Exam Cheat Sheet · Quick Reference

Texas Master Electrician NEC Knowledge Portion

Texas  ·  PSI Services Contractor

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
75
Passing score
70%
Exam time
150 min
Administered by
PSI Services Contractor
Format
Reference materials allowed

Texas State Portion 75 questions

Definitions, Theory, and Plans 7 Q · 10%
Purpose and scope of the NEC (practical safeguarding of persons and property)Installations covered vs. not covered by the NECCode arrangement: chapters, their applicability, and hierarchy (Chapters 1–9)Mandatory vs. permissive vs. explanatory rules (shall/shall not vs. shall be permitted)Authority having jurisdiction: enforcement, interpretations, and special permissionExamination and listing of equipment for safetyWiring planning: future expansion, spare raceways, and limiting circuits in enclosuresUnits of measurement: SI vs. inch-pound, hard vs. soft conversion
Electrical Services, Service Equipment, and Separately Derived Systems 11 Q · 16%
Service disconnect requirements: location, rating, number, and grouping (Article 230, Parts VI)Overhead and underground service conductor installation: clearances, wiring methods, minimum sizes, and protection (Article 230, Parts II-IV)Service entrance conductor sizing, ampacity calculations, and continuous load requirements (Article 230, Part IV and Article 220)Grounding and bonding of service-supplied AC systems: main bonding jumper, grounding electrode conductor sizing, and system grounding connections (Article 250, Parts II-III)Separately derived systems: grounding, system bonding jumper, grounding electrode, and bonding requirements (Article 250, Section 250.30)Service equipment overcurrent protection: ground-fault protection of equipment, overload protection, and equipment connected on supply side of service disconnect (Article 230, Part VII)Service equipment marking, listing, surge protection, and emergency disconnect requirements (Article 230, Sections 230.66, 230.67, 230.85)Switchboards, switchgear, and panelboards used as service equipment: bonding, grounding, overcurrent protection, and installation requirements (Article 408)
Electrical Feeders 4 Q · 6%
Minimum feeder conductor ampacity for continuous and noncontinuous loads (125% rule and exceptions)Feeder overcurrent protection requirements and ratingsFeeder and service load calculations using demand factors (dwelling, multifamily, commercial occupancies)Ground-fault protection of equipment for feeder disconnects rated 1000 amperes or moreFeeder conductor identification (grounded, equipment grounding, and ungrounded conductors)Outside feeder requirements including overhead clearances, conductor support, and disconnecting means for separate buildingsSurge-protective device (SPD) requirements for feeders supplying dwelling units and similar occupanciesFeeder tap conductor rules (10-foot, 25-foot, and outside tap provisions)
Branch Circuit Conductors 11 Q · 16%
Minimum ampacity and size requirements for branch-circuit conductors (NEC 210.19)Overcurrent protection ratings for branch circuits including continuous and noncontinuous loads (NEC 210.20)Branch-circuit ratings and permissible loads by circuit size (NEC 210.18, 210.22, 210.23, 210.24)Conductor ampacity tables and adjustment/correction factors for temperature and number of conductors (NEC 310.15, 310.16)Conductor identification for grounded, equipment grounding, and ungrounded conductors (NEC 210.5, 200.6, 310.6)Multiwire branch circuit requirements including disconnecting means and line-to-neutral loads (NEC 210.4)Conductor insulation types, temperature ratings, and permitted uses by location (NEC 310.4, 310.10)Conductors in parallel requirements including minimum size and installation characteristics (NEC 310.10(G))
Electrical Wiring Methods and Electrical Materials 7 Q · 10%
