Exam Cheat Sheet · Quick Reference
Arkansas Roofing/Roof Decks - Residential Exam
Arkansas · PSI Services Contractor
Arkansas State Portion 30 questions
Key Distinctions
The positive method divides an irregular roof into rectangles and adds their areas, while the negative method extends the roof lines into one large rectangle and subtracts the areas that are not roof; both give identical results.
Roofing Construction and Estimating, Chapter 1, Pages 7-8Fiberglass shingles use a fiberglass base mat saturated and coated with flexible asphalt and surfaced with mineral granules, whereas organic shingles use a cellulose-fiber base mat.
Roofing Construction and Estimating, Chapter 4—Asphalt ShinglesOn wood plank or board decks nails must penetrate at least ¾ inch into the deck, while on plywood/wood panel decks less than ¾ inch thick nails must extend a minimum of ⅛ inch through the underside.
NRCA Roofing Manual: Steep-slope Roof Systems (2025), Section 4.2—Asphalt Shingle Roof System Design and Installation (Fasteners)A common rafter (90° to the ridge) always has a unit run of 12 inches, while a rafter at a 45° angle to the ridge has a unit run of 17 inches.
Carpentry and Building Construction, Section 17.1, Page 470IBC 2024 and IRC 2024 prescribe a single layer of mechanically attached underlayment for asphalt shingle systems on slopes of 4:12 or greater outside high-wind regions, but a double layer on slopes from 2:12 to 4:12 outside high-wind regions.
NRCA Roofing Manual: Steep-slope Roof Systems (2025), Section 3.2—Underlayment Design and InstallationFull-length three-tab strip shingles require a minimum of four roofing nails per strip under normal conditions, while six nails per strip may be required by local codes in high-wind areas and are recommended by NRCA (with hand-tabbing) on slopes of 18:12 and greater.
NRCA Roofing Manual: Steep-slope Roof Systems (2025), Section 4.2—Asphalt Shingle Roof System Design and InstallationTemporary bracing serves during initial installation (the gable-end truss is braced first with lumber standoffs anchored to ground stakes), while permanent bracing keeps the bottom chords of long-span trusses from moving as the ceiling finish is applied.
Carpentry and Building Construction, Chapter 17 Review, Page 501The number in front of the slash is the maximum spacing of supports in inches for roof sheathing use; the number after the slash is the maximum support spacing for subflooring use.
Carpentry and Building Construction, Section 19.5, Pages 562-563Carpentry and Building Construction states eaves protection should reach at least 22 inches inside the exterior wall line, while IRC 2024 Section R905.1.2 / IBC 1507.1.2 and the NRCA Manual require not less than 24 inches (measured in the level plane) inside the exterior wall line — on a code question use 24 inches.
Carpentry and Building Construction, Section 22.1 — Eaves Protection / Placement of Eaves FlashingBattens can be installed on tile roof slopes of 2½ in 12 and steeper, but they are required on slopes of 7 in 12 and steeper.
Roofing Construction and Estimating, Chapter 7 — Tile RoofingASTM C1167 is the product standard clay roof tile must comply with (IRC 2024 R905.3.4 / IBC 1507.3.4), while ASTM C1492 is the standard for concrete tile.
NRCA Roofing Manual: Steep-slope Roof Systems (2025), Clay and Concrete Tile Roof Systems, Appendix 1—Building Code Compliance for Clay and Concrete Tile Roof SystemsClass A covers fires involving wood, paper, cloth and plastic, while Class B covers grease, oil and chemical fires (Class C is electrical equipment; Class D is combustible metals).
Carpentry and Building Construction, Construction Safety & Health, Page 81A closed cornice has no rafter overhang and is seldom used on newer houses because adequate attic ventilation (soffit venting) is difficult to provide.
Carpentry and Building Construction, Section 19.4, Page 552Key Terms
Formulas to Know
Total daily crew cost ÷ daily crew production (squares). Example: 8 hrs × ($25.00 roofer + $10.00 laborer = $35.00/hr) = $280.00; $280.00 ÷ 6.37 squares = $43.96 per square (Equation 14-1).Slope = (Total Rise ÷ Total Run) × 12. Example: 7'6" = 7.5 ft; (7.5 ÷ 15) × 12 = 6, i.e., 6 in 12.Actual rafter length = Run × roof-slope factor (Column 2 of the conversion factor table). Example: 14 ft × 1.202 = 16.83 linear feet on an 8 in 12 slope.Actual valley length = Run of the low-sloping roof × valley length factor (Appendix B). Example: 24 ft × 1.247 = 29.93 linear feet.Plan length = 1.414 × run (1.414 = √2, for the 45° plan angle). Example: 1.414 × 14 ft = 19.80 feet.Allowance factor = Gross area including allowances ÷ Net roof area. Example: 18 squares ÷ 15 squares = 1.20 (a 20 percent allowance).Area = Extended large rectangle − areas that are not roof. Example: (80 × 50 = 4,000 SF) − [(20 × 15 = 300) + (10 × 15 = 150) = 450 SF] = 3,550 SF.Board feet = (Roof surface area ÷ 100) × table board feet per 100 SF. Example: 2×6 rafters at 16" OC = 102 bf per 100 SF; 2,100 ÷ 100 = 21; 21 × 102 = 2,142 board feet (includes common rafters, hip and valley rafters, ridge boards and collar ties).Panels = total roof area ÷ 32 SF per panel, then add 5 percent for trim and waste. Example: 72.19 × 0.05 = 3.6; 72.19 + 3.6 = 75.79, rounded up to 76 sheets.Metal gutters must slope at least 1 inch every 16 feet (1/16 inch per foot) toward the downspout; the maximum distance from the gutter high point to the downspout should not ordinarily exceed 25 feet. Example: 32 ft × 1/16 = 2 inches of total drop.