Estimación y Lectura de Planos
5 Q · 10%
Measuring and calculating roof area (level and sloped roofs)Roof slope and pitch calculations using slope factorsQuantity takeoff for specific roofing materials (shingles, tile, slate, metal panels, roll roofing)Estimating underlayment quantities including lap and overcut allowancesLabor unit pricing and production rate calculationsAdjusting published labor costs to actual crew wagesEstimating gutter, downspout, and accessory quantitiesWaste factors for roofing materials
Techado de Pendiente Pronunciada y Baja incluyendo BUR e Impermeabilización
18 Q · 36%
Asphalt shingle types, materials, and installation requirementsSteep slope roof underlayment types, configurations, and applicationBuilt-up roofing (BUR) components, bitumens, and installation methodsLow-slope membrane roof systems including polymer-modified bitumen, EPDM, and thermoplastic membranesClay, concrete, and slate tile roof systems including profiles, materials, and installationWood shake and wood shingle roof systems including grades, materials, and installationRigid board insulation types, R-values, and thermal performance for low-slope roofsFlashing, drainage, fire classification, and wind uplift requirements per IBC/IRC
Componentes de Techado
10 Q · 20%
Asphalt shingle types, materials, and UL fire/wind ratingsRoof deck types and sheathing requirements for steep-slope systemsUnderlayment types, configurations, and slope requirementsValley flashing and drip edge componentsWood shingles and shakes: grades, types, and installation requirementsClay, concrete, and slate tile types, profiles, and physical propertiesMetal roofing and siding materials, seam types, and panel systemsBuilt-up and elastomeric roofing membrane components and substrate requirements
Seguridad
5 Q · 10%
Fall protection requirements for roofing work (low-slope and steep roofs)Personal fall arrest systems: components, specifications, and proper useGuardrail systems: height, strength, and construction requirementsScaffold safety: capacity, platform construction, and fall protectionLadder and stairway safety requirementsFire protection and prevention on construction sitesPersonal protective equipment selection, use, and employer responsibilitiesAsbestos hazards in roofing and construction: identification, exposure limits, and work practices
Reparaciones y Retejado
7 Q · 14%
Reroofing terminology: re-covering vs. tear-off and replacement definitionsEvaluation of existing roof systems prior to reroofing (interior inspection, deck underside, perimeter, rooftop inspection)Roof deck condition assessment and moisture detection methods (core cuts, infrared thermography, nondestructive testing)Re-covering eligibility criteria by roof system type (asphalt shingle, metal shingle, slate, clay/concrete tile, wood shake/shingle, membrane)Flashing inspection and treatment during reroofing (base flashings, counterflashings, drip edge, penetration flashings)Building code requirements for reroofing under IBC and IRC (Section 1512 re-cover and replacement provisions, layer limits, fire classification)Repair techniques by roof covering type (asphalt shingle patching, wood shingle/shake replacement, slate nail-and-bib method, membrane repairs, tile repair)Identifying and locating roof leaks (attic inspection, water staining patterns, chimney/valley/vent flashing failures, miscellaneous leak sources)
Competent Person (OSHA) OSHA 1926 CFR 29, Page 31
Per OSHA 29 CFR 1926.32(f), one capable of identifying existing and predictable hazards who has authorization to take prompt corrective measures to eliminate them.
Fire Extinguisher Rating Requirement (OSHA) OSHA 1926.150(c)(1)(i)
Per OSHA 1926.150(c)(1)(i), a fire extinguisher rated not less than 2A must be provided for each 3,000 square feet of protected building area.
First Aid Kit Inspection Frequency (OSHA) OSHA 1926 CFR 29, Page 33
Per OSHA 1926.50, the contents of a first aid kit shall be checked before each job and at least weekly on each job to ensure expended items are replaced.
Qualified Equipment Operator (OSHA) OSHA 1926 CFR 29, Page 29
Per OSHA 1926.20(b)(4), only employees qualified by training or experience shall be permitted to operate equipment and machinery.
Danger Sign Specifications (OSHA) OSHA 1926 CFR 29, Page 201
Per OSHA 1926.200(b)(2), danger signs shall have red as the predominating color for the upper panel, black outline on borders, and a white lower panel for additional wording.
High Voltage Danger Sign (NEC) NEC 305.12
Per NEC 305.12, danger signs conspicuously posted at all access points to conductors in raceway and cable systems over 1000 volts must state: DANGER—HIGH VOLTAGE—KEEP OUT.
Qualified Person for Type MV Cable (NEC) NEC 315.30
Per NEC 315.30, installation and testing of Type MV cable must be performed by a qualified person with documented training and experience, and cable joints require qualified persons with documented MV joint training.
High-Voltage Conductor Termination in Buildings (NEC) NEC 235.412
Per NEC 235.412, where voltage exceeds 35,000 volts between conductors entering a building, they must terminate in a switchgear compartment or vault; they may not terminate at just any accessible location.
Raceways and Non-Electrical Pipes (NEC) NEC 300.8
Per NEC 300.8, raceways or cable trays containing electrical conductors shall not contain any pipe, tube, or equal for steam, water, air, gas, drainage, or any service other than electrical.
Drainage Fixture Unit (d.f.u.) International Residential Code, Page 667-668 (Section P3004.1, Table P3004.1)
A numerical factor assigned to plumbing fixtures representing the probable hydraulic discharge load used to compute and size DWV system piping per IRC P3004.1.
Branch Interval International Residential Code, Page 13 (Section R202, Definitions)
Per IRC Section R202, a vertical measurement of 8 feet or more in developed length between connections of horizontal branches to a drainage stack, measured downward from the highest horizontal branch.
Sweep (drainage fitting) International Residential Code, Page 25 (Section R202, Definitions)
Per IRC Section R202, a drainage fitting designed to change pipe direction with a longer turning radius than a bend, resulting in a less turbulent flow pattern.
Steel Shield Plate (pipe protection) IRC P2603.2.1
Per IRC P2603.2.1, when piping passes through structural members within 1½ inches of the nearest edge, a steel shield plate of minimum 0.0575 inch (No. 16 gauge) thickness is required.
Pipe Sleeve Through Foundation Wall International Residential Code, Page 620; International Plumbing Code, Page 3-2
Per IRC P2603.4 and IPC 305.3, a sleeve built into a foundation wall for a pipe passage must be two pipe sizes greater than the pipe passing through the wall.
Minimum Conductor Size for 8001–15,000V MV Cable NEC Table 315.12(A)
Per NEC Table 315.12(A), the minimum conductor size for Type MV cable rated 8001–15,000 volts is 2 AWG for copper, aluminum, or copper-clad aluminum.
Elevation Pressure Loss (water supply) IRC Appendix P, Section AP103.2.2
Per IRC Appendix P (AP103.2.2), static pressure loss due to elevation rise in a water supply system is calculated at 0.433 psi per foot of elevation change.