Exam Cheat Sheet · Quick Reference
Louisiana Horizontal Directional Drilling
Louisiana · PSI Services Contractor
Louisiana State Portion 30 questions
Key Distinctions
The gyroscope system is accurate to within ±3 ft (1 m) at 6,500 ft and is not affected by magnetic fields from underground utilities such as ductile iron pipe or by surface electromagnetic fields, while a wire-line system without a surface grid is accurate only to about ±130 ft at that distance and its accuracy is further diminished by strong magnetic fields.
Construction Planning, Equipment, and Methods (9th ed.), Pages 555 to 557Pipe reaming uses a directional drill with a reaming head to pulverize and grind out the existing pipe (mud carries particles to a receiving manhole), while pipe bursting expands the old pipe's fragments into the surrounding soil — making reaming optimum in incompressible or granular soils and near fragile adjacent pipes.
Construction Planning, Equipment, and Methods (9th ed.), Pages 552 to 553V-Bio (offered beginning 2013) uses co-extrusion to infuse a corrosion inhibitor and an anti-microbial component into the innermost surface of the film, and is the recommended film for ductile iron pipe in corrosive soils (installed per ANSI/AWWA C105/A21.5).
DIPRA Installation Guide for Ductile Iron Pipe, Pages 29 to 30 (Section 2.16 V-Bio Enhanced Polyethylene)Welds completed uphill typically use a 75-degree groove angle (37.5-degree bevel on each pipe), while downhill welding uses a narrower 60-degree groove angle.
Modern Welding, Page 23-6; Pipe Welding Procedures, Chapter 4Whipping is the remedy for molten-metal overflow when welding a root bead vertical uphill in 5G, but it must never be used with low-hydrogen electrodes — a V-shaped weave is used entirely around the pipe instead; excessive whipping exposes the puddle and causes porosity and slag entrapment.
Pipe Welding Procedures (2nd ed.), Chapter 5Martensite has a body-centered tetragonal (elongated body-centered cubic) structure caused by carbon atoms trapped within it and forms on very rapid quenching from austenite, while ferrite has a body-centered cubic structure with very little dissolved carbon.
Pipe Welding Procedures (2nd ed.), Chapter 11 (Introduction to Welding Metallurgy)Slow cooling through the eutectoid temperature produces pearlite; quenching to about 675°F (360°C) then cooling slowly produces bainite (good strength, not as hard as martensite, ductile and tough); only a full ice-water quench produces martensite.
Pipe Welding Procedures (2nd ed.), Chapter 11, T-T-T Diagram / Steel Microstructures sectionA single-acting steam or air hammer strikes 40 to 60 blows per minute, while a double-acting hammer delivers 95 to 300 blows per minute (700 to 1,200 refers to optimal vibratory hammer frequency ranges).
Construction Planning, Equipment, and Methods (9th ed.), Chapter 17 — Single-Acting Hammers sectionOn an earthwork volume sheet, stripping over a cut is SUBTRACTED from the cut volume because organic material cannot be used as structural fill, while stripping under a fill is ADDED to the fill requirement.
Construction Planning, Equipment, and Methods (9th ed.), Chapter 3 — Stripping / Earthwork Volume Sheet sectionsBank volume is the in-place (in situ) measure used for excavation quantities, while loose volume is the swelled, disturbed measure that must be used for figuring haul-off truck loads; dividing bank volume by truck size under-counts the loads.
Pipe and Excavation Contracting — Ch. 9, Estimating Surface Excavation (bank vs loose yards)Wet clays and loams that 'slab off' the lower trench call for tight-sheeting with plywood on each side of (or attached to) the shoring jacks, while trench boxes are recommended for deep trenches in unstable ground such as wet sands and gravels; open ditches suit only shallow excavations in reasonably dry, stable soil.
Pipe and Excavation Contracting, Page 228 (Installing Sewer & Stormwater Systems chapter)Per 29 CFR 1926.1202, oxygen enriched means more than 23.5 percent oxygen by volume and oxygen deficient means less than 19.5 percent; either is a hazardous atmosphere under the confined spaces standard.
