Exam Cheat Sheet · Quick Reference

Oklahoma HVACR Journeyman Unlimited

Oklahoma  ·  PSI Services Contractor

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
70
Passing score
70%
Exam time
180 min
Administered by
PSI Services Contractor
Format
Reference materials allowed

Oklahoma State Portion 70 questions

Electrical Knowledge and Controls 15 Q · 21%
Reading and interpreting pictorial and ladder wiring diagramsOhm's law, Watt's law, and basic circuit calculationsSeries, parallel, and series-parallel circuit fundamentalsSingle-phase and three-phase AC motor types and starting methodsMotor starting relays: current, potential, solid-state, and PTC typesMotor protection devices: fuses, circuit breakers, and bimetal devicesTemperature and pressure motor controls: range and differential adjustmentElectrical test equipment: voltmeters, ohmmeters, ammeters, and multimetersControl transformers and 24-volt control circuits
Natural Gas 10 Q · 14%
Gas piping materials, fittings, and approved pipe types (steel, copper, CSST, polyethylene)Gas piping sizing methods (longest length, branch length, hybrid pressure) and capacity tablesGas piping pressure requirements, testing, and leak checkingCombustion air requirements for gas appliances (indoor, outdoor, and combined methods)Venting systems for gas appliances (Type B, single-wall, chimney, direct-vent) and vent sizingGas furnace components and operation (burners, gas valves, ignition systems, safety controls)Combustion fundamentals (air-fuel ratio, complete/incomplete combustion, flue gas analysis)Appliance installation requirements, clearances, and prohibited locations
Air Distribution Systems 16 Q · 23%
Duct system types and configurations (radial, extended plenum, reducing trunk, perimeter loop, SDHV)Duct construction materials and joining methods (metallic, fiberglass, flexible, ductboard)Duct sizing principles and procedures (aspect ratio, friction rate, ACCA Manual D)Registers, diffusers, grilles, and dampers (types, placement, airflow control)Duct sealing, insulation, and leakage testing (mastic, metal tape, blower door, duct blaster)Ventilation requirements and air changes per hour calculationsFans and air movement measurement (anemometers, pitot tubes, flow hoods, manometers)Indoor air quality and exhaust system requirements per IMC Chapter 5 and Chapter 6
Refrigeration and Air Conditioning Systems 16 Q · 23%
Compression refrigeration cycle components and operationCompressor types and configurations (reciprocating, rotary, scroll, screw, centrifugal)Metering devices (capillary tube, TXV, AXV, EEV, fixed orifice)Evaporator and condenser types, construction, and defrost methodsRefrigerant classification, properties, and environmental regulations (ODP, GWP, Clean Air Act)Refrigerant handling procedures (recovery, evacuation, charging, superheat and subcooling checks)Refrigerant flow components (filter-driers, receivers, check valves, solenoid valves, pressure-regulating valves)Heat pump operation, reversing valves, and system configurations
Heating Systems 10 Q · 14%
Gas-fired heating systems: combustion, gas valves, burners, and ignition systemsOil-fired heating systems: fuel oil properties, oil burners, combustion efficiency testing, and fuel delivery systemsHydronic heating system components: boilers, circulating pumps, expansion tanks, and terminal unitsElectric heating systems: resistance elements, electric furnaces, duct heaters, and baseboard unitsForced-air furnace types and heat exchanger operationHeating and cooling load calculations: heat loss, R-values, U-values, and design temperaturesVenting and chimney requirements for heating appliances per IFGC and IMCHeating system controls: thermostats, aquastats, safety controls, and zone controls
Safety 3 Q · 4%
Lockout/tagout (LOTO) procedures for electrical safetyFire hazard identification and fire extinguisher use (P.A.S.S. method and fire classes)Refrigerant cylinder handling, storage, and pressure hazardsPersonal protective equipment (PPE) selection and useSafety Data Sheets (SDS) and Globally Harmonized System (GHS) chemical labelingBreathing hazards and respiratory protection (air-purifying vs. supplied-air respirators)Ladder, scaffolding, and fall protection safe work practicesOSHA regulations, hazard assessment, and safety certifications

