Exam Cheat Sheet · Quick Reference

Tennessee BC-C Industrial Contractor

Tennessee  ·  Prov

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
70
Passing score
73%
Exam time
210 min
Administered by
Prov
Format
Reference materials allowed

Tennessee State Portion 70 questions

Estimating, Plan Reading 8 Q · 11%
Reading and interpreting civil drawings (site plans, plan and profile sheets, cross-sections)Contour lines, grading plans, and cut-and-fill mapsExcavation volume calculations (rectangular, triangular, trapezoidal, and cylindrical shapes)Unit conversions and material weight calculations for excavationConstruction specifications format (CSI MasterFormat Division 31 Earthwork)Slope and grade control using stakes, benchmarks, and layout methods
General Code 5 Q · 7%
Occupancy classification and use group assignments (Groups A, B, E, F, H, I, M, R, S, U)Building height and area limitations by occupancy and type of constructionTypes of construction (Types I–V) and fire-resistance rating requirements for building elementsFire-resistance-rated assemblies: fire walls, fire barriers, fire partitions, smoke barriers, and smoke partitionsMeans of egress requirements: occupant load, exit capacity, number and separation of exits, egress illuminationAutomatic sprinkler system requirements by occupancy, building height, and fire areaAccessibility requirements: accessible routes, entrances, parking, and means of egressScope, administration, and authority of the building official; permits, inspections, and certificates
Sitework 2 Q · 3%
Excavation safety requirements and competent person responsibilities (OSHA 1926 Subpart P)Trench protective systems: sloping, benching, shoring, and shieldingSoil classification for excavation (Type A, B, C, Stable Rock)Grading operations: cuts, fills, compaction, and slope requirements (IBC Appendix J)Earthmoving equipment selection and site excavation methodsDrainage and water control on construction sitesUnderground pipe installation: trench preparation, bedding, and thrust blocksPaving operations: concrete and hot-mix asphalt methods, equipment, and quality control
Footings and Foundations 3 Q · 4%
Soil classification and presumptive load-bearing valuesFooting minimum dimensions, depth, and frost protectionConcrete and masonry foundation wall design and reinforcementFoundation dampproofing and waterproofingGeotechnical investigations and soil testing requirementsFootings and foundations on or adjacent to slopesDeep foundation elements and pile design requirements
Concrete and Concrete Reinforcement 17 Q · 24%
ConcreteConcrete ReinforcementConcrete mix design and proportioningConcrete batching, mixing, and transportingConcrete placement, consolidation, and finishingCuring methods and requirementsConcrete durability and exposure categoriesFormwork design and removalReinforcing bar fabrication, sizes, grades, and ASTM standardsConcrete cover requirements and bar supports
Masonry 6 Q · 9%
Masonry materials: clay brick types, grades, and manufacturing processesConcrete masonry unit (CMU) types, grades, and propertiesMortar types, proportions, and mixing requirementsMasonry wall systems: solid, cavity, composite, hollow, and veneer wallsLaying brick and block techniques: mortar placement, coursing, leads, and mason's lineMasonry reinforcement, anchors, ties, and joint reinforcementMasonry structural design: allowable stress, strength design, and empirical design methodsOSHA safety requirements and jobsite safety for masonry construction
Carpentry 3 Q · 4%
Wood wall framing components (studs, plates, headers, cripple studs, trimmer studs)Wall bracing methods and braced wall panel requirementsHeader sizing and span tables for wall openingsFastening schedules for wood wall and roof framing connectionsDrilling and notching limitations for studs and top platesCold-formed steel wall framing materials, member identification, and installationWood floor framing: joist spans, bridging, blocking, and cantileversWood roof framing: rafter spans, ridge boards, collar ties, and ceiling joists
Structural Steel 14 Q · 20%
Pre-erection activities and site readiness verificationStructural steel erection sequence (columns, horizontal members, bracing and bridging)Column anchorage requirements and anchor bolt tolerancesBolted and welded field connections (framed-beam, seated-beam, end-plate, single-plate shear)Erection tolerances for columns and structural membersTemporary supports, bracing, and plumbing-up during erectionSteel erection safety requirements under OSHA Subpart R (fall protection, hoisting, open web steel joists, metal decking)Pre-engineered metal building erection and IBC Chapter 22 steel design standards
Roofing, Siding, and Insulation 4 Q · 6%
Roof covering types and minimum slope requirements (asphalt shingles, clay/concrete tile, metal panels, wood shingles/shakes, built-up, modified bitumen, single-ply)Underlayment selection, application, and attachment requirements by roof covering type and wind speedRoof flashing requirements (valleys, drip edges, base/cap flashing, crickets and saddles, parapet walls)Fire classification of roof assemblies (Class A, B, C ratings and applicable construction types)Insulation types, R-values, and installation methods (flexible, loose-fill, rigid/semirigid, reflective, spray foam)Vapor retarders and moisture control (perm ratings, vapor barrier classes, placement relative to building thermal envelope by climate zone)Exterior wall weather protection and water-resistive barriers (building wrap/house wrap installation, flashing at openings, drainage requirements)Reroofing requirements (roof recover vs. roof replacement, conditions prohibiting recover, reinstallation of materials)
Plumbing Concepts 1 Q · 1%
Minimum plumbing fixture counts by occupancy type (IBC Table 2902.1)Sanitary drainage system design: pipe sizing, slope, and fixture unit valuesBackflow prevention devices and cross-connection controlVenting methods and vent pipe sizing requirementsWater supply system design: pressure, flow rates, and pipe sizingFixture trap requirements: seal depth, size, and prohibited trap typesWater heater installation: relief valves, pan requirements, and prohibited locationsStorm drainage and subsoil drain systems
HVAC Concepts 1 Q · 1%
Combustion air requirements and sizing methods for fuel-gas appliancesFuel gas piping materials, sizing, and installationVenting systems and chimney types for gas appliances (Type B, BW, L, single-wall, factory-built)Duct system construction, materials, insulation, and sealingHeating and cooling equipment installation, sizing, and clearances to combustiblesCondensate disposal and auxiliary drain pan requirementsBoiler and water heater installation, safety controls, and pressure reliefExhaust systems for dryers, cooking equipment, and mechanical ventilation
Electrical Concepts 1 Q · 1%
GFCI and AFCI protection requirements by locationService entrance sizing, conductors, and disconnecting meansGrounding and bonding systems (electrodes, conductors, jumpers)Branch circuit ratings, loading, and overcurrent protectionReceptacle outlet placement and spacing requirementsWiring methods, raceways, and conduit fillPanelboard installation, ratings, and working space clearancesEmergency and standby power systems (IBC requirements)
OSHA Safety 5 Q · 7%
Fall protection requirements and systems (guardrail, safety net, personal fall arrest)Scaffold safety requirements and load capacityExcavation and trenching safety (cave-in protection, sloping, shoring)Personal protective equipment (PPE) selection and employer responsibilitiesElectrical safety in construction (grounding, GFCI, lockout/tagout, working clearances)Hazardous and toxic substances (asbestos, silica, permissible exposure limits)Fire protection and prevention on construction sitesStairway and ladder safety requirements

