Exam Cheat Sheet · Quick Reference

Mississippi Municipal

Mississippi  ·  PSI Services Contractor

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
60
Passing score
70%
Exam time
120 min
Administered by
PSI Services Contractor
Format
Reference materials allowed

Mississippi State Portion 60 questions

Excavation, Compaction and Grading 8 Q · 13%
Backhoe components, hydraulics, and operating principlesBackhoe production rate calculation and operator efficiencyTrench safety, shoring systems, and cave-in preventionSoil compaction methods, Proctor testing, and density determinationCut and fill volume estimation using cross section and average end area methodsRock classification, rippability, and blasting techniquesGroundwater management and dewatering methodsSite preparation, clearing, pavement removal, and material layout
Safety 7 Q · 12%
General safety and health provisions and employer accident prevention responsibilitiesPersonal protective equipment (PPE) selection, use, and employer payment requirementsFall protection systems — guardrail, safety net, and personal fall arrest system requirementsScaffold erection, capacity, and fall protection requirementsExcavation hazards, cave-in protective systems, and competent person inspectionsFire protection, fire prevention, and flammable liquid storage and handlingConfined space entry procedures, permit requirements, and atmospheric monitoringMedical services, first aid requirements, and emergency action planning
Steel 10 Q · 17%
Reinforcing bar types, grades, and identification markingsConcrete cover requirements and placement tolerances for reinforcing barsBar supports: types, sizes, and placementFabrication of reinforcing bars: bending shapes, splices, and spiralsPlacing reinforcing bars in footings, walls, columns, floors, and roofsOpen web steel joist and joist girder products: types, erection, and bridging requirementsPost-tensioning tendon installation, stressing, and elongation measurementUnloading, storing, handling, and inspection of steel reinforcement and joist products
Concrete 15 Q · 25%
Formwork design loads: vertical dead and live loads, lateral concrete pressureFormwork materials: lumber, plywood, engineered wood, steel, and aluminumDesign of formwork members: slab, wall, beam, and column formsShoring and reshoring design for multi-story concrete structuresFormwork safety requirements and OSHA complianceForm removal and stripping criteria based on concrete strengthConcrete mixture properties and field testing (slump, air content, compressive strength)Formed concrete surface quality, tolerances, and surface finish classifications
General Knowledge 3 Q · 5%
Estimating direct costs: labor, equipment, and materialsOverhead calculation: direct job overhead and indirect office overheadMarkup, profit, contingency, and escalation in biddingBonding types: bid bonds, performance bonds, payment bonds, and maintenance bondsContract provisions: change orders, liquidated damages, warranties, and indemnityCrew and equipment productivity: cycle times, operator ability, and job efficiency factorsTrench excavation quantity calculations: soil states, swell, and volume formulasReading plans and surveying: elevations, grades, optical levels, and laser alignment
Underground Utilities-Concrete Pipe Installation 7 Q · 12%
Pre-construction ordering, receiving, and inspection of concrete pipe and box culvertsUnloading, handling, and stockpiling concrete pipe without damageTrench excavation dimensions, trench width requirements, and dewateringPipe bedding types and compaction requirements (Standard Installations Types 1–4, Class A–D beddings)Jointing procedures, gasket types, and sealant materials for concrete pipeBackfill placement, compaction equipment selection, and soil density testingAcceptance testing methods (infiltration, exfiltration, low-pressure air, vacuum, and visual inspection)Box culvert installation including alignment, placement sequence, jointing, and minimum cover for construction loads
Underground Utilities-Ductile Pipe Installation 7 Q · 12%
Receiving, inspection, and safe unloading of ductile iron pipeTrench excavation requirements, dimensions, and bedding conditionsPush-on and mechanical joint assembly proceduresThrust restraint methods: thrust blocks, restrained joints, and tie rodsBackfill material requirements and compaction proceduresHydrostatic pressure testing and allowable leakageDisinfection methods for new water mainsService taps: direct taps, saddle taps, and corporation stops
MS One-Call 3 Q · 5%
Advance notice requirements and timelines for excavationExcavator pre-marking obligations before notificationEmergency and impending emergency excavation proceduresOperator marking responsibilities and APWA color codesTolerance zone requirements and safe digging practicesLarge project excavation and preconstruction meeting processDamage reporting requirements for struck underground facilitiesCivil penalties and enforcement by the Underground Facilities Damage Prevention Board

