Arkansas Concrete - Commercial Exam Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 30 questions (same as real exam)
- 75 minute time limit
- 6 topic areas covered
- 131 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
Arkansas Concrete - Commercial Practice Exam Guide
What's on the exam
Questions per topic, out of 30This practice exam is laid out like the official content outline for the Arkansas Concrete - Commercial exam: Estimating, Layout and Excavation, Formwork, Reinforcing Steel, General Concrete, OSHA Safety.
Two ways to practice: the free practice exam gives you 10 questions per attempt, as often as you want. The full practice exam gives you 30 questions on a 75 minutes clock, with a new draw from our question bank every time.
Estimating 3 items
Layout and Excavation 6 items
Formwork 4 items
Reinforcing Steel 4 items
General Concrete 9 items
OSHA Safety 4 items
Sample 1 — General Concrete
Question: You are a commercial concrete contractor planning a wall pour. Your project engineer asks where vertical construction joints in walls should be located when construction joints are not shown on the drawings. According to best practice, what is the maximum recommended horizontal length of a single concrete wall placement between vertical construction joints?
- A. 40 ft
- B. 20 ft
- C. 30 ft
- D. 50 ft
Correct Answer: A
According to The Contractor's Guide to Quality Concrete Construction, Chapter 7, a horizontal length of concrete placement greater than 40 ft (12 m) long in walls is not normally recommended for vertical construction joints.
Reference: Contractor's Guide to Quality Concrete Construction (4th ed.), Chapter 7 – Joints and Embedments in Structures, Page 113
Sample 2 — Layout and Excavation
Question: A perimeter foundation drain of gravel or crushed stone is being installed around a commercial basement foundation. How far beyond the outside edge of the footing must the drain extend?
- A. 12 inches
- B. 6 inches
- C. 8 inches
- D. 4 inches
Correct Answer: A
IBC Section 1805.4.2 requires the perimeter foundation drain to extend a minimum of 12 inches beyond the outside edge of the footing. The same section separately requires the top of the drain to be not less than 6 inches above the top of the footing and the pipe or tile to be bedded on not less than 2 inches of gravel or crushed stone.
Reference: IBC 2015 Chapter 18 — Section 1805.4.2 Foundation Drain
Sample 3 — Formwork
Question: In addition to standard cylinder break tests, which of the following is a recognized method for gauging in-place concrete strength by measuring the concrete's temperature over a period of time?
- A. Pullout testing
- B. Penetration resistance testing
- C. Maturity meter testing
- D. Rebound hammer testing
Correct Answer: C
According to the Contractor's Guide to Quality Concrete Construction, Chapter 5, maturity meters measure the temperature of the concrete over a period of time to calculate the strength. The text identifies pullout, penetration, and maturity meters as alternative methods to cylinder testing, but only the maturity meter method specifically works by measuring temperature over time. A correlation between the measured property and strength of the actual concrete mixture must be established prior to field testing.
Reference: Contractor's Guide to Quality Concrete Construction (4th ed.), Page 81
Your first attempt is an inspection, not a final grade. The results page breaks your score down by outline topic, so you can see which areas need work. Compare it with the real exam's passing score, 21 correct answers out of 30 scored questions, and keep practicing until you pass consistently.
- Answer what you know first and bookmark the rest. Our practice exams let you bookmark and come back.
- Work your bookmarks on the second pass.
- Keep your pace. The real exam works out to about 2 minutes 30 seconds per question.
- After each attempt, look up each missed question's reference in your book and read the section.
| Questions | 30 questions |
| Time limit | 75 minutes |
| Passing score | 21 correct answers out of 30 scored questions |
| Books in the exam room | Open book |
Source: Arkansas Contractors Licensing Board - Concrete Commercial, 10/17/2220. Check the bulletin before test day: fees and rules can change.