Exam Cheat Sheet · Quick Reference
Oklahoma Mechanical Business and Law
Oklahoma · PSI Services Contractor
Oklahoma State Portion 50 questions
Key Distinctions
Company overhead is the cost of doing business that cannot be directly linked to a specific project (office rent, accounting fees, taxes, telephone, legal fees, administrative labor), while project overhead covers project-specific items like bonds, temporary storage/office, security, utilities, dumpsters, and portable toilets.
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Add Company Overhead section (Page 6-6)Bid peddling is a subcontractor approaching the general contractor after award to lower its original bid-day price, while bid shopping is the general contractor seeking lower bids from other subcontractors after original bids are submitted.
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Bid Peddling section (Page 6-2)In arbitration a third-party arbitrator acts as a judge and issues an arbitral award that legally binds all parties, while a mediator only facilitates dialogue and the parties set the terms with no binding decision.
NASCLA Contractors Guide (14th ed.), Chapter 7 — ArbitrationUnder the accrual method (used by most construction businesses) income is recognized when services occur and expenses when incurred, rather than when money is collected or paid.
NASCLA Contractors Guide (14th ed.), Chapter 14 — Accrual Method sectionNamed peril policies have narrower coverage and list only the perils covered (e.g., fire and lightning), while all-risk policies cover all perils not specifically excluded.
NASCLA Contractors Guide (14th ed.), Chapter 3 – Named Peril Builder's Risk Insurance sectionA bank letter of credit is not a bond but a cash guarantee to the owner (not a guarantee of performance) customarily covering only 5 to 10 percent of the contract, whereas performance bonds are usually set at 100 percent of the contracted price.
NASCLA Contractors Guide (14th ed.), Chapter 3 – Bond Language sectionOn the income statement, direct costs are directly linked to a particular project (materials, subcontractor fees, permit fees, labor), while office salaries, advertising, and warehouse rental are operating/indirect expenses.
NASCLA Contractors Guide (14th ed.), Chapter 2 — Income Statement sectionCPM graphically illustrates interdependent relationships between tasks, while calendar and bar chart methods share the weakness of not showing activity interdependencies or delay impacts.
NASCLA Contractors Guide (14th ed.), Chapter 8 — Critical Path Method sectionFree float is the time an activity can be delayed without impacting the early start of the next activity, while total float is the leeway available without delaying the overall project completion date.
NASCLA Contractors Guide (14th ed.), Chapter 8 — Float Time sectionCost-plus progress payments are based on actual costs incurred plus a proportionate markup with reconciliation once actual costs are known, while a unit-price contract pays a calculated price per unit according to the actual quantities used when the extent of work cannot be determined in advance.
NASCLA Contractors Guide (14th ed.), Chapter 13 — Payment for Cost-Plus Contracts sectionThe square-foot method multiplies project square footage by a unit cost for a quick early estimate but ignores project specifics, while the unit price method bundles labor, materials, equipment, and subcontractors into a single unit price for an entire task.
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Other Methods of Estimating section (Page 6-7)A conceptual estimate is generally prepared by the architect using cost models from previous projects, while a preliminary estimate is the risky practice of quoting a price to a customer before accurate calculations are made.
NASCLA Contractors Guide (14th ed.), Bidding and Estimating chapter — Other Methods of Estimating section (Page 6-7)A material breach is a serious contract violation (such as an owner refusing to pay for completed work) that may void the contract and end in litigation with monetary damages, while liquidated damages are a contractually specified per-day assessment for late completion, and an owner suing for liquidated damages cannot also sue for actual damages.
NASCLA Contractors Guide (14th ed.), Chapter 7 — Breach of ContractKey Terms
Formulas to Know
Required Labor Hours per Task × Labor Rate = Labor Cost per Task (hours spent planning and scheduling must also be figured into this equation)Price per Unit × Number of Units Needed = Total Material Unit Cost (add a small waste contingency that varies by material type and job specifications)Total Yearly Equipment Cost ÷ Estimated Hours of Use per Year = Unit Cost per Hour (e.g., $12,000 ÷ 600 = $20/hr)Unit Cost per Hour × Hours Used on Project (e.g., $30,000 ÷ 1,000 hrs = $30/hr; $30 × 60 hrs = $1,800)Direct Costs ÷ (1 − Total Overhead %) = Bid Price before profit markup (e.g., 20% total overhead: $200,000 ÷ 0.80 = $250,000; $100,000 ÷ 0.80 = $125,000)Total Overhead Costs from Previous Year (income statement administrative expenses) ÷ Revenues (income statement); overhead percentages generally average 5%–20%Apply markup (standard industry markup is 15 percent, considering market and competition) to direct costs — labor, material, project equipment, project overhead, and subcontractorsPer-Day Rate × Number of Days Late = Total Liquidated Damages (e.g., $400 × 30 = $12,000; $500 × 20 = $10,000)Project Costs Incurred ÷ Total Estimated Costs = % Complete; % Complete × Contract Amount = Cumulative Earnings (e.g., $300,000 ÷ $1,000,000 = 30%; 30% × $1,500,000 = $450,000)Current Assets − Current Liabilities = Working Capital (e.g., $26,400 − $8,200 = $18,200; dividing instead gives the liquidity ratio)Gross Pay − (all taxes and deductions) = Net Pay (e.g., $3,200 − $884.80 = $2,315.20)Total Labor Hours ÷ Hours per Day Available for the Task = Working Days (e.g., 16 ÷ 4 = 4 working days)