Exam Cheat Sheet · Quick Reference
Oklahoma Residential Journeyman Plumbing and Natural Gas
Oklahoma · PSI Services Contractor
Oklahoma State Portion 85 questions
Key Distinctions
Atmospheric vacuum breaker requires critical level not less than 6 inches above downstream piping/flood level rim, while pressure vacuum breaker requires not less than 12 inches.
IRC 2018, Section P2902.3.2, Page 632Center-to-center lengths are equal for equal-spaced assemblies regardless of fitting type, but end-to-end lengths differ when different fitting types (e.g., 90° vs. 45° ell) are used because fitting allowances differ.
Mathematics For Plumbers And Pipefitters, Chapter 1 — Equal SpacingVertical wet venting runs the wet-vented section through a vertical stack, while horizontal wet venting runs it along a horizontal branch drain.
International Residential Code, Appendix N, Figure N4, Pages 896A circuit vent is a single vent serving multiple fixtures on a horizontal branch drain, whereas an individual vent serves only one fixture.
International Residential Code, Appendix N, Figure N7, Page 898General water supply pipe and fittings may contain up to 8% lead, but pipe and fittings used for drinking or cooking water are restricted to a weighted average of 0.25% lead or less.
International Residential Code, Page 651, Section P2906.2For No-Hub cast iron, the 'D' measurement (center-to-end of fitting to pipe coupling end) is used directly for fitting allowance calculation, while threaded fittings require an additional thread-in measurement to be subtracted.
Mathematics For Plumbers And Pipefitters, Cast Iron Assemblies with Various Bends sectionIn the standard position, rise equals the offset and setback equals 1.414 × offset; in the alternate position, rise equals 1.414 × offset and setback equals the offset.
Mathematics For Plumbers And Pipefitters, Chapter 2 — Combination OffsetsCopper or copper-alloy pipe requires hangers at maximum 12-foot horizontal intervals, while copper tubing 1¼ inches and smaller requires support at maximum 6-foot horizontal intervals.
IRC Table P2605.1 / IPC Table 308.5When the building sewer is constructed of approved materials (Table P3002.1(2)), standard separation applies; when NOT of approved materials, at least 5 feet of undisturbed or compacted earth horizontal separation is required.
IRC P2906.4.1 / IPC 603.2A standard hose bibb subject to freezing requires an accessible stop-and-waste valve inside the building, but a frostproof hose bibb whose stem extends through building insulation into an open heated or semiconditioned space is exempt from this requirement.
IRC P2903.10In a parallel manifold system where developed length is 60 feet or less and available pressure is at least 40 psi, individual distribution lines may be as small as ⅜ inch diameter, which is smaller than typical standard sizing requirements.
IRC P2903.8.2Excavations in Type C soil (e.g., submerged or freely seeping soil) always require a protective system when 5 feet or more deep, while excavations made entirely in stable rock are exempt from protective system requirements regardless of depth.
29 CFR 1926, Subpart P, §1926.652(a)(1) and Appendix AKey Terms
Formulas to Know
E-E = Center-to-Center − (Fitting Allowance₁ + Fitting Allowance₂)E-E = Center-to-Center − (D₁ + D₂) [where D = center-to-end of each fitting]Rise = 1.414 × OffsetDiagonal = 2 × OffsetSetback = 1.414 × OffsetFe = (T₁/L₁) + (T₂/L₂) + … + (Tₙ/Lₙ) [Fe > 1 means overexposure]