Exam Cheat Sheet · Quick Reference
South Carolina - Wood Frame Structures
South Carolina · PSI Services Contractor
South Carolina State Portion 50 questions
Key Distinctions
The thickened slab area acts like a footing but is formed by a trench dug into the subgrade (strengthened with rebar) rather than by formwork.
Carpentry and Building Construction, Section 11.1, Page 295Leading edge control lines go not less than 6 ft nor more than 25 ft from the edge, while precast erection uses 6-to-60 ft (or half the member length) and overhand bricklaying uses 10-to-15 ft.
OSHA 29 CFR 1926, §1926.502(g)(1)(i)140 dB peak sound pressure is the impulse/impact noise ceiling, while 115 dB is the lowest-duration (1/4 hour or less) entry of the continuous-noise table.
OSHA 29 CFR 1926, §1926.52(e)8 inches is the minimum edge thickness for plain concrete footings supporting walls of other than light-frame construction; 6 inches is permitted for Group R-3 only if the footing does not project beyond the supported wall more than the footing thickness.
SC Building Code 2021, Section 1809.8The single-side-cut shortening allowance is one-half the 45° thickness of the ridge board; the double-side-cut allowance is one-half the 45° thickness of a common rafter.
Carpentry and Building Construction, Chapter 18, Page 509Type M has high compressive strength and durability for heavily loaded or below-grade foundation walls, Type N is for general above-grade work, Type S is used where high tensile strength is needed (earthquake or high-wind regions), and Type O is a low-strength interior mortar.
Carpentry and Building Construction, Pages 278 to 279A mansard has steep slopes on all four sides with a shallower second slope to the top, while a gambrel has its two slopes on only two sides, a Dutch hip is a hip roof with a small gable at each end near the top, and a low-slope (flat) roof has rafters at only a slight angle for drainage.
Carpentry and Building Construction, Pages 467 to 468After surfacing and seasoning the actual size is less than nominal (a 2×4 measures about 1½ × 3½ inches), and codes use actual dimensions for maximum allowable drilling and notching.
Carpentry and Building Construction, Section 12.1, Page 325Web holes/punchouts are permitted for utility routing, but holes must never be punched in the flange of a stud, joist, or track because it reduces structural strength.
Carpentry and Building Construction, Section 29.3, Builder's Tip - PunchoutsGeneral covers must support at least twice the weight of employees, equipment and materials imposed at any one time, while the axle-load criterion applies only to covers in roadways and vehicular aisles.
OSHA 29 CFR 1926, §1926.502(i)(2)A warning line stanchion must resist 16 pounds applied horizontally 30 inches above the surface toward the roof edge, whereas 50 pounds belongs to toeboards and 200 pounds is the guardrail top-rail load (5,000 pounds is an anchorage requirement).
OSHA 29 CFR 1926, §1926.502(f)(2)(iii)A closed cornice has no rafter overhang and is seldom used on newer houses because attic ventilation (soffit venting) is difficult to provide.
Carpentry and Building Construction, Section 19.4, Page 552Attaching a chord to the side of a girder truss or wood beam is generally limited to a maximum of three toe-nails for 2×4 chords and four toe-nails for 2×6 chords to reduce splitting.
BCSI Guide, Page 63 (B8 section)Nails at supported panel edges are spaced 6 inches on center while intermediate supports require 12-inch spacing.
Carpentry and Building Construction, Chapter 15, Table 15-5Key Terms
Formulas to Know
Board feet per piece = (nominal thickness × nominal width × length in feet) ÷ 12; multiply by number of pieces. Example: (2 × 10 × 22) ÷ 12 = 36.67 bf per piece × 24 pieces ≈ 880 bf.Excavation length and width = building dimension + clearance on each side; Area = L × W; Volume (cu yd) = area × factor for depth. Example: (40+2+2) × (26+2+2) = 1,320 sq ft × 0.259 (7-ft depth factor) = 341.88 ≈ 342 cu yd.Step 1: Area of floor = length × width for each level (example 20' × 40' = 800 sq ft); then apply a board-feet-per-100-sq-ft factor from Table 15-4 and multiply by cost per board foot.(Roof surface area ÷ 100) × board feet per 100 sq ft for the rafter size/spacing. Example: 2,100 ÷ 100 = 21; 21 × 102 (2×6 @ 16" OC) = 2,142 bf, including common rafters, hip and valley rafters, ridge boards and collar ties.Roof area ÷ 32 sq ft per panel, then add 5% trim and waste. Example: 72.19 × 0.05 = 3.6; 72.19 + 3.6 = 75.79, rounded up to 76 sheets.Slab area ÷ 81 sq ft per cu yd (coverage at 4 in.), rounded up to whole yards. Examples: 30 × 32 = 960 ÷ 81 = 11.85 → 12 cu yd; 44 × 32 = 1,408 ÷ 81 = 17.38 → 18 cu yd. (Check: area × 0.333 ft ÷ 27.)Length = outside perimeter = 2 × (L + W); Volume (cu ft) = length × width (ft) × depth (ft); ÷ 27 = cu yd. Examples: 124 ft × 1.333 × 0.833 = 137.78 ÷ 27 = 5.10 cu yd; 136 ft × 1.333 × 0.667 = 120.89 ÷ 27 = 4.48 cu yd.Each pier = L × W × depth in feet; multiply by number of piers; ÷ 27 = cu yd. Examples: 2.5 × 2.5 × 1 = 6.25 cu ft × 3 = 18.75 ÷ 27 = 0.69 cu yd; 2 × 2 × 1 = 4.00 cu ft × 4 = 16.00 ÷ 27 = 0.59 cu yd.Round the net footing volume UP to the next quarter yard. Examples: 5.10 → 5.25 cu yd; 4.48 → 4.5 cu yd.Sum the net volumes, then round up to the next whole yard. Examples: 5.10 + 0.69 + 11.85 = 17.65 → 18 cu yd; 9.38 + 0.59 + 17.38 = 27.36 → 28 cu yd.Contact area = both faces: 2 × perimeter × wall height. Examples: 2 × 136 ft × 8 ft = 2,176 sq ft; 2 × 152 ft × 8 ft = 2,432 sq ft.Wall area = perimeter × height; (area ÷ 100) × 2.47 cu yd per 100 sq ft. Examples: 136 × 8 = 1,088 ÷ 100 = 10.88 × 2.47 = 26.87 cu yd; 152 × 8 = 1,216 ÷ 100 = 12.16 × 2.47 = 30.04 cu yd (check: area × 0.667 ft ÷ 27).Walls + footing (net, two decimals). Examples: 26.87 + 4.48 = 31.35 cu yd; 29.24 + 7.31 = 36.55 cu yd.Measure 3 ft along one layout line and 4 ft along the other; the diagonal must read exactly 5 ft for a 90° corner — if it reads 5'-1", adjust one layout line until the diagonal is exactly 5 ft before locating the remaining walls.Apply the table factor for the ratio Hc/Hr (height of ceiling joists/rafter ties to height of ridge, both measured vertically above the top of the rafter support walls); at Hc/Hr = 1/3 the factor is 0.67 applied to the tabulated rafter span.(1) Determine live load category (e.g., 40 psf), (2) locate species/group column, (3) find grade column, (4) follow the row right to the required span, (5) follow that column up to the on-center spacing, (6) read lumber dimensions in the row above.