Arkansas · PSI

Arkansas Insulation - Commercial Exam Practice Exam

30 questions 75 minutes 70% to pass 7 topics 2:30 per question Open book 129 questions in pool
Free Cheat Sheet Official Bulletin
Free

Free Practice Exam

$0

Test your knowledge with 10 questions from our pool of 20 free questions.

  • 10 questions per attempt
  • 30 minute time limit
  • Unlimited attempts
  • A new mix each time
  • Instant results
No account required.
Full Exam

Full Practice Exam

$9.95

Complete exam simulation matching the real PSI test format.

  • 30 questions (same as real exam)
  • 75 minute time limit
  • 7 topic areas covered
  • 129 questions in pool
  • Detailed explanations
Price per attempt. Never the same exam twice: each attempt draws a fresh set of questions.
Not sure which exam you need? Text us: (813) 582-5360
Texts preferred · 9am–9pm Central
Want a guided study plan? Study Course: topic briefs, 7 topic quizzes and this full exam, plus the Business and Law exam. $59.95/month.
See the study course

Arkansas Insulation - Commercial Practice Exam Guide

Built from the official PSI exam bulletin. View the bulletin

What's on the exam

Questions per topic, out of 30
General Knowledge and Theory8
Batt / Roll Insulation5
OSHA Safety5
Vapor Retarders4
Spray-On Application3
Blown or Loose- Fill Insulation3
Rigid-Board and Reflective Insulation2

This practice exam is built around the official content outline for the Arkansas Insulation - Commercial exam: General Knowledge and Theory, Spray-On Application, Batt / Roll Insulation, Blown or Loose- Fill Insulation, Rigid-Board and Reflective Insulation, Vapor Retarders, OSHA Safety.

There are two ways to practice. The free practice exam gives you 10 questions per attempt, and you can take it as many times as you like. The full practice exam gives you 30 questions on a 75 minutes clock, with a new draw from our question bank each time.

7 topics

General Knowledge and Theory 8 items

Spray-On Application 3 items

Batt / Roll Insulation 5 items

Blown or Loose- Fill Insulation 3 items

Rigid-Board and Reflective Insulation 2 items

Vapor Retarders 4 items

OSHA Safety 5 items

3 questions

Sample 1 — General Knowledge and Theory

Question: What is the maximum theoretical R-value per inch that any air-based insulation material, such as fiberglass batt, can achieve?

  • A. R-3.8 per inch
  • B. R-5.5 per inch
  • C. R-4.0 per inch
  • D. R-6.5 per inch

Correct Answer: B

According to Chapter 3, any air-based insulation material such as fiberglass batt cannot exceed a theoretical maximum R-value of R-5.5 per inch because 5.5 is the R-value of still air. Plastic foams such as urethane and polystyrene sometimes exceed this value by using a fluorocarbon gas instead of air within the insulation cells.

Reference: Insulation Handbook (2001), Chapter 3 - Insulation Fundamentals and Principles

Sample 2 — Batt / Roll Insulation

Question: You are installing two layers of batt insulation in an attic to achieve R-49. The first layer is R-30 faced insulation installed between the joists. How should the second R-19 layer be oriented?

  • A. Faced, perpendicular to the joists
  • B. Unfaced, parallel to the joists
  • C. Unfaced, perpendicular to the joists
  • D. Faced, parallel to the joists

Correct Answer: C

When installing a second layer in an attic, always use unfaced insulation because using a second vapor retarder will trap moisture between the two layers. It is also recommended that the second layer be applied across (perpendicular to) the joists in open attic spaces.

Reference: Insulation Handbook (2001), Chapter 8 - Blanket Insulation: Batts and Rolls

Sample 3 — OSHA Safety

Question: When selecting respiratory protection for construction work involving very fine dust particles, such as cutting concrete or masonry, which type of protection is required instead of a standard dust mask?

  • A. A dust respirator or full respirator
  • B. A standard surgical mask
  • C. A self-contained breathing apparatus
  • D. A cotton bandana rated for particulates

Correct Answer: A

A standard dust mask can filter out large particles such as sawdust but cannot protect against very fine dust. For very fine dust, such as that created when cutting concrete or masonry, a dust respirator or full respirator is required. Respirators should be approved by the National Institute for Occupational Safety and Health (NIOSH) and contain replaceable filter cartridges designed for the specific hazard.

Reference: Carpentry and Building Construction, Chapter 3 — Respiratory Protection section (Book Page 95-96)

Your first score is just a starting point. After every attempt, the results page shows how you did on each outline topic, so you can see what to work on next. Compare your score with the real exam's passing score, 21 correct answers out of 30 scored questions, and keep at it until you pass consistently.

  • Start with the questions you know. Go through the whole exam once and bookmark anything you're unsure about. Our practice exams let you bookmark and come back.
  • Circle back to your bookmarks on the second pass.
  • Keep an eye on your pace. The real exam works out to about 2 minutes 30 seconds per question.
  • Turn every miss into a lesson. After each attempt, look up each missed question's reference in your book and read the section.

Questions 30 questions
Time limit 75 minutes
Passing score 21 correct answers out of 30 scored questions
Books in the exam room Open book

Source: Arkansas Contractors Licensing Board - Insulation - Commercial, 3/5/2020. Check the bulletin before test day: fees and rules can change.

Reference books

3 books on the bulletin
As an Amazon Associate we earn from qualifying purchases.
10 free questions30 min · no account