Exam Cheat Sheet · Quick Reference
New Jersey Business and Law Exam (Electrical Contractor and Master Plumber)
New Jersey · PSI Services Contractor
New Jersey State Portion 50 questions
Key Distinctions
Addenda are changes made to the bid package/contract documents prior to the contract award (and become part of the contract when awarded), while modifications are changes made after the contract is signed and executed.
NASCLA Contractors Guide, Chapter 7 - Contract ManagementBid shopping is the general contractor approaching subcontractors other than those who submitted bids to seek a lower offer, while bid peddling is a subcontractor approaching the general contractor after the project was awarded to lower the price submitted on bid day.
NASCLA Contractors Guide, Bidding and Estimating chapter — Bid Shopping sectionBid rigging is collusion where contractors coordinate their bids to fix the award outcome of a project, unlike bid shopping (GC seeking lower sub prices after bids) or bid peddling (sub lowering its price after award).
NASCLA Contractors Guide, Bidding and Estimating chapter — Bid Rigging sectionIn arbitration a third-party arbitrator acts as a judge and renders an arbitral award that legally binds all parties, while in mediation an independent third-party mediator only facilitates dialogue and the parties themselves set the terms of any agreement.
NASCLA Contractors Guide, Contract Management chapter — Arbitration sectionCollaborative law involves no neutral mediator or arbitrator; the parties use their own advocates, most often lawyers, to negotiate a mutually beneficial result.
NASCLA Contractors Guide, Contract Management chapter — Alternative Dispute Resolution sectionA material breach is a serious violation (e.g., contractor refuses to perform or owner refuses to pay) that may void the contract and most likely ends in litigation, while an immaterial or partial breach usually does not terminate the contract and the injured party may only sue for the value of the damages suffered.
NASCLA Contractors Guide, Contract Management chapter — Breach of Contract sectionAll-risk covers direct loss by any peril not specifically excluded by the policy (nearly all risks), while named peril has narrower coverage and specifies which perils are covered, such as fire and lightning.
NASCLA Contractors Guide, Managing Risk chapter — Insurance sectionProject overhead includes bonds, temporary storage, temporary office, security guard, utilities, dumpsters and portable toilets (typically 5-10 percent of the total bid), while company overhead includes items such as office rent, accounting fees and legal fees.
NASCLA Contractors Guide, Bidding and Estimating chapter — Add Project Overhead sectionThe quantity take-off method individually estimates units of materials and labor for each task (generally the most accurate), while the unit price method bundles all cost factors — labor, materials, equipment and subcontractors — into a single price for the entire task.
NASCLA Contractors Guide, Bidding and Estimating chapter — Quantity Take-off sectionLeasing requires no down payment, spreads lower payments over a longer period, allows lease payments to be deducted as operating expenses and returns obsolete equipment to the owner, while purchasing usually costs less in the long run and gives ownership/salvage value (leases generally cannot be cancelled).
NASCLA Contractors Guide, Bidding and Estimating chapter — Determining Estimated Costs sectionThey are mutually exclusive remedies — an owner who sues for liquidated damages (the contract's per-day assessment) cannot also sue for actual damages.
NASCLA Contractors Guide, Contract Management chapter — Breach of Contract sectionPer the statutory lien claim form notice, an owner who pays the claimant and obtains a discharge of lien claim loses the right to challenge the lien claim in a court proceeding, whereas an owner who discharges by surety bond or deposit of funds retains that right.
NASCLA Contractors Guide, New Jersey (2nd ed.), Appendix J — N.J.S. 2A:44A-8 (lien claim form notice) and 2A:44A-31Under N.J.S. 2A:44A-2 a first tier lien claimant is a claimant who is a contractor (in direct privity with the owner), a second tier claimant is a subcontractor or supplier in relation to the contractor, and a third tier claimant is a subcontractor or supplier to a second tier claimant; N.J.S. 2A:44A-9(f) gives no lien rights to anyone other than first, second or third tier claimants (so a fourth tier party has none).
NASCLA Contractors Guide, New Jersey (2nd ed.), Appendix J — N.J.S. 2A:44A-2 and 2A:44A-9(f)Key Terms
Formulas to Know
Required Labor Hours per Task × Labor Rate = Labor Cost per TaskPrice per Unit × Number of Units Needed = Total Material Unit CostDirect Costs ÷ (1 − Total Overhead %) ; $100,000 ÷ 0.80 = $125,000Total Yearly Equipment Cost ÷ Estimated Hours of Use per Year = Unit Cost per Hour; Unit Cost per Hour × Project Hours = Project Equipment CostTotal Labor Hours ÷ Hours per Day Available for the Task = Activity Duration in Working DaysPer-Day Liquidated Damages Rate × Number of Unexcused Days LateProject Costs Incurred ÷ Total Estimated Costs = % Complete; % Complete × Contract Amount = Cumulative EarningsNet Pay = Gross Pay − All Taxes and DeductionsProfit Margin = Net Income ÷ RevenuesQuick Ratio = (Current Assets − Inventory) ÷ Current Liabilities(Initial Asset Cost − Salvage Cost) ÷ Useful Life in Years = Yearly Depreciation AmountE − [F + G] = Total Contract Price (initial price + executed amendments/change orders) − (Agreed Upon Credits + Amounts Paid to Date)