29 CFR 1926, §1926.1202Per NEC 2017 Article 100, service-entrance conductors (underground system) run between the terminals of the service equipment and the point of connection to the service lateral, while underground service conductors run between the service point and the first point of connection to the service-entrance conductors in a terminal box, meter, or other enclosure.
NEC 2017 Article 100 — Definitions, Service-Entrance Conductors, Underground SystemIn certain soils, soil resistance is usually greater in undisturbed earth, so an old ditch digs easier; the grademan can spot the old line visually by darker spots of topsoil mixed in with lighter-colored subsoil.
Pipe and Excavation Contracting, Page 148Key Terms
Formulas to Know
LCY = BCY × (1 + swell%); e.g., 25.19 × 1.30 = 32.74 LCY; 23.70 × 1.25 = 29.63 LCY; 512.00 × 1.20 = 614.40 LCY; 388.89 × 1.20 = 466.67 LCY; 456.00 × 1.20 = 547.20 LCYLCY = BCY × 1.7 (always allow 1.7 for asphalt and concrete slabs); worked example: 1,400 BCY × 1.7 = 2,380 LCY. Factors of 1.3, 1.4 and 1.5 apply to soils such as loam, not broken slab.Loads = LCY ÷ truck capacity, rounded up; e.g., 32.74 ÷ 12 = 2.73 → 3 loads; 29.63 ÷ 14 = 2.12 → 3 loads; 614.40 ÷ 10 = 61.44 → 62 loads; 466.67 ÷ 12 = 38.89 → 39 loads; 547.20 ÷ 14 = 39.09 → 40 loadsLength = 2 × (L + W); BCY = length × width × depth ÷ 27; e.g., 2 × (40 + 28) = 136 ft × 2.5 ft × 2 ft = 680.0 cu ft ÷ 27 = 25.19 BCY; 2 × (40 + 24) = 128 ft × 2.5 × 2 = 640.0 ÷ 27 = 23.70 BCYFootprint = (L + 2 × offset) × (W + 2 × offset); BCY = footprint × depth ÷ 27; e.g., (44+2×2)×(28+2×2) = 48×32 = 1,536 sf × 9 ft = 13,824 cf ÷ 27 = 512.00 BCY; (44+2×3)×(24+2×3) = 50×30 = 1,500 sf × 7 ft = 10,500 cf ÷ 27 = 388.89 BCY; (32+2×3)×(30+2×3) = 38×36 = 1,368 sf × 9 ft = 12,312 cf ÷ 27 = 456.00 BCYExtra LCY = BCY × 0.10; e.g., 25.19 × 0.10 = 2.52; 23.70 × 0.10 = 2.37; 512.00 × 0.10 = 51.20; 388.89 × 0.10 = 38.89; 456.00 × 0.10 = 45.60HI = rod reading on hub + cut − (pipe diameter + wall thickness); worked example: 4.78 + 12.66 − 1.25 = 16.19Required max rated digging depth = trench depth ÷ 0.70; worked example: 12 ÷ 0.70 ≈ 17 ftLongitudinal quantity = sum of absolute values of mass-diagram peaks and low points; Crosshaul = total cut within project limits − longitudinal quantity; worked example: 1,500 + 2,200 = 3,700 bcy; 4,100 − 3,700 = 400 bcyAvailable cut = cut − stripping over cut; Adjusted fill = fill + stripping under fill; convert fill to bank by dividing by 0.90; algebraic sum = available cut − bank fill. Worked example: (1,800 − 200) = 1,600 bcy; (900 + 100) = 1,000 ccy ÷ 0.90 = 1,111 bcy; 1,600 − 1,111 = 489 bcy surplusSafe load = (W × h) / (s + 1), where s = penetration in inches per blow; a safety factor of six is built into the equationMinimum hammer weight = 1/3 × pile weight (recommended weight equals the pile weight); worked example: 0.33 × 21,000 lb = 6,930 lb