Key Distinctions

Standard Proctor (T-99 / ASTM D 698)vsModified Proctor (T-180 / ASTM D 1557)

The standard test compacts three layers each struck 25 times with a 5.5-pound, 2-inch hammer (12,400 ft-lb total), while the modified test compacts five layers each struck 25 times with a 10-pound hammer (56,250 foot-pounds per cubic foot) and is specified for high-design-load areas such as heavy-duty paving, concrete drives, federal highways and runways.

Pipe and Excavation Contracting, Pages 183 to 184
Form tie safety factorvsForm anchor safety factor

The usual safety factor for form tie working loads is 2:1 (working load limited to one-half ultimate tensile strength), while form anchors securing formwork to previously placed concrete require a minimum safety factor of 3 including live loads and impact because the concrete may still be green.

Contractor's Guide to Quality Concrete Construction (4th ed.), Page 66
Oxygen enriched atmospherevsOxygen deficient atmosphere

Under 29 CFR 1926.1202, oxygen enriched means more than 23.5 percent oxygen by volume while oxygen deficient means less than 19.5 percent; either condition is a hazardous atmosphere in a confined space.

29 CFR 1926, §1926.1202
Average End Area MethodvsCross Section Method

The Average End Area Method multiplies the average area of two parallel cross sections by the distance between them (and is used for prisms containing both cut and fill, split at the zero line), while the Cross Section Method averages the cut/fill depths at a prism's four corners and multiplies by the prism base area.

Pipe and Excavation Contracting, Page 262
Ductile iron laying condition Type 3vsDuctile iron laying condition Type 4

Per ANSI/AWWA C150/A21.50, Type 3 is pipe bedded in 4-inch minimum loose soil with backfill lightly consolidated to the top of pipe, while Type 4 requires sand, gravel, or crushed stone bedding to 1/8 pipe diameter with backfill compacted to approximately 80 percent Standard Proctor.

DIPRA Installation Guide for Ductile Iron Pipe, Page 43 (Section 3.1 Standard Laying Conditions)
Industry 10-point soil evaluation procedurevsDesign Decision Model (DDM)

The 10-point system addresses the likelihood of corrosion, while the DDM extends (but does not invalidate) it as a two-dimensional, risk-based model that also weighs the consequences of a pipeline failure in selecting a mitigation strategy.

DIPRA Installation Guide for Ductile Iron Pipe, Pages 28 to 29 (Section 2.15 Corrosive Soil)
IRC R317.1 Item 1 (crawl space / unexcavated area)vsIRC R317.1 Item 2 (framing on foundation walls)

Wood joists or the bottom of a wood structural floor in a crawl space or unexcavated area within the foundation periphery need naturally durable or preservative-treated wood when closer than 18 inches to exposed ground, while wood framing members including columns resting directly on concrete or masonry exterior foundation walls need it when less than 8 inches from exposed ground.

IRC Section R317.1, Item 1; IRC 2018 Section R317.1
Undisturbed native soilvsSoil in an old, previously-dug trench line

In certain soils, soil resistance is usually greater in undisturbed earth than in an existing trench line, so the old ditch is usually easier digging, and by watching the ditch walls the grademan can often spot the old line by darker spots of topsoil mixed in with lighter-colored subsoil.