Conductor ampacity tables and temperature ratings (Tables 310.16–310.21)Ampacity correction and adjustment factors for ambient temperature and multiple conductorsProtection of cables and raceways against physical damage (bored holes, notches, framing members)Underground installation requirements including minimum cover depths (Table 300.5(A))Securing and supporting requirements for conduit types (RMC, IMC, PVC, FMC, AC, MC, NM)Uses permitted and not permitted for wiring methods (Type AC, MC, NM/NMC, RMC, IMC, PVC, FMC)Conductor installation rules including same-circuit grouping, parallel conductors, and conductor typesWiring in environmental air spaces, plenums, and protection against fire spread
Electrical Equipment and Devices 8 Q · 11%
Switch types, ratings, and permitted uses (AC/DC snap switches, dimmers, knife switches, circuit breakers as switches)Receptacle ratings, types, installation, and grounding requirementsSwitchboards, switchgear, and panelboard installation, overcurrent protection, and groundingMotor branch-circuit conductors, overload protection, and short-circuit/ground-fault protectionMotor controllers and disconnecting means requirementsLuminaire installation, support, grounding, and location restrictionsTransformer installation, overcurrent protection, and vault requirementsAir-conditioning and refrigerating equipment branch circuits, disconnecting means, and overload protection
Motors and Generators 7 Q · 10%
Motor branch-circuit conductor sizing and ampacity requirements (430.22, 430.24)Motor branch-circuit short-circuit and ground-fault protective device ratings and settings (430.52, Table 430.52(C)(1))Motor overload protection requirements and trip current percentages (430.32)Motor disconnecting means type, location, and rating requirements (430.102, 430.109, 430.110)Motor controller ratings, markings, and design requirements (430.8, 430.83)Motor control circuit overcurrent protection and disconnection (430.72, 430.75)Generator installation requirements including overcurrent protection, conductor ampacity, and disconnecting means (445.12, 445.13, 445.18, 445.19)Motor and controller grounding and bonding requirements (430.242, 430.244, 430.245)
Electrical Control Devices and Disconnecting Means 3 Q · 4%
Motor disconnecting means requirements: location, type, and rating (Article 430, Part IX)Switch ratings and load types for general-use snap switches, dimmers, and control switches (Article 404)Motor controller ratings, types, and disconnecting means (Article 430, Parts VII and IX)Overcurrent protection for motor branch circuits: rating and setting per Table 430.52(C)(1)Panelboard, switchboard, and switchgear overcurrent protection and disconnecting means (Articles 408 and 240)Industrial control panel disconnecting means, overcurrent protection, and short-circuit current rating (Article 409)Switch enclosure requirements: accessibility, grounding, and installation in damp/wet locations (Article 404)Circuit breaker use as switch or motor controller: marking, indicating, and application requirements (Articles 240 and 404)
Special Occupancies, Equipment, and Conditions 8 Q · 11%
Classification of hazardous locations by Class (I, II, III) and Division (1 and 2)Material group classifications for Class I (Groups A, B, C, D) and Class II (Groups E, F, G) locationsProtection techniques for hazardous locations (explosionproof, dust-ignitionproof, intrinsic safety, purged/pressurized, nonincendive, etc.)Wiring methods and sealing requirements for Class I, II, and III Division 1 and 2 locationsEquipment requirements and markings for hazardous classified locations (temperature codes, class, division, group)Grounding and bonding requirements specific to hazardous classified locationsSpecial occupancy area classification and wiring requirements for commercial garages, aircraft hangars, motor fuel dispensing facilities, and cannabis oil equipmentZone classification system (Zones 0, 1, 2 and Zones 20, 21, 22) as an alternative to the Division system
Renewable Energy Technologies 4 Q · 6%
PV system maximum voltage calculations and temperature correction factorsRapid shutdown requirements for PV systems on buildingsPV system disconnecting means requirements and markingsOvercurrent protection for PV system DC circuitsArc-fault circuit protection for PV DC circuitsGrounding and bonding of PV system equipment and arraysEnergy storage system (ESS) disconnecting means and circuit sizingInterconnected power source connections to load-side distribution equipment