Key Distinctions

Direct construction costvsDirect (job) overhead cost

Direct construction costs are the labor, material and equipment tied to a specific trade or phase (pipe materials, backhoe rental, pipe bedding aggregate), while direct (job) overhead covers administrative items caused by the particular job but not tied to a trade or phase, such as traffic control (barricades, flaggers, lane delineators) and pipe/soil density testing.

Pipe and Excavation Contracting, Pages 20-21
Contact lap splicevsSpaced-lap splice

A contact splice places the bars in actual contact and is preferred because it provides more strength, while a spaced-lap splice sets the bars apart without contact at a center-to-center spacing that must not exceed 6 inches.

Study Guide for Commercial Building Contractor, Module 27304 Reinforcing Concrete, Section 4.1.2
B-B Plyform® deck surfacevsHDO-overlaid deck surface

B-B Plyform®, sanded both sides and mill oiled, can be reused 5 to 10 times, whereas an HDO-overlaid surface normally produces 20 to 50 reuses or more with reasonable care.

Study Guide for Commercial Building Contractor, Module 27309 Horizontal Formwork, Section 4.1.0
Site-built beam sides of lumbervsSite-built beam sides of plywood

Lumber beam sides require 2x4 vertical cleats on 2' to 2'-6" centers, while plywood sides eliminate the cleats and use 2x4 vertical stiffeners instead.

Study Guide for Commercial Building Contractor, Module 27309 Horizontal Formwork, Section 3.3.1
Field-cured test cylindersvsLaboratory-cured test cylinders

Field-cured samples stay on site under the same conditions as the placement and may be used to determine when it is safe to remove forms, while acceptance strength is determined from laboratory-cured cylinders tested under ASTM C39.

Study Guide for Commercial Building Contractor, Module 23212 Properties of Concrete, Section 3.4.0
Registered design professional (IBC 2207.2)vsSteel joist manufacturer (IBC 2207.3)

The registered design professional must show on the construction documents the joist/joist girder designations and requirements for design, layout, end supports, anchorage, bridging design differing from SJI, bridging termination connections and bearing connections resisting uplift and lateral loads; the manufacturer designs the joists for those stated loads and, when required, submits sealed calculations plus bridging design differing from SJI and connection design for connections differing from SJI, field splices and joist headers.

