Exam Cheat Sheet · Quick Reference
South Carolina Concrete
South Carolina · PSI Services Contractor
South Carolina State Portion 50 questions
Key Distinctions
Quality control is the action/documentation taken to control the product so applicable standards and contract documents are followed, while quality assurance is the action/documentation verifying that those controls are in place and working in accordance with applicable standards.
The Contractor's Guide to Quality Concrete Construction, Page 132For applying ACI 347R lateral pressure formulas, a column is a vertical element with no plan dimension larger than 6.5 ft (2 m), whereas a wall has at least one plan dimension exceeding 6.5 ft (2 m); the classification determines which pressure equation applies.
Contractor's Guide to Quality Concrete Construction (4th ed.), ACI 347R, Table 5.2 (Book Page 71)Per SP-4 Section 4.3.5, tabulated effective section modulus KS must be used for all bending stress calculations, while moment of inertia I is used only for deflection calculations (effective I ÷ distance to extreme fiber does not equal effective KS for plywood).
ACI SP-4 Formwork for Concrete (8th ed.), Section 4.3.5In the SP-4 Chapter 3 bridge planning example, pier shaft forms are assumed strippable 1 day after placing while supported cap beam forms must stay in place 14 days, and that longer required curing/stripping period is the primary factor driving the need for two complete cap beam form sets.
SP-4 Chapter 3, Section 3.7The usual safety factor for form tie working loads is 2:1 (working load limited to half of ultimate tensile strength), while form anchors securing forms to previously placed concrete require a minimum safety factor of 3 including live load and impact because the concrete may still be 'green.'
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 66Bank yards are the in-place excavated volume (length × width × depth ÷ 27), while loose yards are the swelled hauled volume (bank × (1 + swell %)); haul-off truck loads must be figured from loose yards, since using bank volume undercounts loads.
Pipe and Excavation Contracting — Ch. 9, Estimating Surface Excavation (bank vs loose yards)Wood joists or the bottom of a wood structural floor in a crawl space/unexcavated area within the foundation periphery need naturally durable or preservative-treated wood when closer than 18 in. to exposed ground, while wood framing members including columns resting directly on concrete or masonry exterior foundation walls need it when less than 8 in. from exposed ground.
IRC Section R317.1, Item 1; IRC 2018 Section R317.1Per Table 2.5, F3 permits a maximum w/cm of 0.40 with 5000 psi minimum, S2 permits 0.45 with 4500 psi minimum, and W1 (concrete in contact with water requiring low permeability) permits 0.50 with 4000 psi minimum.
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 24 (Table 2.5)Jobsite storage of strength test cylinders must be at 60 to 80°F (16 to 27°C) for specified strengths less than 6000 psi, while the tighter 68 to 78°F range applies only to specified strengths of 6000 psi or greater.
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 149Criteria A requires the average of any three successive tests to equal or exceed the specified fc′, while Criteria B requires that no single test fall below fc′ by more than 500 psi (3.5 MPa) for fc′ of 5000 psi or less (or more than 10 percent of fc′ when fc′ exceeds 5000 psi).
Contractor's Guide to Quality Concrete Construction (4th ed.), Pages 149-150Per IRC R408.2 the minimum net ventilation opening area is 1 sq ft per 150 sq ft of under-floor area, but may be reduced to 1/1,500 of the under-floor area where an approved Class I vapor retarder covers the ground surface.
IRC Section R408.2; IRC 2018 Section R408.2Retarders delay setting, raise lateral form pressure (chemistry coefficient CC of 1.2 versus 1.0) and require lengthened stripping times, while replacing part of the portland cement with fly ash or slag cement can require about twice the cure time before forms are stripped due to slower early strength gain.
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 82Per Table 4.1 (adapted from 2015 IBC Table 1809.7), one floor requires 12 in. width × 6 in. thickness and two floors 15 in. width × 6 in. thickness, while three floors require 18 in. width × 8 in. thickness.
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 47 (Table 4.1)Key Terms
Formulas to Know
Volume (cu yd) = length (ft) × width (ft) × depth (ft) ÷ 27; e.g., pier 2.5 × 2.5 × 1 = 6.25 cu ft, ×3 piers = 18.75 ÷ 27 = 0.69 cu ydFooting length = outside perimeter = 2 × (length + width); e.g., 2 × (40 + 28) = 136 lin ftAt 4 in. thickness one cubic yard covers 81 sq ft: cu yd = slab area ÷ 81, rounded UP to whole yards (check: area × 0.333 ft ÷ 27)Wall area (sq ft) = perimeter × height; cu yd = (area ÷ 100) × 2.47 cu yd per 100 sq ft (check: area × 0.667 ft ÷ 27)Contact area = both faces = 2 × perimeter (ft) × wall height (ft)Continuous footing: round net volume UP to the next quarter yard (e.g., 5.10 → 5.25 cu yd); combined total orders: sum net volumes, then round UP to the next whole yard (e.g., 17.65 → 18 cu yd)Loose cu yd = bank cu yd × (1 + swell %); truck loads = loose cu yd ÷ load capacity, rounded UP; extra loose yards from a 10% higher swell = bank cu yd × 0.10Adding 1 gal of water per cu yd (5 L/m³) increases slump ≈1 in. (25 mm) and reduces compressive strength ≈150 psi (1.0 MPa), plus increased shrinkageCenter shore load for a two-span uniform load = 1.25wℓ; for non-manufactured shores either consider continuity or increase the simple tributary-area load by 25%Three courses stack 2 ft: courses = height (ft) × 3/2; three blocks lay 4 ft: blocks per course = wall length (ft) × 3/4