Key Distinctions

Standard branch-circuit/feeder sizing for continuous loads (210.19(A)(1), 215.2(A)(1))vsException for separately installed pressure connections (210.19(A), Exception to (1) and (2))

The standard rule requires ampacity of the noncontinuous load plus 125% of the continuous load, while the exception permits ampacity equal only to the sum of the continuous plus noncontinuous load (100%) where a portion of the branch circuit is connected at both supply and load ends to separately installed pressure connections covered in 110.14(C)(2).

NEC 2026 Section 210.19
3 percent voltage dropvs5 percent voltage drop

Per the Informational Note to 210.19, 3 percent is the maximum drop at the farthest outlet for branch circuits serving power, heating, and lighting loads, whereas 5 percent is the maximum combined drop on both feeders and branch circuits to the farthest outlet.

NEC 2026 Section 210.19, Informational Note
Flush-mounted switches/circuit breakers in damp or wet locationsvsSurface-mounted switches/circuit breakers in damp or wet locations

Per 404.6(B) flush-mounted devices must be equipped with weatherproof covers, while per 404.6(A) surface-mounted devices must be enclosed in a weatherproof enclosure or cabinet complying with 312.4.

NEC 2026 Section 404.6(B)
NEC Chapters 1, 2, 3, and 4vsNEC Chapters 5, 6, 7 and Chapter 8

Per 90.3, Chapters 1–4 apply generally to all electrical installations; Chapters 5–7 apply to special occupancies, special equipment, or other special conditions and may supplement or modify the general requirements, and Chapter 8 (communications systems) is not subject to Chapters 1 through 7 except where specifically referenced in Chapter 8.

NEC 2026 Section 90.3
Installations covered by the NECvsInstallations not covered by the NEC (90.2(D))

Mobile homes and recreational vehicles (Articles 550/551), industrial substations, and marina shore power (Article 555) are covered, while ships, watercraft other than floating buildings, railway rolling stock, aircraft, and automotive vehicles other than mobile homes and RVs are excluded.

NEC 2026 Section 90.2
SI (metric) unitsvsInch-pound units

Per 90.9(A) and 90.9(B), metric (SI) is the system of preference and SI units appear first, with inch-pound units immediately following in parentheses based on hard conversion; 90.9(C) permits either system to be used.

NEC 2026 Section 90.9
Enforceable Code rulesvsInformational notes (90.5(C))

Code rules are enforceable requirements, while informational notes are explanatory only — such as references to other standards or related sections — and are not enforceable as requirements.

NEC 2026 Section 90.5
Motor overload protection sizingvsMotor branch-circuit conductor, disconnect, and short-circuit protection sizing

Overload protection per 430.32 is based on the motor NAMEPLATE full-load current, while conductors (430.22), disconnects (430.110(A)), and branch-circuit short-circuit/ground-fault protection are based on the Table 430.250 FLC per 430.6(A)(1), not nameplate current.

NEC 2026 Section 430.32
Overload at 125% of nameplate FLAvsOverload at 115% of nameplate FLA

Per 430.32, motors with a marked service factor of 1.15 or greater (or a temperature rise not over 40°C) use 125% of nameplate FLA, while other motors — such as one with a 46°C temperature rise and no SF of 1.15 or greater — use 115% of nameplate FLA.

NEC 2026 Section 430.32
Time-delay (dual-element) fuse for a squirrel cage motorvsInverse-time circuit breaker for a squirrel cage motor

Per Table 430.52 the time-delay fuse maximum is 175% of FLC while the inverse-time circuit breaker maximum is 250% of FLC; in both cases 430.52(C)(1) permits the next higher standard rating from 240.6(A) when the calculated value is not a standard size.

NEC 2026 Table 430.250, Table 430.52, Section 240.6(A)
Motor branch-circuit conductor ampacity (430.22)vsMotor feeder conductor ampacity (430.24)

A branch circuit to a single motor is sized at 125% of that motor's FLC, whereas a feeder to multiple motors is sized at 125% of the largest motor's FLC plus 100% of all other motor FLCs (plus other loads per their applicable articles).

NEC 2026 Table 430.250, Section 430.22
10-ampere branch circuitsvs15, 20, 30, 40, and 50-ampere branch circuits

Per 210.18 the ratings for other than individual branch circuits are 10, 15, 20, 30, 40, and 50 amperes; the difference is in permitted loads — per 210.18 Exception No. 2 and 210.23(A)(2)/Table 210.24 footnote 2 a 10-ampere circuit shall not supply receptacle outlets (it may supply lighting outlets, dwelling-unit bathroom/laundry exhaust fans, or an individual gas fireplace unit), while 15/20/30/40/50-ampere circuits may supply receptacles and other loads per 210.23(B) through (D).