IBC 2021 Section 2207.2
"K" series joist end attachment (welded)vs"LH"/"DLH" series joists and joist girders

Each end of a "K" series joist requires a minimum of two 1/8-inch fillet welds 1 inch long (or two 1/2-inch bolts or the equivalent), while the larger 1/4-inch by 2-inch welds apply to "LH" and "DLH" series joists and joist girders.

29 CFR 1926, Subpart R, §1926.757(b)(1)
Standard SJI joist productsvsNon-standard SJI products

Non-standard products — barrel, bowstring, gable and scissor joists and other special truss configurations — are not standard SJI products and must be erected per AISC Code of Standard Practice Section 7 and OSHA 1926.756 rather than typical SJI erection procedures.

SJI Technical Digest, Chapter 1 - Products
BentvsTruss

A bent is a section of vertical structure usually assembled from fabricated members at the site and requires temporary bracing until all permanent members are attached, while a truss provides horizontal and vertical strength and is usually shop-fabricated and shipped to be lifted into place as a unit.

Study Guide for Structural Steel, Structural Ironworking Two, Section 2.10.0 — Building Trusses and Bents
Hollow masonry unitvsSolid masonry unit

A hollow unit has net cross-sectional area less than 75 percent of its gross cross-sectional area measured in any plane parallel to the surface containing voids; a solid unit has 75 percent or more.

ACI 530/530.1-11, TMS 402 Code Chapter 1, Section 1.6 Definitions, Page C-16
Solid-core doorvsHollow-core door

Solid-core construction (wood strips, particleboard, rigid foam or other core covered with a thin veneer) reduces warping, is more fire-resistant and is generally preferred for exterior doors, unlike hollow-core doors.

Residential Doors chapter, Flat-Panel Doors section
Markup on costvsMargin as a percent of gross receipts

Marking hard costs up by the overhead percentage under-recovers overhead (10% markup on $90 = $99), while dividing the hard cost total by (1.0 − desired margin) yields the correct selling price ($90 ÷ 0.90 = $100, a true 10% margin).

Pipe and Excavation Contracting, Pages 24-25
Type II(MH) portland cementvsType V portland cement

Type II(MH) generates heat at a slower rate by limiting the heat index (C₃S + 4.75 C₃A) to a maximum of 100 for mass elements, while Type V is the sulfate-resistant cement used only where severe sulfate action from high-alkali water and/or soil occurs (Type II offers only moderate sulfate resistance).

Design and Control of Concrete Mixtures, 17th ed., Chapter 2 - Portland, Blended, and Other Hydraulic Cements, Page 30 (16th ed.: Page 112)

