Arkansas · PSI

Arkansas Concrete - Commercial Exam Practice Exam

30 questions 75 minutes 70% to pass 6 topics 2:30 per question Open book 131 questions in pool
Free Cheat Sheet Official Bulletin
Free

Free Practice Exam

$0

Test your knowledge with 10 questions from our pool of 20 free questions.

  • 10 questions per attempt
  • 30 minute time limit
  • Unlimited attempts
  • A new mix each time
  • Instant results
No account required.
Full Exam

Full Practice Exam

$9.95

Complete exam simulation matching the real PSI test format.

  • 30 questions (same as real exam)
  • 75 minute time limit
  • 6 topic areas covered
  • 131 questions in pool
  • Detailed explanations
Price per attempt. Never the same exam twice: each attempt draws a fresh set of questions.
Not sure which exam you need? Text us: (813) 582-5360
Texts preferred · 9am–9pm Central
Want a guided study plan? Study Course: topic briefs, 6 topic quizzes and this full exam, plus the Business and Law exam. $59.95/month.
See the study course

Arkansas Concrete - Commercial Practice Exam Guide

Built from the official PSI exam bulletin. View the bulletin

What's on the exam

Questions per topic, out of 30
General Concrete9
Layout and Excavation6
Formwork4
Reinforcing Steel4
OSHA Safety4
Estimating3

This practice exam is laid out like the official content outline for the Arkansas Concrete - Commercial exam: Estimating, Layout and Excavation, Formwork, Reinforcing Steel, General Concrete, OSHA Safety.

Two ways to practice: the free practice exam gives you 10 questions per attempt, as often as you want. The full practice exam gives you 30 questions on a 75 minutes clock, with a new draw from our question bank every time.

6 topics

Estimating 3 items

Layout and Excavation 6 items

Formwork 4 items

Reinforcing Steel 4 items

General Concrete 9 items

OSHA Safety 4 items

3 questions

Sample 1 — General Concrete

Question: You are a commercial concrete contractor planning a wall pour. Your project engineer asks where vertical construction joints in walls should be located when construction joints are not shown on the drawings. According to best practice, what is the maximum recommended horizontal length of a single concrete wall placement between vertical construction joints?

  • A. 40 ft
  • B. 20 ft
  • C. 30 ft
  • D. 50 ft

Correct Answer: A

According to The Contractor's Guide to Quality Concrete Construction, Chapter 7, a horizontal length of concrete placement greater than 40 ft (12 m) long in walls is not normally recommended for vertical construction joints.

Reference: Contractor's Guide to Quality Concrete Construction (4th ed.), Chapter 7 – Joints and Embedments in Structures, Page 113

Sample 2 — Layout and Excavation

Question: A perimeter foundation drain of gravel or crushed stone is being installed around a commercial basement foundation. How far beyond the outside edge of the footing must the drain extend?

  • A. 12 inches
  • B. 6 inches
  • C. 8 inches
  • D. 4 inches

Correct Answer: A

IBC Section 1805.4.2 requires the perimeter foundation drain to extend a minimum of 12 inches beyond the outside edge of the footing. The same section separately requires the top of the drain to be not less than 6 inches above the top of the footing and the pipe or tile to be bedded on not less than 2 inches of gravel or crushed stone.

Reference: IBC 2015 Chapter 18 — Section 1805.4.2 Foundation Drain

Sample 3 — Formwork

Question: In addition to standard cylinder break tests, which of the following is a recognized method for gauging in-place concrete strength by measuring the concrete's temperature over a period of time?

  • A. Pullout testing
  • B. Penetration resistance testing
  • C. Maturity meter testing
  • D. Rebound hammer testing

Correct Answer: C

According to the Contractor's Guide to Quality Concrete Construction, Chapter 5, maturity meters measure the temperature of the concrete over a period of time to calculate the strength. The text identifies pullout, penetration, and maturity meters as alternative methods to cylinder testing, but only the maturity meter method specifically works by measuring temperature over time. A correlation between the measured property and strength of the actual concrete mixture must be established prior to field testing.

Reference: Contractor's Guide to Quality Concrete Construction (4th ed.), Page 81

Your first attempt is an inspection, not a final grade. The results page breaks your score down by outline topic, so you can see which areas need work. Compare it with the real exam's passing score, 21 correct answers out of 30 scored questions, and keep practicing until you pass consistently.

  • Answer what you know first and bookmark the rest. Our practice exams let you bookmark and come back.
  • Work your bookmarks on the second pass.
  • Keep your pace. The real exam works out to about 2 minutes 30 seconds per question.
  • After each attempt, look up each missed question's reference in your book and read the section.

Questions 30 questions
Time limit 75 minutes
Passing score 21 correct answers out of 30 scored questions
Books in the exam room Open book

Source: Arkansas Contractors Licensing Board - Concrete Commercial, 10/17/2220. Check the bulletin before test day: fees and rules can change.

10 free questions30 min · no account