NEC 2026 Section 210.18 Exception No. 2, 210.23
Simultaneous disconnect at the multiwire branch-circuit originvsSimultaneous disconnect at the motor controller

Per 210.4(B) the means to simultaneously disconnect all ungrounded conductors is required at the point where the multiwire branch circuit originates (typically the panelboard); that section does not require the motor controller itself to provide it.

NEC 2026 Section 210.4

Key Terms

Authority Having Jurisdiction (AHJ) NEC 2026 Section 90.4
Per 90.4, the entity enforcing the Code that is responsible for making interpretations of the rules, deciding on approval of equipment and materials, and granting special permission contemplated in the rules.
Informational Note NEC 2026 Section 90.5
Per 90.5(C), explanatory material (such as references to other standards or related sections) that is informational only and not enforceable as a Code requirement.
Purpose of the NEC NEC 2026 Section 90.2
Per 90.2(A) (Practical Safeguarding), the purpose of the Code is the practical safeguarding of persons and property from hazards arising from the use of electricity; it is not intended as a design specification or an instruction manual for untrained persons.
Multiwire branch circuit NEC 2026 Section 210.4
A branch circuit that, per 210.4(B), must be provided with a means to simultaneously disconnect all ungrounded conductors at the point where the branch circuit originates.
Neutral conductor (single-circuit restriction) NEC 2026 Section 200.6(A)
Per 200.4(A), a conductor that shall not be used for more than one branch circuit, more than one multiwire branch circuit, or more than one set of ungrounded feeder conductors unless specifically permitted elsewhere in the Code.
Grounded conductor continuity NEC 2026 Section 200.4(B)
Per 200.2(B), the continuity of a grounded conductor shall not depend on a connection to a metal enclosure, raceway, or cable armor; per 210.5(A) the grounded conductor of a branch circuit is identified in accordance with 200.6.
Wet location (underground) NEC 2026 Section 300.7(B)
Per 300.5(B), the interior of enclosures or raceways installed underground is considered a wet location, and conductors and cables installed there must comply with wet-location requirements.
Free conductor length at boxes NEC 2026 Section 300.16
Per 300.14, at least 150 mm (6 in.) of free conductor measured from where it emerges from the raceway or cable sheath must be left at each outlet, junction, and switch point, and where the opening is less than 200 mm (8 in.) in any dimension each conductor must extend at least 75 mm (3 in.) outside the opening.
Direct burial minimum cover NEC 2026 Table 300.7(A)
Per Table 300.5(A), Column 1, direct burial cables or conductors rated 1000 volts or less in locations not otherwise specified require a minimum cover of 600 mm (24 in.).
Vertical raceway conductor support NEC 2026 Table 300.21(A)
Per 300.19(A), conductors in vertical raceways must be supported where the vertical rise exceeds the values in Table 300.19(A); copper conductors 18 AWG through 8 AWG shall not be supported at intervals greater than 30 m (100 ft).
Physical protection in wood framing NEC 2026 Section 300.6(A)(1)
Per 300.4(A)(1) bored holes must have the edge of the hole not less than 32 mm (1-1/4 in.) from the edge of the wood member, and per 300.4(A)(2) cables or raceways laid in notches must be protected by a steel plate at least 1.6 mm (1/16 in.) thick.
Raceway sealing for condensation NEC 2026 Section 300.9(A)
Per 300.7(A), where portions of a raceway or sleeve are subjected to different temperatures and condensation is known to be a problem, the raceway or sleeve must be sealed to prevent circulation of warm air to a colder section.
Flexible cords and cables NEC 2026 Section 400.12(1)
Per 400.12, cords intended for temporary or portable equipment connections that shall not be used as a substitute for the fixed wiring of a structure.
Explosionproof NPT thread engagement NEC 2026 Section 500.8
Per 500.8(E)(1), NPT-threaded entries into explosionproof equipment must be made up with at least five threads fully engaged, except listed explosionproof equipment with factory-threaded NPT entries, which allows at least four and one-half threads fully engaged.
Supplemental grounding electrode bonding jumper NEC 2026 Section 250.53(E)
Per 250.53(E) (2026 NEC), where the supplemental electrode is a rod, pipe, or plate, the portion of the bonding jumper that is the sole connection to it is not required to be larger than 6 AWG copper (or 4 AWG aluminum/copper-clad aluminum).
120-percent rule busbar warning label NEC 2026 Section 705.12(B)(2)b
Per 705.12(B)(2)b, where the 120-percent rule is used for load-side busbar connections with two sources at opposite ends, a permanent label adjacent to the power source OCPD must read 'WARNING: POWER SOURCE OUTPUT. DO NOT RELOCATE THIS OVERCURRENT DEVICE.'
Small-appliance branch circuits NEC 2026 Section 210.11
Per 210.11(C)(1), two or more 20-ampere branch circuits that must be provided in dwelling units for all receptacle outlets specified by 210.52(B).
Household cooking appliance branch circuit NEC 2026 Section 210.19
Per 210.19(C), for ranges rated 8¾ kW or more the minimum branch-circuit rating is 40 amperes, and per Exception No. 1 conductors tapped from a branch circuit not exceeding 50 amperes supplying ranges, wall-mounted ovens, or counter-mounted cooking units must have an ampacity of at least 20 amperes and be sufficient for the load served.

