Key Distinctions
Open-cell semirigid water-blown polyurethane foam is R-3.81 per inch and expands up to 120 times its liquid volume, while closed-cell SPF is R-6 to R-7 per inch and expands at an average ratio of about 30:1 (or more), because open-cell cells hold air rather than a blowing agent.
Insulation Handbook (2001), Chapter 10 - Foamed-in-Place Insulation, Open-cell SPF sectionXPS holds a consistent R-value of 5.0 per inch regardless of density and has greater compressive strength suited for below-grade foundation walls, while EPS R-value varies with density (PIR varies with facer type; cellular glass is stable but lower).
Insulation Handbook (2001), Chapter 11 - Rigid Board InsulationCellulose absorbs 5 to 20 percent of its weight in moisture (a listed disadvantage), whereas fiberglass and rock wool absorb less than 1 percent of their weight.
Insulation Handbook (2001), Chapter 7 - Loose-Fill Insulation, Cellulose sectionMore than 90 percent of moisture entering a perimeter structural cavity comes from air leakage, with the other 10 percent or less from vapor diffusion.
Insulation Handbook (2001), Chapter 4 - Vapor and Air RetardersPerlite is bagged and must be poured into place (widely poured into concrete block cavities in masonry construction) and is not suitable for blow-in installation methods.
Insulation Handbook (2001), Chapter 7 - Loose-Fill InsulationThe 'C' suffix cathedral-ceiling superbatt is 8¼ to 8½ inches thick so it fits nominal 2×10 framing while keeping the required 1-inch ventilation airspace, versus 9½ to 10 inches for a standard R-30 batt.
Insulation Handbook (2001), Chapter 8 - Blanket Insulation: Batts and RollsFor 2×4 walls low-density batts are usually rated R-11 and high-density batts R-15; low-density batts for 2×6 walls are rated R-19.
Carpentry and Building Construction, Section 31.1 — Fiberglass Insulation R-ValueCellulose loose-fill is approximately R-3.5 per inch, fiberglass loose-fill approximately R-2.5 per inch, and rock wool approximately R-3.2 per inch.
Carpentry and Building Construction, Section 31.1 — Loose-Fill Insulation Materials and R-ValueCollar ties at every rafter pair are required only when they support a ceiling; when used only structurally they attach to every fourth rafter pair at 16" OC spacing and every third rafter pair at 24" OC spacing.
Carpentry and Building Construction, Section 19.3, Page 542The number before the slash is the maximum spacing of supports in inches for roof sheathing use; the number after the slash is the maximum spacing for subflooring use.
Carpentry and Building Construction, Section 19.5, Pages 562-563Walls with studs 16" OC need sheathing at least ⅜" thick (½" is more common), but where finish siding requires nailing between studs (as with wood shingles) the sheathing should be at least ⅝" thick.
Carpentry and Building Construction, Section 16.1, Page 435Under §1926.35(e)(3), employers with 10 or fewer employees may communicate the plan orally and need not maintain a written plan.
OSHA 1926 CFR 29, §1926.35(e)(3)Class B covers grease, oil and chemical fires; Class A covers wood, paper, cloth and plastic; Class C covers electrical equipment; Class D covers combustible metals (combination ratings such as A:B or A:B:C also serve Class B fires).
Carpentry and Building Construction, Construction Safety & Health, Page 81A closed cornice is seldom used on newer houses because the absence of overhang eliminates the usual soffit-vent location, making adequate attic ventilation difficult.
Carpentry and Building Construction, Section 19.4, Page 552Key Terms
Formulas to Know
U = 1/R; example: R-20 assembly → U = 1/20 = 0.05 (lower U-value = better insulating value)Total R = (R-value per inch) × (inches); example: 2 in. of R-5 per inch = R-101 sq ft of net venting per 150 sq ft of crawl-space area; example: 1,200 ÷ 150 = 8 sq ft (crawl space had a vapor retarder over the soil)Panels = roof area ÷ 32 sq ft per panel, then add 5% for trim and waste; worked example: 72.19 × 0.05 = 3.6; 72.19 + 3.6 = 75.79 → 76 sheets(roof surface area ÷ 100) × table board-feet per 100 sq ft; worked example: 2×6 rafters at 16" OC = 102 bf/100 sq ft, 2,100 ÷ 100 = 21, 21 × 102 = 2,142 board feetMeasure 3 ft along one leg and 4 ft along the other; the diagonal must be exactly 5 ft for a 90° corner — a reading such as 5 ft 1 in. means adjust one layout line until it measures 5 ft before marking remaining wallsPer §1926.51(c)(1) Table D-1: 20 or fewer employees → minimum of 1 facilityAn anchor bolt must fall within 12 inches (maximum) of the end of each section of bottom plate