Pipe and Excavation Contracting, Page 148
Standard or high-strength concrete mixturesvsMixtures with portland cement partially replaced by fly ash or slag cement

Mixtures using fly ash or slag replacement may require twice as much cure time before stripping forms as standard or high-strength mixtures, because these supplementary cementitious materials slow early strength gain.

Contractor's Guide to Quality Concrete Construction (4th ed.), Page 82
Vented crawl space without approved ground vapor retardervsVented crawl space with approved Class I vapor retarder on the ground

Per IRC R408.2 the net ventilation opening area shall be not less than 1 square foot per 150 square feet of under-floor area, but may be reduced to 1/1,500 of the under-floor area where an approved Class I vapor retarder covers the ground surface.

IRC Section R408.2; IRC 2018 Section R408.2
Swell factor for broken concrete/asphalt slabvsSwell factor for soils such as loam

Always allow a swell factor of 1.7 from bank to loose volume for asphalt and concrete slabs, whereas soils such as loam swell about 30 percent (factor 1.3); factors of 1.3, 1.4 and 1.5 do not apply to broken slab material.

Pipe and Excavation Contracting, Page 138
Prescriptive footing for one floor of light-frame constructionvsPrescriptive footing for three floors of light-frame construction

Per Table 4.1 (adapted from 2015 IBC Table 1809.7), a footing supporting one floor requires a minimum 12-inch width and 6-inch thickness, two floors require 15-inch width and 6-inch thickness, and three floors require 18-inch width and 8-inch thickness.

Contractor's Guide to Quality Concrete Construction (4th ed.), Page 47 (Table 4.1)

Key Terms

Benchmark (BM) Pipe and Excavation Contracting, Pages 111 and 115–116, elevation and benchmark definitions
A fixed point of known elevation from which surveyors calculate the elevations of other points by adding or subtracting measured vertical distances.
Elevation (El) Pipe and Excavation Contracting, Pages 111 and 115–116, elevation and benchmark definitions
The height of a point above sea level.
Escalation Pipe and Excavation Contracting, Page 27
The increase in costs of labor, materials, and equipment between the time the bid is submitted and the time the work is actually done and paid for, for which a small allowance should be included when costs are expected to rise.
Pull (curved alignment, deflected straight pipe) Concrete Pipe and Box Culvert Installation, Concrete Pipe Installation Manual — Jointing / Curved Alignment section (Pages 46-47)
The difference between the home joint space and the opened joint space when a joint is opened on one side for a curved alignment; the maximum permissible pull is obtained from the pipe manufacturer.
Seating-loss (post-tensioning) PTI Field Procedures Manual, Chapter 1 Definitions - Seating-Loss
Per PTI Field Procedures Manual Chapter 1, the relative movement of the wedges into the anchor cavity during transfer of the prestressing force to the anchorage, resulting in some loss of prestressing force.
Marine exclusion zone (Miss. Code 77-13-3(bb)) Mississippi Regulation of Excavation, Section 77-13-3(bb)
A strip measured seventy-five (75) feet from the outside edge of both sides of the submerged facility marks on a horizontal plane.
Damage (Miss. Code 77-13-3(f)) Mississippi Regulation of Excavation, Section 77-13-3(f)
Substantial weakening of structural or lateral support, penetration or destruction of protective coatings, and partial or complete severance of underground facilities, but it does not include any operator's abandoned facility.
Proposed excavation location on a locate request ticket (Miss. Code 77-13-5(1)(a)) Mississippi Regulation of Excavation, Section 77-13-5(1)(a)
An area the excavator reasonably believes may be completed within 20 calendar days that does not include any area in which the excavator has already completed the excavation work.
Set (production trenching) Pipe & Excavation Contracting, Chapter 5, Page 143 - Digging Cycle Component table
The length of trench a backhoe can excavate from one position; the digging cycle components are listed as load bucket, lift load, swing and prepare to dump, dump bucket load, and return to dig.
Maturity meter testing Contractor's Guide to Quality Concrete Construction (4th ed.), Page 81
An in-place strength method that measures the temperature of the concrete over a period of time to calculate strength, requiring a correlation between the measured property and the strength of the actual mixture before field testing.
Camber Contractor's Guide to Quality Concrete Construction (4th ed.), Page 77
A slight upward curvature intentionally built into a structural element or form to compensate for deflection under loads, shrinkage, and creep.
Payment bond Pipe and Excavation Contracting, Page 47
A bond guaranteeing that all bills for labor, equipment, and materials will be paid and that liens filed against the project are discharged, as distinct from a performance bond, which guarantees completion of the work.
Front end loading (unbalanced bid) Pipe and Excavation Contracting, Pages 36-37
Padding markup onto bid items scheduled early in the project, which costs the contractor profit if the owner reduces those padded quantities (the example shows a 50 percent cut in a loaded item dropping overall markup from 20 percent to 10 percent).
V-Bio enhanced polyethylene DIPRA Installation Guide for Ductile Iron Pipe, Pages 29 to 30 (Section 2.16 V-Bio Enhanced Polyethylene)
Polyethylene film, offered beginning in 2013, in which co-extrusion infuses a corrosion inhibitor and an anti-microbial component into the innermost surface; it is the recommended film for ductile iron pipe in corrosive soils and is installed per ANSI/AWWA C105/A21.5.
Truncated prism Pipe and Excavation Contracting, Page 256
The three-dimensional solid most often encountered in an earthwork takeoff, whose volume equals the base area times the average height of its four corners.
Mobilization Pipe and Excavation Contracting, Page 60
A project cost that is sometimes itemized as a separate bid item; if it is not, it must be included in the equipment cost calculations.

