Exam Cheat Sheet · Quick Reference
Oklahoma Process Piping Journeyman
Oklahoma · PSI Services Contractor
Oklahoma State Portion 35 questions
Key Distinctions
Soft temper Type K has thick walls recommended for underground lines carrying water, oil or gas (adequate to withstand backfill damage), while Type M is the lightest wall tube intended for soldered fittings only in vents, waste lines, interior drainage and other non-pressure uses.
Pipefitters Dictionary, Dimensions of Type L Copper Tube sectionStandard Weight matches Schedule 40 only from ⅛ through 10 inches (12–24 in. wall constant at 0.375 in.), while Extra Strong matches Schedule 80 only from ⅛ through 8 inches (10–24 in. wall constant at 0.500 in.).
Pipefitters Dictionary, Dimensions of Schedule 40 Steel and Wrought Iron Pipe — NotesShort radius elbows have a centerline radius equal to nominal diameter × 1.0, whereas long radius elbows have a centerline radius of nominal diameter × 1½.
Pipe Fitters Handbook, Page 2-40Steel globe and angle valves — butt welding ends and all flanged face types/pressure ratings including ring joint at 1500 psi — are tabulated as face-to-face '2 × A,' while gate valves and swing check valves with butt welding ends use the single 'Dimension A.'
Pipefitter's Handbook (3rd ed.), Chapter 1 (Full Text), Laying Lengths of Steel Globe and Angle Valves With Butt Welding EndsA damaged disc-stem joint is remedied by replacing the disc or stem, whereas seat damage requires replacing the valve and deposits under the disc require washing or cleaning.
Pipefitter's Handbook (3rd ed.), Chapter 1 (Full Text), Trouble Shooting Methods — Globe Valves, Page 5-10Horizontal run spacing values are based on stress, while sloping run values are based on gradient.
Spacing of Pipe Supports for Lines Carrying Water table notesTabulated (Schedule 40 butyrate/ABS) spans must be decreased 50% for polyethylene but may be increased 20% for Schedule 80 ABS; insulated lines of plastic pipe other than PVC — and insulated PVC — are reduced 30%.
Pipe Fitters Handbook, Recommended Support Spacing for Plastic Pipe Other Than PVC sectionPVC Type I has the highest tensile strength of all thermoplastic pipe (7,000 psi), excellent chemical resistance and a 160°F maximum temperature, while Type I polyethylene is limited to 120°F, has the highest coefficient of expansion (9.4 × 10⁻⁵ in/in/°F) and comes in coils up to 400 ft through 3 in. OD.
Pipefitters Dictionary, Characteristics of Pipe Plastics and Relative Physical Properties tablesPVC Type I is rated satisfactory (S) for 75% sulfuric acid and for hydrochloric acid in both cold and hot service; for 75% sulfuric acid ABS, butyrate and polyethylene have unsatisfactory or limited ratings.
Pipe Fitters Handbook, Chemical Resistance Comparison Chart — ThermoplasticsOne U.S. gallon equals 231 cubic inches; 277.3 cubic inches is the Imperial gallon.
Pipefitters Dictionary, Conversion Factors tableSmaller steel pipe is usually designated by its inside diameter, but over 14 inches the nominal size is the outside diameter and the pipe is termed O.D.
Pipefitters Dictionary, Page 5-87 (O.D. Pipe entry)Tangent is the opposite side divided by the adjacent side, while cosine is the adjacent side divided by the hypotenuse.
Pipefitters Dictionary, Solving Problems by Trigonometry sectionThe water-line support spacing data (average conditions) includes allowance for insulation but does not include allowance for flanges, fittings and valves, which such as valves should always be located close to supports.
Pipe Fitters Handbook, Spacing of Pipe Supports for Lines Carrying Water sectionKey Terms
Formulas to Know
Length of Arc = Number of Degrees × 0.01745 × RadiusSetback = Radius × factor; 22½° = 0.199, 30° = 0.268, 45° = 0.414, 60° = 0.577, 72° = 0.727, 120° = 1.732, 135° = 2.41, 150° = 3.73Length of Bend = Radius × factor; 120° = 2.09, 135° = 2.36, 150° = 2.62, 180° = 3.14 (a 180° bend is regarded as two 90° bends)Travel = Offset × (15° = 3.8637, 22½° = 2.6131, 30° = 2.0000, 45° = 1.4142, 60° = 1.1547, 72° = 1.0515); Run = Offset × (45° = 1.000, 60° = 0.5774) — e.g., 60° offset of 12 in.: Run = 12 × 0.5774 = 6.93 in.Nipple = (Offset × 1.414) − laying length of each fitting; e.g., 6 in. offset: 6 × 1.414 = 8½ in. center-to-center, minus 1 in. per elbow = 6½ in.Expansion = (table value at operating temp − table value at install temp) × (Length ÷ 100); e.g., steel 400°F (3.245) − 60°F (0.449) = 2.796 in./100 ft × 5.0 = 13.98 in. for 500 ftEach joint = total turn angle ÷ 2 joints; each piece is mitered at half the joint angle — e.g., 3-piece 45° turn: 45/2 = 22½° joints, cut each piece at 11¼°A = Radius of turn × factor; 3-piece 60° = .2679 (tan 15°), 3-piece 90° = .4142, 3-piece 45° = .1989Schedule 80 ABS = table × 1.20 (e.g., 2 in. at 70°F: 5.0 × 1.20 = 6.0 ft); polyethylene = table × 0.50 (e.g., 1 in.: 3.5 × 0.50 = 1.75 ft); insulated lines (PVC and other plastics) = reduce span 30%Threaded PVC operating pressure ≈ 55% of plain-end table value; minimum PVC bend radius on a grooved bending form = 5 × pipe diameter without flattening