Exam Cheat Sheet · Quick Reference
Oklahoma Electrical Business and Law
Oklahoma · PSI Services Contractor
Oklahoma State Portion 50 questions
Key Distinctions
Bid peddling is when a subcontractor approaches the general contractor after award intending to lower its original bid-day price, while bid shopping is when the general contractor seeks lower bids from other subcontractors.
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Bid Peddling section (Page 6-2)Arbitration uses a third-party arbitrator acting as a judge whose arbitral award legally binds all parties, while a mediator only facilitates dialogue and does not impose a binding decision (the parties set the terms).
NASCLA Contractors Guide (14th ed.), Chapter 7 — ArbitrationNamed peril policies are narrower and cover only the perils specifically listed (typically fire and lightning, sometimes wind, explosion, water damage, terrorism, earthquake), while all-risk covers all perils not specifically excluded.
NASCLA Contractors Guide (14th ed.), Chapter 3 – Named Peril Builder's Risk Insurance sectionA bank letter of credit is not a bond but a cash guarantee to the owner (convertible to a payment) that is not a guarantee of performance and customarily covers only 5 to 10 percent of the contract, not 100 percent.
NASCLA Contractors Guide (14th ed.), Chapter 3 – Bond Language sectionMaintenance bonds often use 10 percent of construction cost as the required bond amount, while performance bonds are usually set at 100 percent of the contracted price.
NASCLA Contractors Guide (14th ed.), Chapter 3 (Managing Risk) — Bond Language sectionCompany overhead is the cost of doing business that cannot be linked to a specific project (office rent, accounting and legal fees, taxes, telephone, administrative labor), while project overhead is project-specific (bonds, temporary storage/office, security, utilities, dumpsters, portable toilets).
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Add Company Overhead section (Page 6-6)On the income statement, direct costs are those directly linked with a particular project (materials, subcontractor fees, permit fees, labor), while operating expenses are indirect items such as office salaries, advertising, and warehouse rental.
NASCLA Contractors Guide (14th ed.), Chapter 2 — Income Statement sectionSmall tools and pickup trucks are considered an indirect cost figured into project overhead rather than listed as direct project equipment in the estimate.
NASCLA Contractors Guide, Bidding and Estimating chapter — Determining Estimated Costs sectionThe accrual method recognizes income when the services occur and records expenses when incurred, not when money is collected or bills are paid; most construction businesses use the accrual method.
NASCLA Contractors Guide (14th ed.), Chapter 14 — Accrual Method sectionCPM graphically illustrates the interdependent relationships between tasks, while calendar and bar chart methods do not show interdependencies or the impact a delayed task has on other tasks (calendar scheduling's advantage is linking tasks to specific dates).
NASCLA Contractors Guide (14th ed.), Chapter 8 — Critical Path Method sectionFree float is the time an activity can be delayed without impacting the early start of the next activity, while total float is the leeway allowed without delaying the overall project completion date (contingency time is a buffer between tasks for unforeseen delays).
NASCLA Contractors Guide (14th ed.), Chapter 8 — Float Time sectionThe superintendent is the onsite supervisor over all daily operations (coordinating activities, tracking schedule/cost deviations, punch lists, records), while the foreman supervises specific areas by trade such as rough carpentry or concrete installation; certifying progress payments belongs to the architect/engineer, not either one.
NASCLA Contractors Guide (14th ed.), Chapter 8 — Foreman sectionWhen specifications and codes conflict, the contractor must follow the stricter of the two because codes are the minimum requirements by law.
NASCLA Contractors Guide (14th ed.), Chapter 6, Specifications paragraph, Bidding and Estimating chapter — Project Documents section (Page 48)The S corporation entity is liable for employment taxes (Social Security, Medicare, income tax withholding, and FUTA), while income tax flows through to shareholders on Form 1040/Schedule E and self-employment and estimated tax (Form 1040-ES) are individual responsibilities.
NASCLA Contractors Guide, Tax Basics chapter — Summary of Federal Tax Forms sectionKey Terms
Formulas to Know
Required Labor Hours per Task × Labor Rate = Labor Cost per Task (consider skill level, crew size, weather when setting hours)Price per Unit × Number of Units Needed = Total Material Unit Cost (add a small waste contingency that varies by material type and job specs)Overhead costs from prior year ÷ Revenues = Overhead % (e.g., $220,000 ÷ $2,000,000 = 11% company; $160,000 ÷ $2,000,000 = 8% project); company overhead averages 5%–20%, project overhead typically 5%–10% of the total bidBid Price = Direct Costs ÷ (1 − combined overhead %); e.g., 9% + 11% = 20% → $100,000 ÷ 0.80 = $125,000; 10% + 15% = 25% → $90,000 ÷ 0.75 = $120,000Project Costs Incurred ÷ Total Estimated Costs = % Complete; % Complete × Contract Amount = Cumulative Earnings (e.g., $300,000 ÷ $1,000,000 = 30%; 30% × $1,500,000 = $450,000)(Initial Asset Cost − Salvage Cost) ÷ Useful Life Years = Yearly Depreciation (e.g., ($80,000 − $5,000) ÷ 5 = $15,000)Total yearly equipment cost (depreciation, maintenance, insurance, taxes, operating) ÷ Estimated hours of use per year = Unit cost per hour (e.g., $12,000 ÷ 600 = $20/hr)Revenues ÷ 365 = Sales per Day; Accounts Receivable ÷ Sales per Day = Average Collection Period (e.g., $730,000 ÷ 365 = $2,000; $60,000 ÷ $2,000 = 30 days)Net Income ÷ Revenues = Profit Margin (e.g., $40,000 ÷ $500,000 = 8.0%)Total Labor Hours ÷ Hours per Day Available for the Task = Activity Duration (e.g., 16 hrs ÷ 4 hrs/day = 4 working days)