Formulas to Know

Three-phase current from kVAI = (kVA × 1000) ÷ (E × √3), using √3 = 1.732 (e.g., 45,000 ÷ (480 × 1.732) = 54.13 A; 75,000 ÷ (208 × 1.732) = 208.2 A)
Minimum conductor ampacity / OCPD for continuous and noncontinuous loadsMinimum ampacity = 100% of noncontinuous load + 125% of continuous load (branch circuits per 210.19(A)(1), feeders per 215.2(A)(1)); then select the next standard OCPD size from 240.6(A). Exception: where a portion of a branch circuit is connected at both ends to separately installed pressure connections per 110.14(C)(2), ampacity not less than the simple sum of continuous + noncontinuous load is permitted.
Motor branch-circuit conductor ampacityAmpacity = 125% × FLC from Table 430.250 (use table FLC, not nameplate, per 430.6(A)(1)); then pick the conductor from Table 310.16 at the insulation's temperature column (THWN = 75°C) that meets or exceeds that ampacity.
Motor feeder conductor ampacityAmpacity = 125% × FLC of the largest motor + 100% of the FLC of all other motors (Table 430.250 values), plus other loads computed per their applicable articles (e.g., a continuous lighting load added at 125% per 215.2(A)(1)).
Motor overload protection maximum settingUse NAMEPLATE full-load amperes: 125% × nameplate FLA if service factor ≥ 1.15 or temperature rise not over 40°C; 115% × nameplate FLA for all other motors (e.g., temperature rise 46°C).
Motor disconnecting means minimum ratingRating = 115% × FLC from Table 430.250 (not nameplate current), per 430.110(A); for 480V motors use the 460V column.
Motor branch-circuit short-circuit and ground-fault protectionTime-delay (dual-element) fuse = 175% × Table 430.250 FLC; inverse-time circuit breaker = 250% × Table 430.250 FLC; where the result is not a standard rating, 430.52(C)(1) permits the next higher standard size from 240.6(A).
Portable power feeder cable / flexible cord ampacity correctionsCorrected ampacity = table ampacity × correction factor. Flexible cords/cables: Table 400.5(A)(2) ampacity × ambient temperature correction from Table 310.15(B)(2)(a) (e.g., 4/0 AWG 75°C three-conductor 277 A × 0.82 at 45°C ambient = 227.1 A). Portable power feeder cables rated over 2000 volts only (400.51(A)): ambient factor from Table 400.51(A)(2) (10°C/50°F = 1.26) and reel-winding factor from Table 400.51(A)(3) (2 layers on a reel = 0.65).
Flexible cord conductor count adjustmentAdjusted ampacity = Table 400.5(A)(1) Column A value × adjustment factor from Table 400.5(A)(3); for 4–6 current-carrying conductors the factor is 80% (e.g., 10 AWG Type S: 25 A × 0.80 = 20 A).
Conduit fill percentageFor more than two conductors and/or cables, permitted fill = 40% of the conduit's total cross-sectional area (Chapter 9, Table 1).