Exam Cheat Sheet · Quick Reference
Louisiana Pile Driving
Louisiana · PSI Services Contractor
Louisiana State Portion 50 questions
Key Distinctions
Quality control involves actions taken to control the product so it meets applicable standards, while quality assurance verifies that those controls are in place and working.
The Contractor's Guide to Quality Concrete Construction, Page 132A Type 1 condition arises when actual site conditions differ materially from those indicated in the contract documents, whereas a Type 2 condition arises when actual conditions differ from what would be reasonably expected.
Construction Planning, Equipment, and Methods, Chapter 3 — Earthwork Planning sectionOwnership costs include major repairs and overhauls that extend service life, while operating costs include consumables such as fuel, lubricants, and tires.
Construction Equipment Guide, Chapter 2, Page 80A track excavator yields higher production (50 LCY/hr vs. 29 LCY/hr) but carries significantly higher mobilization costs that can make it uneconomical on short or small jobs.
Pipe and Excavation Contracting, Pages 99-100Shielded or lead-covered conductors must not be bent to a radius less than 12 times the overall diameter, whereas nonshielded conductors require a minimum of 8 times the overall diameter.
NEC 305.5Type MV-90 medium voltage cable has a maximum operating temperature of 90°C, while Type MV-105 has a maximum operating temperature of 105°C; both are suitable for dry or wet locations.
NEC Table 315.10(A)Form ties require a 2:1 safety factor (working load = half of ultimate tensile strength), while form anchors require a minimum safety factor of 3 because they may be loaded while the surrounding concrete is still green.
The Contractor's Guide to Quality Concrete Construction, Page 66Danger signs—featuring a red upper panel, black outline borders, and white lower panel—are used only where an immediate hazard exists, distinguishing them from general warning or caution signage.
OSHA 1926 CFR 29, Page 201Predrilling (setting H-piles in predrilled holes then grouting) provides close control of alignment and location, whereas driving does not offer the same positional precision.
Construction Planning, Equipment, and Methods, Chapter 3 — Soldier Piles and Lagging sectionRegular ground surfaces typically use 100-ft station spacing for cross-sections, while areas with tight curves or rapid topographic changes such as swales and drop-offs often require 25-ft spacing.
Construction Equipment Guide, Chapter 3 - Planning for Earthwork Construction, Volume Calculation / Example 3.2Retarding admixtures delay concrete setting, increase lateral pressure on forms (chemistry coefficient CC = 1.2 vs. 1.0), and require longer form-stripping times compared to mixes without retarders.
The Contractor's Guide to Quality Concrete Construction, Pages 72 and 82Direct-buried cables rated over 1000V AC through 22kV require a minimum cover of 750 mm (30 in.), while cables over 22kV through 40kV installed in rigid metal conduit require only 150 mm (6 in.).
NEC Table 305.15(A)Key Terms
Formulas to Know
V = ((d1 + d2 + d3 + d4) / 4) × A, where d1–d4 = cut or fill depths at four corners, A = prism base areaMax difference = Highest corner elevation − Lowest corner elevationWorking Load = Ultimate Tensile Strength / 2Allowable Load = Ultimate Anchor Load / 3 (minimum safety factor = 3)Camber (in) = (Span in feet / 10) × 0.25Lateral Pressure = f(concrete temperature, rate of placement, unit weight of concrete); higher rate or lower temperature → higher pressure~20% reduction in load-carrying capacity per 0.5 in. misplacement of bars in a 6-in. slab (illustrative ratio, not a standalone algebraic formula)Min radius = 12 × overall diameter (shielded/lead-covered); Min radius = 8 × overall diameter (nonshielded)