Exam Cheat Sheet · Quick Reference
South Carolina Grading
South Carolina · PSI Services Contractor
South Carolina State Portion 40 questions
Key Distinctions
Type 1 exists when actual conditions differ materially from those indicated in the contract, while Type 2 arises when actual conditions differ from what would reasonably be expected; neither relieves the contractor of the duty to thoroughly examine project conditions.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 3 — Earthwork Planning section (p. 121)A structure erected over a depression or obstruction carrying a passageway for traffic is a bridge rather than a culvert when its length measured along the center of the roadway is more than 20 feet.
SCDOT Standard Specifications for Highway Construction, Subsection 101.3.8, Page 5A double horizontal line means 'and then' — everything below it is measured from the RS/RP (reference) point, while a single line means all measurements and elevations are taken from the surveyor's hub beside the information stake.
Excavation and Grading Handbook, Chapter 1 — Cut Stakes section (Page 9)The front-end loader bucket standard rates material above the struck load at a 2:1 angle of repose, whereas shovel and hoe buckets are rated at a 1:1 repose angle.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 9 — Loaders, Fill Factors for Loader Buckets sectionExcavation quantity is figured in bank yards (in-place volume), but haul-off and truck loads must be figured in loose yards after applying swell — dividing bank volume by truck size under-counts the loads.
Pipe and Excavation Contracting — Ch. 9, Estimating Surface Excavation (bank vs loose yards)Tires are deducted from the delivered price and carried as an operating cost (about 35% of a haul truck's operating cost) because they wear out faster than the machine, and normal maintenance repairs are operating costs, while major repairs and overhauls that extend service life are ownership costs added to the adjusted basis and depreciated.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 2 — Elements of Ownership Cost, Purchase Expense section (p. 72) and Cost for Bidding, Ownership Cost section (p. 88)For estimating, a diesel engine consumes about 0.04 gal per flywheel-horsepower-hour while a gasoline engine consumes about 0.06 gal per flywheel-horsepower-hour.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 2 — Elements of Operating Cost, Fuel section (p. 82) and Example 2.12 (p. 96)A two-cycle diesel holds full power to 1,000 ft and then loses about 0.9% per additional 1,000 ft (its low-pressure intake blower), while the four-cycle rule is about 3% per 1,000 ft.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 6 — Altitude's Effect on Usable Power section (pp. 265–266)PCSA data assume mechanical machines split repair cost half materials/parts and half labor, while hydraulic machines are two-thirds materials/parts and one-third labor.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 2 — Cost for Bidding, Repairs section (p. 97)Cars and light-duty trucks under 13,000 lb unloaded are 3-year property, while most other pieces of construction equipment are 5-year property.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 2 — Tax Code Depreciation Schedules section (p. 78)For barrier curb, good practice is to cut the subgrade 2 feet behind the back of curb so the crew can set forms or run the curb machine, whereas the 6-inch figure applies to how far behind an extruded (glue-down) curb aggregate must be placed.
Excavation and Grading Handbook, Pages 185 and 193 (Chapter 10 — Curbs and Paving section)The normal minimum offset is 2 feet for forming, but surveyors must set a 3-foot offset to back of curb when a concrete machine is used on Type 2 or Type 1-A curb so the men and machine have room to work.
Excavation and Grading Handbook, Pages 287 and 289 (Chapter 17 — Curb Stakes / Cutting Curb Grade)When the surveyors show a cut, the road/parking section thickness is added to the cut to get the cut to subgrade — but the grade setter adds slightly less than the full section (e.g., 0.60 added to a 1.20 cut for an 8-in./0.66-ft parking section = 1.80) to leave the grade about 0.06 ft high for compacting; when they show a fill, the fill is ADDED to the rod reading before the full road section is subtracted (4.20 + 0.50 − 0.85 = 3.85 subgrade).