Key Terms

Fire wall (IBC 202) IBC 2021 Section 202 (Definitions - Fire Wall)
A fire-resistance-rated wall with protected openings that restricts the spread of fire and extends continuously from the foundation to or through the roof, with sufficient structural stability under fire conditions to allow collapse of construction on either side without collapse of the wall.
Building area (IBC 202) IBC 2021 Section 202 (Definitions - Area, Building)
The area within surrounding exterior walls, or exterior walls and fire walls, exclusive of vent shafts and courts; unwalled areas are included if they fall within the horizontal projection of the roof or floor above.
Occupant load (IBC 202) IBC 2021 202
The number of persons for which the means of egress of a building or portion thereof is designed — a design value, not the actual number of people present.
Story above grade plane (IBC 202) IBC 2021 Section 202 (Definitions - Story Above Grade Plane)
Any story whose finished floor surface is entirely above grade plane, or in which the finished surface of the floor next above is more than 6 feet above grade plane or more than 12 feet above the finished ground level at any point.
Cavity wall (TMS 402/ACI 530 Sec. 1.6) ACI 530/530.1-11, TMS 402 Code Chapter 1, Section 1.6 Definitions, Page C-14
A masonry wall of two or more wythes, at least two separated by a continuous air space, with the separated wythes connected by wall ties.
Seating-loss (PTI Field Procedures Manual, Ch. 1) PTI Field Procedures Manual, Chapter 1 Definitions - Seating-Loss
The relative movement of the wedges into the anchor cavity during transfer of the prestressing force to the anchorage, which results in some loss of prestressing force.
Expansive soil (IBC 1803.5.3) IBC 2021 Section 1803.5.3
Soil meeting the code criteria that include more than 10 percent of the particles passing a No. 200 sieve (75 µm) and more than 10 percent of the particles being less than 5 micrometers in size, determined per ASTM D422.
Active-zone stabilization of expansive soils (IBC 1808.6.4) IBC 2021 Section 1808.6.4
Where the active zone is stabilized in lieu of designing foundations under Section 1808.6.1 or 1808.6.2, the soil shall be stabilized by chemical, dewatering, presaturation or equivalent techniques.
Class 4 soil materials (IBC Table 1806.2) IBC 2021 Table 1806.2
Sand, silty sand, clayey sand, silty gravel and clayey gravel (SW, SP, SM, SC, GM, GC), assigned a lateral bearing pressure of 150 psf per foot below natural grade.
Class 3 soil materials (IBC Table 1806.2) IBC 2021 Table 1806.2
Sandy gravel and gravel (GW and GP), assigned a coefficient of friction of 0.35 for lateral sliding resistance — the same as sedimentary and foliated rock and lower than crystalline bedrock's 0.70.
Truss design drawings / truss placement diagram (IBC 2303.4.1.1, 2303.4.2) IBC 2021 Section 2303.4.1.1
Documents that must be provided with the shipment of trusses delivered to the job site; the design drawings list design loads as applicable, including top chord live load and top chord dead load.
Truss alteration (IBC 2303.4.5) IBC 2021 Section 2303.4.5
Any alteration adding load to a truss member (HVAC equipment, piping, additional roofing or insulation) is not permitted without verification that the truss can support such additional loading.
Gain (door hinge) Residential Doors chapter, Hinges section
A mortise or notch cut for a hinge leaf whose depth equals the thickness of a single hinge leaf, with one gain in the door edge and one in the jamb so the closed door sits flush.
Plyform Modern Masonry (9th ed.), Chapter 19, Page 402
An exterior-type plywood made from special wood species and veneer grades specifically for concrete forming, available in Class I and Class II grades.
Boulder (earthmoving classification) Study Guide for Commercial Building Contractor, Module 22201, Section 1.2.0 (Soil Characteristics)
Rock pieces larger than 10 inches in diameter; gravel is greater than 0.08 inch and less than 10 inches, with pieces between called cobbles or stones.
Job efficiency factor (excavation estimating) Pipe and Excavation Contracting, Page 68
The productive-time allowance based on about 50 productive work minutes per hour as the best expected on most jobs, giving a factor of 0.83 (50 ÷ 60).
Bar support tolerance (Placing Reinforcing Bars, Ch. 10) Placing Reinforcing Bars (10th ed.), Chapter 10, Bar Supports section
Bar supports hold reinforcing bars in location during placement for proper cover and design depth, with a normal construction tolerance of plus or minus 1/8 inch from the specified nominal height, measured from the bottom of the leg or sand plate to the underside of the bar.

Formulas to Know

Sloped rafter/top-chord length from run and riseRafter length = √(run² + rise²); e.g., run 28.00' and rise 14.00' → √(784+196)=31.30'; run 24.00' and rise 12.00' → √720 = 26.8 ft
Rise from span and pitchRun = span ÷ 2; Rise = run × (pitch rise/12); e.g., 63'-0" span at 8:12 → run 31.50' × 8/12 = 21.00' rise
Top-chord slope angleAngle from horizontal = arctan(rise ÷ run); e.g., rise 12.00' ÷ run 24.00' = 0.5 → 26.6°
Actual sloped roof area / length from plan dimensionsSloped area = plan footprint × slope factor (6:12 factor 1.118 → 2,000 sf × 1.118 = 2,236 sf); sloped length = run × slope factor (3:12 factor 1.031; porch 20×10 = 200 sf × 1.031 = 206 sf; porch run 12' × 1.054 = 12.6 lin ft). Take off areas with differing slopes separately.
Cubic feet to cubic yards (and bedding quantity)Cubic yards = cubic feet ÷ 27 (27 cf = 1 cy); bedding cy = trench length (ft) × trench width (ft) × bedding depth (ft) ÷ 27
Bar spacing within a footing when no spacing is dimensionedSpacing = footing dimension in inches ÷ (number of bars in that direction − 1); e.g., 15 ft = 180 in., 11 bars → 180 ÷ 10 = 18 in. o.c. (odd bar count puts the first bar on the center line)
Volume of a trapezoidal (prism) footing excavationArea = ½(base 1 + base 2) × height; Volume = area × length; cy = cf ÷ 27; e.g., ½(2+3)×4 = 10 sf × 27 ft = 270 cf ÷ 27 = 10 cy
Truncated prism method for grid-cell excavationAverage the four corner depths, multiply by the base area, then ÷27; e.g., (4+2+6+8)/4 = 5 ft × 2,500 sf = 12,500 cf ÷ 27 ≈ 463 cy
Haul trips from bank cubic yardsLCY = BCY × swell factor, then truckloads = LCY ÷ truck capacity (LCY); e.g., 500 BCY × 1.32 = 660 LCY ÷ 14 LCY = 47.1 → 47 loads
Selling price that recovers an overhead marginSelling price = hard cost total ÷ (1.0 − desired margin %); e.g., $90 ÷ 0.90 = $100 for a 10% margin