Exam Cheat Sheet · Quick Reference

ICC G15 Shingle Roofing Exam (2018 IBC/IRC)

National  ·  Pearson Vue

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
60
Passing score
70%
Exam time
150 min
Administered by
Pearson Vue
Format
Reference materials allowed

National State Portion 60 questions

Job Planning and Setup 11 Q · 18%
Permits, inspections and code applicability for roofing workRoofing definitions (roof covering, roof deck, underlayment, reroofing, recover)Roof deck requirements and weather protectionMinimum roof slope by steep-slope coveringFire classification of roof coveringsWind resistance and high-wind requirements for shingles and tileUnderlayment selection by slope and wind speedIce barrier requirements
Types of Roofing Material and Application 14 Q · 23%
Asphalt shingles: slope, underlayment, fastening and applicationWood shingles: slope, exposure, spacing and applicationWood shakes: slope, interlayment, exposure and applicationSlate shingles: slope, headlap and applicationClay and concrete tile: slope, underlayment, attachmentMetal roof shingles and metal roof panels: slope and attachmentMaterial standards and labeling for steep-slope coverings
Fasteners, Flashings, Scuppers, Etc. 19 Q · 32%
Fastener type, length and deck penetration by coveringFastener count per shingle and high-wind fasteningValley linings and valley flashingDrip edgeStep, sidewall and kickout flashingChimney and penetration flashing, crickets and saddlesRoof drainage, gutters and scuppersIce barrier at eaves
Re-roofing 16 Q · 27%
Roof recover vs roof replacementConditions prohibiting roof recover (layers, water-soaked, slate/tile)Reinstallation of existing materials (slate, tile, flashings)Flashing replacement during reroofingStructural and load considerations when reroofingRepairing roof-ceiling framing and deck before reroofing

Key Distinctions

Wood shakesvsWood shingles

Per IBC 1507.9.5 and Table 1507.8, wood shakes require interlayment complying with ASTM D226, Type I, while Table 1507.8 lists 'No requirements' for interlayment under wood shingles (two fasteners per unit, solid sheathing in icing areas and bundle labeling apply to both).

IBC 2018 Pages 352 to 353
Wood shake spacing in same course (IRC R905.8.6)vsWood shingle spacing in same course (IRC R905.7.5)

IRC R905.8.6 requires 3/8 inch to 5/8 inch between wood shakes in the same course including tapersawn shakes, while IRC R905.7.5 sets 1/4 inch to 3/8 inch for wood shingles. (Under IBC 1507.9.8 the 3/8-to-5/8-inch spacing covers shakes and taper sawn shakes of naturally durable wood only; preservative-treated taper sawn shakes are 1/4 to 3/8 inch.)

IRC 2018 Page 440
Taper sawn shakes of naturally durable woodvsPreservative-treated taper sawn shakes

IBC 1507.9.8 requires 3/8 to 5/8 inch spacing between shakes in the same course for shakes and taper sawn shakes of naturally durable wood, but 1/4 to 3/8 inch only for preservative-treated taper sawn shakes.

IBC 2018 Page 353
Asphalt shingle roofing nails (IRC R905.2.5)vsClay/concrete tile nails (IRC R905.3.6)

Asphalt shingle nails are minimum 12 gage [0.105 inch] shank with minimum 3/8-inch-diameter head complying with ASTM F1667, while tile nails are corrosion resistant, not less than 11 gage with a 7/16-inch head.

IRC Section R905.2.5
Ring shank cap nails for underlaymentvsSmooth shank cap nails for underlayment

Shank shall be not less than 0.083 inch for ring shank cap nails and not less than 0.091 inch for smooth shank cap nails (IRC R905.1.1 Exception 3.4; IBC 1507.1.1 Exception 3 / Table 1507.1.1(3) for V ≥ 140 mph).

IRC 2018 Page 436
Splash diverter rib — clay and concrete tile valley flashingvsSplash diverter rib — metal roof shingle valley flashing

Clay/concrete tile valley flashing requires a rib not less than 1 inch high at the flow line (IBC 1507.3.9; IRC R905.3.8), while metal roof shingle valley flashing requires a rib not less than 3/4 inch high (IBC 1507.5.7; IRC R905.4.6).

IBC 2018 Section 1507.3.9
ASTM D7158vsASTM D3161

ASTM D7158 is the primary required wind-resistance test for asphalt shingles with packaging labeled to the resulting classification, while ASTM D3161 is used under the exception only for shingles not within the scope of D7158 (and is the wind test for photovoltaic shingles per IRC R905.16.6).

IBC 2018 Page 342
ASTM D3462vsASTM D7158 / D3161

ASTM D3462 is the asphalt shingle product (material) standard required by IBC 1507.2.4 and IRC R905.2.4, whereas D7158 and D3161 are the wind-resistance test standards.

IBC 2018 Section 1507.2.4 (Asphalt shingles)
Above-deck thermal insulation — IBC 1508.1vsAbove-deck thermal insulation — IRC R906.1

IBC permits above-deck insulation covered with an approved roof covering where it passes NFPA 276 or UL 1256 tested as an assembly, while IRC permits it where covered with an approved roof covering and complying with FM 4450 or UL 1256.

