock, Volumetric MeasurePer ACI 318-19, curing and protection are considered adequate if field-cured cylinders tested at the age designated for f'c average at least 85% of companion standard-cured cylinder strength, or if field-cured strength at test age exceeds f'c by more than 3.5 MPa (500 psi); the 75% figure instead applies to the lowest individual drilled core.
Design and Control of Concrete Mixtures (17th ed.), Chapter 20 — Evaluation of Compression Test Results section, Page 440An esker is a ridge or mound of boulders, gravel, and sand deposited as the bed load of meltwater streams on, within, or beneath a glacier, while a moraine is a direct glacial deposit — a heterogeneous mixture of all particle sizes from boulders to clay accumulated by the ice as it traveled.
Soils and Foundations, Chapter 1 — Soil Deposits section (Glacial Deposits)Soldier piles (H-piles) are typically set in predrilled holes around the periphery of an excavation and grouted in place with weak concrete, because predrilling rather than driving provides close control of alignment and location.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 3 — Soldier Piles and Lagging sectionConcrete with more than 3 percent entrained air should not be given a hard-troweled finish (risk of trapping bleed water/air and causing delaminations), which is why slabs with the 6 percent or more air typical of exterior freeze-thaw exposure receive float or broom finishes.
Design and Control of Concrete Mixtures (17th ed.), Chapter 15 — Finishing Flatwork / Bullfloating or Darbying section, Page 330In certain soils, digging resistance is usually greater in undisturbed earth than in an existing trench line, so an old ditch line digs easier and can often be spotted visually as darker spots of topsoil mixed in with lighter-colored subsoil.
Pipe and Excavation Contracting, Page 148Depending on soil type, heaped capacity is usually about 130 percent of struck capacity (e.g., a 2-ft-wide hoe bucket with 5 to 6 LCF struck has about 6.5 to 8 LCF heaped).
Pipe and Excavation Contracting, Pages 142-143An oxygen enriched atmosphere contains more than 23.5 percent oxygen by volume and an oxygen deficient atmosphere contains less than 19.5 percent; either is a hazardous atmosphere under the confined spaces standard.
29 CFR 1926, §1926.1202The much longer required curing/stripping period for cap beams ties up each form set so one set cannot keep pace with the schedule, which is the primary factor driving the need for two complete cap beam form sets.
SP-4 Chapter 3, Section 3.7Key Terms
Formulas to Know
q = k·h·N_f / N_d, where N_f = number of flow channels and N_d = number of equipotential drops. Worked example: (2.0 × 10⁻⁴ ft/s)(10 ft)(4)/(8) = 1.0 × 10⁻³ ft³/s per foot of wall.PI = LL − PL. Worked example against a maximum PI of 25: LL 42 − PL 19 = 23 (satisfies); 61 − 30 = 31, 38 − 12 = 26, 55 − 28 = 27 (all exceed 25).Compute on dry weight of soil and compacted volume for one station (100 ft): Volume = 100 ft × width × lift thickness; Dry weight = Volume × dry unit weight; Water (lb) = (optimum w − borrow w) × dry weight; Gallons = lb ÷ 8.33. Worked example: 100 × 36 × 0.667 = 2,400 cf; 2,400 × 115 pcf = 276,000 lb; (0.13 − 0.06) × 276,000 = 19,320 lb; ÷ 8.33 ≈ 2,319 gal. (Using the full 13% instead of the 7% difference wrongly gives 4,307 gal.)Realistic rate = optimum rate × operator ability factor × job efficiency factor × site condition factor. Worked example: 78 LCY/hr × 0.75 × 0.83 × 0.6 = 29.1 ≈ 29 LCY per hour (0.6 covers difficult site conditions such as crosslines). Use 0.75 for an operator of average/unknown ability.Production = (blade width × average speed in mph × 5,280 × job efficiency × operator ability) ÷ number of passes; then hours = area ÷ production. Worked example: (12 × 4 × 5,280 × 0.83 × 0.75) ÷ 5 = 31,553 SF/hr = 3,506 SY/hr; 30,000 SY ÷ 3,506 = ≈ 8.6 hours.Convert both cut and fill to the same soil state before comparing, using the conversion factors for the specific material: Cut (LCY) = BCY × LCY/BCY factor; Fill (LCY) = CCY × LCY/CCY factor; Import = Fill − Cut. Worked example for dry common earth placed at 100% Standard Proctor density (factors 1.32 LCY/BCY and 1.54 LCY/CCY): 4,000 BCY × 1.32 = 5,280 LCY; 4,000 CCY × 1.54 = 6,160 LCY; 6,160 − 5,280 = 880 LCY import.BCF per lin ft = width × depth; LCF per lin ft = BCF × (1 + swell); LCF per set = LCF/ft × set length; cycles per set = LCF per set ÷ bucket load; time per set = (cycles × cycle time) + move time; sets/hr = 3,600 s ÷ time per set; lin ft/hr = sets/hr × set length. Worked example (2 ft × 4 ft trench, loam at 30% swell, 8 LCF bucket, 12-s cycle, 8-ft set, 15-s move): 8 BCF → 10.4 LCF/ft → 83.2 LCF/set → 10.4 cycles → 139.8 s = 2.33 min → 25.75 sets/hr → 206 lin ft/hr.Loose CY = bank CY × (1 + swell); loads = loose CY ÷ truck capacity, rounded up. Worked example at 30% swell: 25.19 BCY × 1.30 = 32.74 LCY; 32.74 ÷ 12 = 2.73 → 3 loads. (Dividing the bank volume by truck size under-counts loads.) Trench length is figured on the outside perimeter: 2 × (40 + 28) = 136 lin ft.Continuous footing length = outside perimeter = 2 × (L + W); volume = length × width × depth ÷ 27 (e.g., 124 × 1.333 × 0.833 = 137.78 cf ÷ 27 = 5.10 cu yd). Pier footing = side × side × depth × number ÷ 27 (e.g., 3 piers at 2.5 × 2.5 × 1 = 18.75 cf ÷ 27 = 0.69 cu yd). 4-in. slab: one cubic yard covers 81 sq ft, so cu yd = area ÷ 81, rounded up to whole yards (960 ÷ 81 = 11.85 → 12 cu yd). Order continuous footings rounded UP to the next quarter yard (5.10 → 5.25 cu yd); order combined net volumes rounded up to the next whole yard (5.10 + 0.69 + 11.85 = 17.65 → 18 cu yd).Form contact area (both faces) = 2 × perimeter × height (2 × 136 × 8 = 2,176 sq ft). 8-in. wall concrete from the printed table = (wall area ÷ 100) × 2.47 cu yd per 100 sq ft (1,088 ÷ 100 = 10.88 × 2.47 = 26.87 cu yd; check 1,088 × 0.667 ÷ 27 = 26.86). 8-in. block: three courses stack 2 ft, so courses = height × 3/2 (4 ft → 6 courses); three blocks lay 4 ft, so blocks per course = length × 3/4 (32 ft → 24 blocks).