Formulas to Know

Cubic yards of pipe bedding material for a trenchTrench length (ft) × trench width (ft) × bedding depth (ft) ÷ 27 (27 cu ft per cu yd)
Square yards of filter fabric (worked example: 250-ft run, 15-ft wrap width)Length (ft) × width (ft) ÷ 9; e.g., 250 × 15 = 3,750 sq ft ÷ 9 ≈ 416 sq yd
Height of instrument when the grade rod is set on top of the pipeHI = rod reading on hub + cut quantity − (pipe diameter plus wall thickness); example: 4.78 + 12.66 − 1.25 = 16.19
Loose volume of broken concrete and asphalt slabLCY = BCY × 1.7 (swell factor 1.7 for asphalt and concrete slabs); example: 1,400 BCY × 1.7 = 2,380 LCY
Selecting backhoe size (most efficient within 70 percent of max digging depth)Required maximum digging depth = trench depth ÷ 0.70
Ideal compaction output of a hoe-mounted vibratory platePlate area (sq ft) × compacted lift thickness (ft) × cycles per hour ÷ 27
Volume of a truncated prism (Cross Section Method)Average the cut or fill depths at the four corners, then multiply by the prism base area; example: (2.3 + 0.9 + 0.8 + 2.3) ÷ 4 = 1.58 ft × 2,500 sq ft = 3,950 cu ft
Volume by Average End Area MethodVolume = average area of two parallel cross sections × distance between them (cut and fill sections of a mixed prism computed separately)
Net cut depth adjusted for topsoil stripped vs. replacedNet cut = average plan cut − stripped topsoil depth + replaced topsoil depth; example: 1.63 − 0.50 + 0.34 = 1.47 ft
Concrete estimating quick rules (footings, 8-in. walls, 4-in. slab, form contact area)Continuous footing: length = outside perimeter, volume = length × width (ft) × depth (ft) ÷ 27, then order rounded UP to the next quarter yard; 8-in. foundation wall: (wall sq ft ÷ 100) × 2.47 cu yd per 100 sq ft; 4-in. slab: slab sq ft ÷ 81 sq ft per cu yd, ordered in whole yards rounded up; wall form contact area = 2 × perimeter (ft) × height (ft)