IBC 2018 Page 356
Sidewall base/step flashing (IRC R905.2.8.3)vsFront wall, soil stack, vent pipe and chimney flashing (IRC R905.2.8.4)

Base flashing against a vertical sidewall has code-prescribed minimum dimensions (4 inches high by 4 inches wide), while flashing against a vertical front wall, soil stack, vent pipe and chimney is applied in accordance with the asphalt shingle manufacturer's printed instructions.

IRC 2018 Sections R905.2.8.3 and R905.2.8.4
Wood shingle valley flashing extension (IRC R905.7.6)vsWood shake valley flashing extension (IRC R905.8.8)

Wood shingle valley flashing extends 10 inches from the centerline each way for slopes less than 12:12 and 7 inches each way at 12:12 and greater, while wood shake valley flashing (No. 26 gage minimum) extends not less than 11 inches from the centerline each way; metal roof shingle valleys extend 8 inches.

IRC 2018 Section R905.7.6
Existing materials permitted to be reinstalledvsAggregate surfacing materials

Per IBC 1511.5, existing slate, clay or cement tile may be reinstalled if not damaged, cracked or broken and existing vent flashing, metal edgings, drain outlets, collars and metal counterflashings may be reinstalled unless rusted, damaged or deteriorated, but aggregate surfacing materials shall not be reinstalled under any condition.

IBC 2018 Section 1511.5
Appointment of the building official (IBC 103.2)vsAppointment of deputies, inspectors and plan examiners (IBC 103.3)

The building official is appointed by the chief appointing authority of the jurisdiction, while the building official appoints deputy building officials, technical officers, inspectors, plan examiners and other employees with the concurrence of the appointing authority.

IBC 2018 Section 103.3 (with Section 103.2)

Key Terms

Roof assembly (2018 IRC Chapter 2) IRC 2018 Chapter 2 — definition of ROOF ASSEMBLY
A system designed to provide weather protection and resistance to design loads that includes the roof deck, underlayment and roof covering, and can also include a thermal barrier, ignition barrier, insulation or a vapor retarder.
Annual permit (IBC 105.1.1) IBC 2018 Section 105.1.1 (with Section 105.1.2)
A permit the building official is authorized to issue in place of an individual permit for each alteration to an already approved electrical, gas, mechanical or plumbing installation, issued to a person, firm or corporation regularly employing one or more qualified tradepersons, with the holder required by IBC 105.1.2 to keep a detailed record of alterations made.
Product identification for bulk shipments (IBC 1506.3) IBC 2018 Section 1506.3
Roof-covering materials must be delivered in packages bearing the manufacturer's identifying marks and approved testing agency labels required by Section 1505, and bulk shipments must be accompanied by that same information issued as a certificate or on a bill of lading by the manufacturer.
Cricket or saddle (IBC 1503.5) IBC 2018 Section 1503.5 Exception
A diverter required on the ridge side of any roof penetration greater than 30 inches wide, except that unit skylights installed per Section 2405.5 and flashed per the manufacturer's instructions may be installed without one.
Drip edge IBC 2018 Section 1507.2.8.3
Edge flashing at eaves and rakes that per IBC 1507.2.8.3 is mechanically fastened at intervals not greater than 12 inches on center with adjacent segments lapped not less than 2 inches and a vertical leg not less than 1 1/2 inches, and per IRC R905.2.8.5 extends not less than 1/4 inch below the roof sheathing and not less than 2 inches back onto the roof deck.
Interlayment (wood shakes) IBC 2018 Pages 352 to 353
18-inch-wide strips of not less than No. 30 felt (ASTM D226, Type I per IBC Table 1507.8) laid between shake courses; IBC Table 1507.8 lists 'No requirements' for interlayment under wood shingles.
Attaching wire (IBC 1507.3.6) IBC 2018 Section 1507.3.6
Wire used to secure clay or concrete tile, which shall not be smaller than 0.083 inch (2.1 mm).
Above-deck radiant barrier (IBC 1509.3) IBC 2018 Page 356
A barrier installed above the roof deck whose low emittance surface must face the continuous airspace between the radiant barrier and the roof covering.
Aerial supports (IBC 1510.8.1) IBC 2018 Page 358
Roof-deck-mounted supports required to be of noncombustible materials, with an exception permitting combustible construction where the supports are not greater than 12 feet in height measured from the roof deck to the highest point on the supports.
Special purpose wood shingle or shake roof (IBC 1505.7) IBC 2018 Page 344
A roof requiring an underlayment of 5/8-inch Type X water-resistant gypsum backing board or gypsum sheathing placed under minimum nominal 1/2-inch-thick wood structural panel solid sheathing or 1-inch nominal spaced sheathing.
Open valley lining (IBC 1507.2.8.2, Item 1) IBC 2018 Page 347
For asphalt shingle open valleys lined with metal, the valley lining shall be not less than 24 inches wide and of a corrosion-resistant metal listed in Table 1507.2.8.2 (18 inches applies to the two-ply mineral-surfaced roll roofing option and 36 inches to closed valley lining).
Slate shingle valley flashing (IBC 1507.7.7) IBC 2018 Page 351
Sheet metal valley flashing not less than 15 inches wide with a minimum uncoated thickness of 0.0179 inch zinc-coated G90.
Slate cap flashing at chimneys and masonry walls (IBC 1507.7.7) IBC 2018 Section 1507.7.7
Not fewer than two plies of felt, with a 4-inch-wide strip of felt set in plastic cement extending 1 inch above the first felt and topped with plastic cement, the felt extending over the base flashing 2 inches.
Building-integrated photovoltaic (BIPV) roof panels IRC 2018 Page 444
Roof panels that per IRC R905.17.7 shall be tested in accordance with UL 1897 with packaging labeled to show that compliance (UL 1703 is the listing and labeling standard per R905.17.5), and whose underlayment in high-wind areas (Vasd greater than 110 mph) must be fastened along the overlap at not more than 36 inches on center per IBC 1507.18.4.1.
Flashing locations (IBC 1503.2.1) IBC 2018 Section 1503.2.1
Flashing shall be installed at wall and roof intersections, at gutters, wherever there is a change in roof slope or direction and around roof openings; where the flashing is metal it must be corrosion resistant and not less than 0.019 inch (No. 26 galvanized sheet) thick.
Wood shingle weather exposure (IBC Table 1507.8.7) IBC 2018 Section 1507.8.7 and Table 1507.8.7 (Wood shingle weather exposure and roof slope)
Maximum permitted wood shingle exposures are divided between '3:12 pitch to less than 4:12' and '4:12 pitch or steeper,' with the greater exposures permitted at 4 units vertical in 12 units horizontal and steeper.
Minimum slope for clay and concrete tile (IBC 1507.3.2) IBC 2018 Pages 347 to 348
Clay and concrete roof tile is permitted only on roof slopes of 2 1/2 units vertical in 12 units horizontal (21-percent slope) or greater; double underlayment is required for slopes from 2 1/2:12 up to 4:12.
Fasteners for wood shingles and shakes (IBC Table 1507.8) IBC 2018 Table 1507.8
Hot-dipped galvanized or Type 304 stainless steel, and Type 316 stainless steel for coastal areas.