Excavation and Grading Handbook, Page 97 (Chapter 5 — Using a Laser Level on a Road Project section)Code 110 is an open code for extraordinary circumstances (hurricanes, floods, ice, acts of God) requiring the excavator to wait until after the date and time the operator posted, while the three-hour No Show remedy applies to an operator that fails to respond where there are indications of an unmarked facility.
SC 811 Excavator Manual (2024), Page 23 (Positive Response Open Codes) and Page 57 (Section 58-36-60(E)(5))Key Terms
Formulas to Know
Trench: length = outside perimeter = 2 × (L + W); bcy = length × trench width × depth ÷ 27. Basement: footprint = (building L + 2 × working space) × (building W + 2 × working space); bcy = footprint × depth ÷ 27. (Example: 2 × (40 + 28) = 136 ft × 2.5 ft × 2 ft = 680 cf ÷ 27 = 25.19 bcy; (44+2×2) × (28+2×2) = 1,536 sf × 9 ft = 13,824 cf ÷ 27 = 512.00 bcy)Loose cy = bank cy × (1 + swell %); loads = loose cy ÷ truck capacity, always rounded UP (never divide bank volume by truck size). (Examples: 25.19 × 1.30 = 32.74 lcy, 32.74 ÷ 12 = 2.73 → 3 loads; 512.00 × 1.20 = 614.40 lcy, 614.40 ÷ 10 = 61.44 → 62 loads)Extra lcy = bank cy × 0.10 (Example: 25.19 × 0.10 = 2.52 cy; 512.00 × 0.10 = 51.20 cy)Average elevation = sum of the four corner spot elevations ÷ 4; average fill depth = finished elevation − average existing elevation; volume (cy) = lot area × average fill depth ÷ 27. Maximum corner difference = highest corner − lowest corner. (Example: (4.00+3.00+2.00+3.00) ÷ 4 = +3.00'; 4.00 − 3.00 = 1.00'; 100' × 60' = 6,000 sf × 1.00' = 6,000 cf ÷ 27 = 222.2 cy; 4.00 − 2.00 = 2.00')Volume (one station) = 100 ft × width × compacted lift thickness in ft; dry weight = volume × specified dry unit weight; water (lb) = (optimum water content − borrow water content) × dry weight; gallons = water lb ÷ 8.33. (Example: 100 × 36 × 0.667 = 2,400 cf; 2,400 × 115 = 276,000 lb; (0.13 − 0.06) × 276,000 = 19,320 lb ÷ 8.33 = ≈2,319 gal — using the full 13% instead of the 7% difference is the error)Equivalent grade of rolling resistance = rolling resistance (lb/ton) ÷ 20 lb/ton per 1% grade; effective grade = grade resistance (%) + equivalent grade (%). (Example: 120 ÷ 20 = 6%; 4% + 6% = 10%)Rimpull (lb) = (375 × hp × drive-train efficiency) ÷ speed (mph); use 0.85 efficiency when the manufacturer publishes none (SAE recommendation). (Example: (375 × 350 × 0.85) ÷ 5.0 = 22,313 lb)Available pull = published drawbar pull − [tractor weight (tons) × (actual rolling resistance − 110 lb/ton)]. (Example: 20 × (150 − 110) = 800 lb; 18,000 − 800 = 17,200 lb)Max tractive force = coefficient of traction × weight on the driving wheels (not × rimpull); usable power is the lesser of this value and the engine-developed rimpull. (Example: 0.30 × 22,000 = 6,600 lb, which is less than the 12,000-lb rimpull)Fuel (gal/hr) = flywheel hp × fuel rate (0.04 gal/fwhp-hr diesel; 0.06 gal/fwhp-hr gasoline) × time factor (working min ÷ 60) × throttle load factor. (Examples: 200 fwhp diesel, load factor 0.40(1.00)+0.60(0.50)=0.70, time 50/60=0.833 → 200 × 0.04 × 0.583 = 4.67 gal/hr; 75 fwhp gasoline, 60/60 = 1.00, 0.60 throttle → 75 × 0.06 × 1.00 × 0.60 = 2.70 gal/hr)