Exam Cheat Sheet · Quick Reference
Arkansas Concrete - Commercial Exam
Arkansas · PSI Services Contractor
Arkansas State Portion 30 questions
Key Distinctions
Plan view is a bird's-eye overhead view showing the layout of the work area, while profile view is a horizontal cut-away (cross-section) along the alignment showing elevations, grades and depths.
Pipe and Excavation Contracting, Page 105, Chapter 3 introduction, plan view/profile view definitionsA payment bond guarantees all bills for labor, equipment and materials are paid and liens discharged; a performance bond guarantees completion of the work.
Pipe and Excavation Contracting, Page 47For applying ACI 347R lateral pressure formulas, a column is a vertical element with no plan dimension larger than 6.5 ft (2 m), while a wall has at least one plan dimension exceeding 6.5 ft (2 m).
Contractor's Guide to Quality Concrete Construction (4th ed.), ACI 347R, Table 5.2 (Book Page 71)Form ties use a usual 2:1 safety factor (working load limited to one-half ultimate tensile strength), while form anchors into previously placed concrete require a minimum safety factor of 3 including live loads and impact because the concrete may still be 'green'.
Contractor's Guide to Quality Concrete Construction (4th ed.), Page 66A wheeled backhoe has a minimum effective digging cycle of about 10 seconds versus about 15 seconds for a small ¾-yard trackhoe (30 to 40 seconds for larger track excavators); in the book's 1,230-ft job example the track excavator produced 50 LCY/hr vs 29 LCY/hr for the backhoe but its mobilization cost (about 10 percent of total job cost) made it unattractive.
Pipe and Excavation Contracting, Page 168Average cut-to-fill haul distance selects the equipment: dozers for a short haul, self-loading scrapers for a longer haul, loaders and trucks for long-distance hauling, and graders for very slight cuts and fills.
Pipe and Excavation Contracting, Pages 270-271Calcium chloride is an effective set accelerator but promotes corrosion of reinforcing steel (and is not an effective antifreeze, lowering the freezing point only a few degrees), so non-chloride accelerators are the more appropriate choice for steel-reinforced concrete.
Design and Control of Concrete Mixtures, 17th ed., Chapter 6 - Chemical Admixtures for Concrete, Page 129 (16th ed.: Pages 222-223)A retarder delays setting and raises lateral form pressure (chemistry coefficient CC of 1.2 versus 1.0 without retarder) and requires lengthened form-stripping times because strength gain is slower.
Contractor's Guide to Quality Concrete Construction (4th ed.), Pages 72 and 82Escalation covers anticipated increases in labor, material and equipment costs between bid submission and performance/payment, while a contingency allowance covers possible problems from uncertain conditions (e.g., no boring logs) and cushions idle equipment rental costs.
Pipe and Excavation Contracting, Page 27Utility site plans use two scales; in the example of 1 in. = 40 ft horizontal and 1 in. = 10 ft vertical the horizontal is 4 times (4:1) the vertical, although usually the horizontal scale is ten times the vertical.
Pipe and Excavation Contracting, Page 109Under §1926.35(e)(3), an employer with 10 or fewer employees may communicate the emergency action plan orally and need not maintain a written plan.
OSHA 1926 CFR 29, §1926.35(e)(3)Per §1926.95(d)(2) the employer is not required to pay for non-specialty safety-toe protective footwear (steel-toe shoes/boots) and non-specialty prescription safety eyewear provided the employer permits them to be worn off the job site; other required PPE remains the employer's duty, and each failure to provide PPE to an employee may be a separate violation.
29 CFR 1926, Subpart E, §1926.95(d)(2)Key Terms
Formulas to Know
CY = trench length (ft) × trench width (ft) × bedding depth (ft) ÷ 27 (27 cubic feet per cubic yard)SY = length (ft) × width (ft) ÷ 9; example: 250 ft × 15 ft = 3,750 SF ÷ 9 ≈ 416 SYVolume = average of the four corner cut/fill depths × prism base area; example: (2.3 + 0.9 + 0.8 + 2.3) averaged = 1.58 ft × 2,500 SF = 3,950 cubic feetDistance = (number left of plus sign × 100 ft) + number right of plus sign; Sta 2+50 = 250 ft from Sta 0+00Spacing in feet = 2-1/2 × slab thickness in inches; example: 6 in. slab → 2-1/2 × 6 = 15 ftFor specified f'c of 5000 psi or less, no single test may fall below f'c by more than 500 psi; example: f'c = 4000 psi → 4000 − 500 = 3500 psi minimum, below which an investigation of structural adequacy is requiredNot more than one-third the depth of a slab and not more than one-fifth the narrowest dimension of a vertical member; example: 4 in. slab → 4 ÷ 3 ≈ 1-1/3 in. governs over 12 ÷ 5 = 2.4 in.Camber = 1/4 inch per 10 feet (6 mm per 3 m) of spanSafety factor 2:1 — working load of new ties limited to one-half the ultimate tensile strength (form anchors require a minimum safety factor of 3 including live loads and impact)When slump exceeds 7 in. (175 mm), CCP = wh (full hydrostatic head) regardless of element type, internal vibration depth or rate of placement; w for normalweight concrete ≈ 150 lb/ft³