Formulas to Know

Minimum fasteners per asphalt shingle (IBC 1507.2.6)Use the minimum number of fasteners required by the manufacturer, but not fewer than 4 fasteners per strip shingle or 2 fasteners per individual shingle; where the manufacturer specifies fewer (e.g., 3 per strip on a 6:12 roof), the code floor of 4 governs. Where roof slope exceeds 21:12, install as required by the manufacturer.
Position of shake interlayment felt strip (IRC R905.8.7)Lower edge of each 18-inch-wide No. 30 felt strip is above the butt end of the shake it covers by 2 × weather exposure; example: 24-inch shakes at 10-inch exposure → 2 × 10 = 20 inches.
Asphalt shingle fastener penetration (IRC R905.2.5)Fastener length must penetrate through the roofing materials and not less than 3/4 inch into the roof sheathing; where sheathing is less than 3/4 inch thick, the fastener must penetrate through the sheathing.
Tile nail penetration (IRC R905.3.6)Nails of sufficient length to penetrate the deck not less than 3/4 inch or through the thickness of the deck, whichever is less.
Cap nail length for underlayment (IRC R905.1.1, Exception 3.4)Cap nail length sufficient to penetrate through the sheathing or not less than 3/4 inch into it; shank not less than 0.083 inch (ring shank) or 0.091 inch (smooth shank).
Tile fasteners — light tile override (IRC R905.3.7)Tiles with an installed weight less than 9 pounds per square foot require not less than one fastener per tile regardless of roof slope, overriding a 'fasteners not required' entry in Table R905.3.7 (example: 7 psf tile over solid sheathing with battens at 4:12, non-snow → 1 fastener per tile).
Tile fasteners — snow areas (IRC R905.3.7)In areas subject to snow, not less than two fasteners per tile; the one-fastener-per-tile value from Table R905.3.7 for solid sheathing without battens applies only outside snow areas (example: 11 psf tile, 4:12, 110 mph, 20 ft above grade, snow area → 2 fasteners per tile).
Underlayment lap for asphalt shingles in high wind (IBC Table 1507.1.1(2))Slopes 4:12 or greater: single layer lapped 2 inches; where maximum basic design wind speed is 140 mph or greater, same application except all laps not less than 4 inches (example: 150 mph, 5:12 → 4-inch laps).
Underlayment fastener grid patternAttach with corrosion-resistant fasteners in a grid pattern of 12 inches between side laps with 6-inch spacing at side and end laps (IRC R905.1.1 Exception 3.2; same 12-inch grid/6-inch side-lap pattern per IBC 1507.18.4.1 where Vasd is not less than 120 mph).
Component and cladding wind load adjustment (IRC Tables R301.2(2) and R301.2(3))Tabulated loads are published for a mean roof height of 30 feet in Exposure B (ASD); multiply the tabulated value by the height/exposure adjustment coefficient from Table R301.2(3).