Key Distinctions

Pictorial wiring diagramvsLadder wiring diagram

A pictorial diagram shows all connections plus the approximate physical location of devices in the unit (and often wire colors), while a ladder diagram shows the order of component operation as horizontal rungs (individual circuits with controls and loads) between two vertical power-supply lines, with devices near the top energized first.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 18 - Electrical Troubleshooting Fundamentals, Page 369 (Section 18.2.2) (20th ed.: Chapter 16, Section 16.1.1)
ContactorvsMotor starter

Both use electromagnetic coils and can be rebuilt, but the motor starter's distinguishing feature is built-in overload protection that prevents motors from burning out or overheating.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 341 ("Contactors and Motor Starters") (20th ed.: Chapter 16, Section 16.3.5 — Contactors and Motor Starters)
Weight-operated current relayvsRotary-solenoid current relay

A weight-operated current relay must be mounted in a level position, whereas a current relay using a rotary solenoid can be mounted in any position.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 338 ("Current Relays") (20th ed.: Chapter 16, Section 16.3.5 — Current Relays)
Solid-state relay (SSR)vsElectromagnetic relay

An SSR switches circuits with electronic components (transistors, SCRs, triacs) and has no physical movement of mechanical parts, and is typically used to start single-phase motors; electromagnetic relays switch mechanically.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 345 ("Solid-State Relays") (20th ed.: Chapter 16, Section 16.3.5 — Solid-State Relays)
Hard lockoutvsSoft lockout

A hard lockout shuts the system down for an unspecified time after a failed trial for ignition and requires a service call or power interruption to reset, while a soft lockout automatically retries after a waiting period.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 33 - Gas-Fired Heating Systems, Page 770 (20th ed.: Page 1129)
Building-related illness (BRI)vsSick building syndrome (SBS)

BRI is a specifically diagnosable illness caused by airborne agents whose symptoms do NOT disappear when the occupant leaves the building, while SBS has no specific cause or identifiable illness and its symptoms disappear when occupants leave.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 29 - Air Quality, Page 647 (20th ed.: Page 730)
K-value (thermal conductivity)vsC-value (thermal conductance)

K-value is heat passing through one square foot of material one inch thick in one hour per 1°F difference (Btu·in/hr·ft²·°F), while C-value is based on the material's actual measured thickness rather than a standardized 1-inch thickness.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 32 - Heating and Cooling Loads, Page 717 (20th ed.: Page 986)
Subcooling charging methodvsSuperheat charging method

The subcooling method is used to check charge on systems with thermostatic expansion valves (low subcooling suggests undercharge, high suggests overcharge), while the superheat method is used on fixed-orifice systems such as capillary tubes.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 12 - Working with Refrigerants, Page 221 (20th ed.: Page 236)
Range adjustment (low-pressure motor control)vsDifferential adjustment (low-pressure motor control)

Turning the range screw clockwise raises both cut-in and cut-out an equal amount (differential unchanged), while the differential adjustment turned clockwise raises only the cut-out pressure and does not affect cut-in.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 333 (Section 17.4.4) (20th ed.: Chapter 16, Section 16.3.4 — Low-Pressure Motor Controls)
Three-phase motors/powervsSingle-phase motors/power

Three-phase supply is already phase-split so the motor develops starting torque without start windings or capacitors, and delivers constant power because there is never an instant when all voltages are zero; single-phase motors need start components.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 16 - Electric Motors, Page 308 (Section 16.2.2) (20th ed.: Chapter 15, Section 15.2.2)
Hot-surface igniter (glow coil)vsFlame rod

In an HSI system the glow coil only ignites and cannot sense flame; a separate flame rod performs flame rectification sensing, and if it is dirty or oxidized the module closes the gas valve seconds after ignition (HSI systems use no thermocouple).

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 33 - Gas-Fired Heating Systems, Page 765 (20th ed.: Pages 1126-1128 (Sections 41.5.4 and 41.6.1))
Liquid line connection for recoveryvsDischarge service valve connection for recovery

Recovering at the liquid line takes refrigerant as subcooled liquid (after the condenser), which speeds recovery, while the discharge service valve delivers superheated high-pressure vapor, making recovery slower and less efficient.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 50 - Servicing Commercial Systems, Page 1233 (20th ed.: Page 1500)
Radial duct systemvsPerimeter loop duct system

A radial system runs individual branch ducts directly from the central plenum to each outlet with no trunk line, while a perimeter loop system (used with downflow furnaces in slab homes without basements) has branches feeding a perimeter duct cast in the slab.

Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 30 - Air Distribution, Page 672 (20th ed.: Page 755)
ACCA Manual DvsACCA Manual J / Manual S

Per IMC 603.2, Manual D is an accepted duct-sizing method for a single dwelling unit (along with manufacturer's instructions or other approved methods); Manual J is for load calculations and Manual S is for equipment selection, and the ASHRAE Handbook of Fundamentals is required for buildings other than single dwelling units.

IMC 2024 Section 603.2

Key Terms

Velocity pressure Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 28 - Air Movement and Measurement, Page 630 (20th ed.: Page 710)
The difference between total air pressure and static air pressure measured by a pitot tube (total pressure = static pressure + velocity pressure).
PTC relay Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 346 (Section 17.5) (20th ed.: Chapter 16, Section 16.3.5 — Positive Temperature Coefficient Relays)
A start device wired in parallel with the run capacitor of a PSC motor that has low resistance (3–12 Ω) when cool so current takes that path, then heats to 10 kΩ–20 kΩ and forces current through the run capacitor.
Potential relay Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 339 ("Potential Relays") (20th ed.: Chapter 16, Section 16.3.5 — Potential Relays)
A motor start relay that actuates on the counter electromotive force (cemf) induced in the start winding, energizing at about three-fourths of rated speed to open its normally closed contacts and drop the start capacitor out.
Current relay (L, M, S terminals) Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 339 (Section 17.4.5) (20th ed.: Chapter 16, Section 16.3.5 — Current Relays)
A start relay with terminals L (line voltage), M (main/run winding) and S (start winding), having a normally open contact between L and S and the relay coil between L and M; falling run-winding current as the motor accelerates weakens the coil and opens the start contacts.
High-pressure motor control Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 334 ("High-Pressure Motor Controls") (20th ed.: Chapter 16, Section 16.3.4 — High-Pressure Motor Controls)
A safety control usually set to cut out at 20% above normal head pressure to protect the compressor from high pressure/temperature and the motor from overheating and overloading.
Multipurpose fuse Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 347 (Section 17.5.1) (20th ed.: Chapter 16, Section 16.4.1)
A fuse combining fast-acting and time-delay characteristics: it will not blow on small short-duration overloads such as motor starting, but blows immediately on overloads over 500% of its maximum current rating.
Current-limiting fuse Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 347 (Section 17.5.1) (20th ed.: Chapter 16, Section 16.4.1)
A fuse using temperature-sensitive resistors that open when current exceeds the limit and the fuse heats up, then close again when cooled, preventing motor current from exceeding rated locked rotor amperage.
Internal bimetal overload protection device Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 17 - Electrical Control Systems, Page 348 (Section 17.5.3) (20th ed.: Chapter 16, Section 16.4.3)
A protector located inside the compressor on or in the motor windings whose bimetal disc bends open on excess current or heat and re-closes when cooled, producing off-and-on compressor cycling.
Refrigerant distributor Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 45 - Commercial Metering Devices and Valves, Page 1088 (Section 45.1.4) (20th ed.: Pages 490-491)
A device at the metering device outlet that splits refrigerant into several shorter parallel evaporator circuits, reducing pressure drop across the evaporator and giving more consistent coil temperature.
Sequencer (electric furnace) Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 35 - Electric Heating Systems, Page 834 (20th ed.: Pages 1196 and 1205)
A device that closes and opens contacts on a time delay (typically about 30 seconds apart) to energize heating elements one after another and minimize initial current draw.
Crankcase heater Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 43 - Commercial Compressors, Page 1045 (Section 43.1) (20th ed.: Page 467)
An electric heating element on or in a compressor that warms it during the Off cycle to prevent refrigerant from condensing into liquid in the crankcase, avoiding liquid slugging or flooded starts.
Overfiring Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 34 - Oil-Fired Heating Systems, Page 795 (Section 34.3.2) (20th ed.: Page 1154)
A condition where a heating system produces too much heat, often from installing a higher-capacity burner nozzle than original, so excess heat escapes up the flue and stack temperature is high.
Draft (flue) Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 34 - Oil-Fired Heating Systems, Page 796 (20th ed.: Page 1155)
The movement of flue gas; a draft test with a draft gauge measures flue air pressure in inches of water column, indicating how quickly combustion gases pass through the heat exchanger.
Category IV furnace Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 33 - Gas-Fired Heating Systems, Page 776 (20th ed.: Page 1134)
A positive-pressure venting, condensing furnace with flue gas temperature below 140°F (60°C) — below its dew point — using a secondary heat exchanger and PVC vent piping.
Refrigerant quality Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 51 - Understanding Heat Loads and System Thermodynamics, Page 1273 (20th ed.: Page 1372)
On a pressure-enthalpy diagram, the fraction of refrigerant mass in the vapor state; 10% quality means 10% vapor and 90% liquid.
Duct pressure classification (IMC 603.3) IMC 2024 Section 603.3
Ducts are classified by maximum operating pressure at positive or negative 0.5, 1.0, 2.0, 3.0, 4.0, 6.0, or 10.0 inches of water column.
cfm50 / ACH50 (blower door test) Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 31 - Ventilation System Service, Page 702 (20th ed.: Page 791)
cfm50 is the measured airflow through the blower door fan with indoor pressure held at −50 Pa with respect to outdoors, and it is used to calculate ACH50, the air changes per hour at that pressure difference.
cfm25 (duct leakage test) Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 31 - Ventilation System Service, Page 703 (20th ed.: Page 792)
The airflow needed to hold sealed ductwork at +25 Pa with respect to the conditioned space; leakage limits are 3 cfm per 100 ft² if tested before the air handler is installed and 4 cfm per 100 ft² with it installed.
Panned joist space Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 30 - Air Distribution, Page 672 (20th ed.: Page 755)
A basement return-air branch duct construction method that uses the joists and floorboards as three sides of the duct.
Small duct, high-velocity (SDHV) system Modern Refrigeration and Air Conditioning (22nd ed.), Chapter 30 - Air Distribution, Page 666 (20th ed.: Page 748)
An air distribution system using small-diameter ducts at high velocity, with supply air to the building's inside perimeter and return air from the center of the building.

