Exam Cheat Sheet · Quick Reference
Louisiana Earthwork, Drainage and Levees
Louisiana · PSI Services Contractor
Louisiana State Portion 30 questions
Key Distinctions
Standard compacts the lab sample in three layers each struck 25 times with a 5.5-lb, 2-in. hammer (12,400 ft-lb), while modified uses five layers each struck 25 times with a 10-lb hammer (56,250 ft-lb per cubic foot) and is specified for high-design-load areas such as heavy-duty paving, concrete drives, federal highways and runways.
Pipe and Excavation Contracting, Pages 183 to 184A swell factor converts in-place (bank) volume to loose volume (e.g., 1.7 for broken asphalt/concrete slab), whereas a load factor converts loose cubic yards back to bank cubic yards and is computed as bank volume ÷ (bank volume + swell percentage).
Pipe and Excavation Contracting, Page 66Cut is measured in bank volume and fill in compacted volume, so both must be converted to the same state (loose) before subtracting — in the worked example 4,000 BCY × 1.32 = 5,280 LCY of cut vs. 4,000 CCY × 1.54 = 6,160 LCY of fill, giving 880 LCY of import.
Pipe and Excavation Contracting, Page 63Depending on soil type, heaped capacity is usually about 130 percent of struck capacity (e.g., a 2-ft hoe bucket struck at 5 to 6 LCF heaps about 6.5 to 8 LCF).
Pipe and Excavation Contracting, Pages 142-143A scraper can dump its payload in uniformly thick layers while trucks cannot, so scrapers improve compaction productivity through more consistent lift thickness.
Pipe and Excavation Contracting, Page 90A safety factor should be applied to theoretically computed grate inlet capacity especially when the inlet has no curb opening, because a grate alone is prone to debris blockage and loss of capacity.
Design and Construction of Urban Storm Water Management Systems, Chapter 8, Page 245Under the confined spaces standard, enriched means more than 23.5 percent oxygen by volume and deficient means less than 19.5 percent; either is a hazardous atmosphere.
29 CFR 1926, §1926.1202In transit with no load and boom lowered the clearances are 4 ft under 50 kV, 10 ft over 50 kV up to and including 345 kV, and 16 ft up to and including 750 kV; working clearance is instead computed under §1926.600(a)(6)(ii) as 10 ft plus 0.4 in. per kV over 50 kV.
OSHA 29 CFR 1926, §1926.600(a)(6)(iii)Field-cured cylinders are cured alongside the structure to judge curing/protection adequacy, which is considered adequate if they average at least 85% of companion standard-cured strength at the age designated for f'c (or exceed f'c by more than 500 psi); the 75% criterion applies instead to the lowest individual drilled core.
Design and Control of Concrete Mixtures (17th ed.), Chapter 20 — Evaluation of Compression Test Results section, Page 440In certain soils, digging resistance is usually greater in undisturbed earth, so the old ditch digs easier; the grademan can also often spot the old line by darker spots of topsoil mixed in with lighter-colored subsoil.
Pipe and Excavation Contracting, Page 148Light utility dozers (blade capacity 1.25 to 2.25 cu yd) are listed for residential/commercial foundations, fine grading, trench backfill, landscaping, light logging and swamp dozing, while mid-sized production dozers list 'logging' and tree and stump removal.
Pipe & Excavation Contracting, Chapter 2 – BulldozersConcrete with more than 3% entrained air should not be given a hard-troweled finish (risk of delamination from trapped bleed water or air), which is why slabs at 6% or more air for exterior freeze-thaw exposure receive float or broom finishes.
Design and Control of Concrete Mixtures (17th ed.), Chapter 15 — Finishing Flatwork / Bullfloating or Darbying section, Page 330Key Terms
Formulas to Know
LCY = BCY × 1.7 (example: 1,400 BCY × 1.7 = 2,380 LCY)Load factor = bank volume ÷ (bank volume + swell percentage); BCY = LCY × load factorConvert both cut and fill to the same state (LCY) using the project's conversion factors, then subtract: import = fill LCY − cut LCY (worked example for dry common earth at 100% Standard Proctor: 4,000 BCY × 1.32 = 5,280 LCY; 4,000 CCY × 1.54 = 6,160 LCY; 6,160 − 5,280 = 880 LCY)HI = rod reading on hub + cut − (pipe diameter + wall thickness) (example: 4.78 + 12.66 − 1.25 = 16.19)Realistic rate = optimum rate × operator-ability factor × job-efficiency factor × site-condition factor (example: 78 LCY/hr × 0.75 × 0.83 × 0.6 = 29 LCY/hr)Production = (blade width ft × speed mph × 5,280 × job efficiency × operator ability) ÷ number of passes = SF/hr; convert to SY/hr (÷9) and divide total SY by the rate (example: (12 × 4 × 5,280 × 0.83 × 0.75) ÷ 5 = 31,553 SF/hr = 3,506 SY/hr; 30,000 ÷ 3,506 ≈ 8.6 hr)BCF/LF = width × depth; LCF/LF = BCF × (1 + swell); LCF per set = LCF/LF × set length; cycles per set = LCF per set ÷ bucket load; time per set = (cycles × cycle seconds) + machine move time; sets/hr = 3,600 s ÷ time per set; LF/hr = sets/hr × set length (example with 15 s move time: 2 × 4 = 8 BCF; ×1.3 = 10.4 LCF; ×8 ft = 83.2; ÷8 = 10.4 cycles; (10.4×12)+15 = 139.8 s = 2.33 min; 60 ÷ 2.33 = 25.75 sets; ×8 = 206 LF/hr)Heaped ≈ 1.30 × struck capacity (example: struck 5 to 6 LCF → heaped about 6.5 to 8 LCF)Volume cu yd = (length × width × thickness in ft) ÷ 27; for a 4-in. slab one cubic yard covers 81 sq ft, so cu yd = area ÷ 81; footing length = outside perimeter = 2 × (L + W); order continuous footing rounded UP to the next quarter yard, and combined net volumes rounded up to the next whole yard (examples: 960 ÷ 81 = 11.85 → 12 cu yd; 124 ft × 1.333 × 0.833 = 137.78 cu ft ÷ 27 = 5.10 → order 5.25 cu yd; 5.10 + 0.69 + 11.85 = 17.65 → 18 cu yd)Form contact area (both faces) = 2 × perimeter × height (example: 2 × 136 × 8 = 2,176 sq ft); 8-in. wall concrete = (wall area ÷ 100) × 2.47 cu yd per 100 sq ft (example: 1,088 ÷ 100 = 10.88 × 2.47 = 26.87 cu yd); block: three courses stack 2 ft (courses = height × 3/2) and three blocks lay 4 ft (blocks = length × 3/4)