Arkansas Insulation - Commercial Exam Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 30 questions (same as real exam)
- 75 minute time limit
- 7 topic areas covered
- 129 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
Arkansas Insulation - Commercial Practice Exam Guide
What's on the exam
Questions per topic, out of 30This practice exam is built around the official content outline for the Arkansas Insulation - Commercial exam: General Knowledge and Theory, Spray-On Application, Batt / Roll Insulation, Blown or Loose- Fill Insulation, Rigid-Board and Reflective Insulation, Vapor Retarders, OSHA Safety.
There are two ways to practice. The free practice exam gives you 10 questions per attempt, and you can take it as many times as you like. The full practice exam gives you 30 questions on a 75 minutes clock, with a new draw from our question bank each time.
General Knowledge and Theory 8 items
Spray-On Application 3 items
Batt / Roll Insulation 5 items
Blown or Loose- Fill Insulation 3 items
Rigid-Board and Reflective Insulation 2 items
Vapor Retarders 4 items
OSHA Safety 5 items
Sample 1 — General Knowledge and Theory
Question: What is the maximum theoretical R-value per inch that any air-based insulation material, such as fiberglass batt, can achieve?
- A. R-3.8 per inch
- B. R-5.5 per inch
- C. R-4.0 per inch
- D. R-6.5 per inch
Correct Answer: B
According to Chapter 3, any air-based insulation material such as fiberglass batt cannot exceed a theoretical maximum R-value of R-5.5 per inch because 5.5 is the R-value of still air. Plastic foams such as urethane and polystyrene sometimes exceed this value by using a fluorocarbon gas instead of air within the insulation cells.
Reference: Insulation Handbook (2001), Chapter 3 - Insulation Fundamentals and Principles
Sample 2 — Batt / Roll Insulation
Question: You are installing two layers of batt insulation in an attic to achieve R-49. The first layer is R-30 faced insulation installed between the joists. How should the second R-19 layer be oriented?
- A. Faced, perpendicular to the joists
- B. Unfaced, parallel to the joists
- C. Unfaced, perpendicular to the joists
- D. Faced, parallel to the joists
Correct Answer: C
When installing a second layer in an attic, always use unfaced insulation because using a second vapor retarder will trap moisture between the two layers. It is also recommended that the second layer be applied across (perpendicular to) the joists in open attic spaces.
Reference: Insulation Handbook (2001), Chapter 8 - Blanket Insulation: Batts and Rolls
Sample 3 — OSHA Safety
Question: When selecting respiratory protection for construction work involving very fine dust particles, such as cutting concrete or masonry, which type of protection is required instead of a standard dust mask?
- A. A dust respirator or full respirator
- B. A standard surgical mask
- C. A self-contained breathing apparatus
- D. A cotton bandana rated for particulates
Correct Answer: A
A standard dust mask can filter out large particles such as sawdust but cannot protect against very fine dust. For very fine dust, such as that created when cutting concrete or masonry, a dust respirator or full respirator is required. Respirators should be approved by the National Institute for Occupational Safety and Health (NIOSH) and contain replaceable filter cartridges designed for the specific hazard.
Reference: Carpentry and Building Construction, Chapter 3 — Respiratory Protection section (Book Page 95-96)
Your first score is just a starting point. After every attempt, the results page shows how you did on each outline topic, so you can see what to work on next. Compare your score with the real exam's passing score, 21 correct answers out of 30 scored questions, and keep at it until you pass consistently.
- Start with the questions you know. Go through the whole exam once and bookmark anything you're unsure about. Our practice exams let you bookmark and come back.
- Circle back to your bookmarks on the second pass.
- Keep an eye on your pace. The real exam works out to about 2 minutes 30 seconds per question.
- Turn every miss into a lesson. After each attempt, look up each missed question's reference in your book and read the section.
| Questions | 30 questions |
| Time limit | 75 minutes |
| Passing score | 21 correct answers out of 30 scored questions |
| Books in the exam room | Open book |
Source: Arkansas Contractors Licensing Board - Insulation - Commercial, 3/5/2020. Check the bulletin before test day: fees and rules can change.