Formulas to Know

Ohm's law (resistance and current)R = E ÷ I and I = E ÷ R; e.g., 240 V ÷ 10 A = 24 Ω; 24 V ÷ 8 Ω = 3 A (in a series circuit the same current flows through every load); 120 V ÷ 24 Ω = 5 A; 120 V ÷ 25 A = 4.8 Ω.
Watt's law (single-phase power)P = I × E; e.g., 20 A × 120 V = 2400 W; 15 A × 240 V = 3600 W; 8 A × 240 V = 1920 W; 4 A × 120 V = 480 W; 1 A × 1 V = 1 W.
Control differentialDifferential = difference between cut-out and cut-in (always subtract the lower value from the higher): heating = cut-out − cut-in, e.g., 74°F − 68°F = 6°F; cooling = cut-in − cut-out, e.g., 25°F − 15°F = 10°F.
SubcoolingSubcooling = condensing (boiling) temperature at operating pressure − actual measured liquid temperature; e.g., 212°F − 190°F = 22°F.
Air velocity from velocity pressure (pitot tube)V = 4005 × √Pv (Pv in inches of water); e.g., 4005 × √0.25 = 4005 × 0.5 ≈ 2003 ft/min.
Swinging-vane anemometer temperature correction (calibrated at 68°F)Actual velocity = instrument reading × √[(460 + T) ÷ (460 + 68)], where T is actual duct temperature in °F.
Air changes per hourACH = (airflow in cfm × 60 min) ÷ room volume in ft³; blower door: ACH50 = (cfm50 × 60) ÷ conditioned volume, e.g., (1,500 × 60) ÷ 12,000 = 7.5.
Electric heat kW ↔ Btu/hr1 kW = 3,413 Btu/hr; kW required = Btu/hr ÷ 3,413, e.g., 50,000 ÷ 3,413 = 14.65 kW.
Coefficient of performance (COP) from a P-H diagramCOP = refrigeration effect ÷ heat of compression = (compressor-in enthalpy − evaporator-in enthalpy) ÷ (compressor-out − compressor-in); e.g., (179 − 116) ÷ (198 − 179) = 63 ÷ 19 = 3.32:1.
Duct design friction rate and total effective lengthTEL = longest supply run effective length + longest return run effective length (e.g., 180 ft + 120 ft = 300 ft); Friction rate = (ASP ÷ TEL) × 100, e.g., (0.20 in. WC ÷ 250 ft) × 100 = 0.08 in. WC per 100 ft; equivalent length of a run = straight measured length + elbow allowances (65 ft + 2 × 25 ft = 115 ft); keep velocity at or below 700 fpm to avoid excessive noise.