ICC F12 General Building Contractor (B) Exam (2015 IBC/IRC) Practice Exam
ICC retires this exam on December 1, 2026: from that date it can no longer be registered through Pearson VUE (ICC Exam Catalog, checked November 10, 2026). If you are registering on or after December 1, take the version on the 2018 codes, ICC G12. It has no retirement date listed, and we have a practice test for it.
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real Pearson VUE test format.
- 80 questions (same as real exam)
- 240 minute time limit
- 4 topic areas covered
- 386 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
ICC F12 General Building Contractor (B) (2015 IBC/IRC) Practice Exam Guide
What's on the exam
Questions per topic, out of 80This practice exam follows the official content outline for the ICC F12 General Building Contractor (B) (2015 IBC/IRC) exam: Permits and General Regulations, Building Planning and Life Safety, Structural Systems, Building Envelope.
You can practice two ways. The free practice exam gives you 10 questions per attempt, and you can retake it whenever you like. The full practice exam gives you 80 questions on a 4 hours clock, with a new draw from our question bank each attempt.
Permits and General Regulations 17 items
Our study plan for this topic: Regulations and Job Planning; Code Definitions and Terms; Permit application requirements and procedures; Work exempt from permit requirements; Inspections and required inspection types; Certificate of occupancy requirements and issuance; Building official authority and enforcement powers; Stop work orders and violation penalties.
Building Planning and Life Safety 24 items
Our study plan for this topic: Use & Occupancy & Types of Construction; Fire & Smoke Alarms & Fire Protection Systems; Exiting & Means of Egress; Accessibility; Building Heights, Number of Stories, and Area Limitations by Occupancy and Construction Type; Fire-Resistant Construction and Separation Requirements (IRC); Occupant Load Calculation and Posting Requirements; Egress Illumination and Emergency Power for Means of Egress.
Structural Systems 33 items
Our study plan for this topic: Footings and Foundations; Concrete; Floors; Wall Framing and Stairs; Roof Ceiling Construction Roof Assembly; Masonry; Structural load types and load combinations (dead, live, wind, seismic, snow); Wall bracing methods and braced wall panel requirements.
Building Envelope 6 items
Our study plan for this topic: Interior Finishes; Glass and Glazing; Exterior Finishes and Roof Coverings; Roof drainage systems and secondary overflow protection; Roof fire classification requirements by construction type; Weather protection and flashing installation requirements; Vapor retarders and water-resistive barriers for exterior walls; Exterior wall cladding materials and attachment requirements.
Sample 1 — Structural Systems
Question: During summer placement on a commercial project, your ready-mix supplier proposes calcium chloride as an accelerator. Above what concrete temperature should calcium chloride NOT be used, because of a possible detrimental effect on strength at later ages?
- A. 70°F
- B. 50°F
- C. 60°F
- D. 80°F
Correct Answer: C
Concrete Manual, Chapter 3, Section 3.13 states that calcium chloride should not be used when the temperature is above 60°F because of a possible detrimental effect on strength at later ages. It is never an antifreeze, must not be used in prestressed concrete, and should be used with caution in reinforced concrete because of reinforcement corrosion potential.
Reference: Concrete Manual (2015 IBC / ACI 318-14), Chapter 3 — Section 3.13 (Accelerated Strength Development — Admixtures)
Sample 2 — Building Planning and Life Safety
Question: A steel pipe penetrates a required fire-resistance-rated masonry wall separating dwelling units, and the installer intends to fill the annular space full-thickness with grout rather than use a tested firestop system. What is the maximum nominal diameter of the penetrating item for which this method is permitted?
- A. 6 inches
- B. 8 inches
- C. 4 inches
- D. 2 inches
Correct Answer: A
IRC Section R302.4.1, Exception Item 1, permits concrete, grout or mortar in concrete or masonry assemblies for steel, ferrous or copper pipes, tubes or conduits provided the nominal diameter of the penetrating item is not more than 6 inches and the opening area does not exceed 144 square inches.
Reference: IRC 2015 Section R302.4.1
Sample 3 — Permits and General Regulations
Question: A dispute arises on your commercial project over how the wording of a code provision must be read. Which statement correctly reflects the rule of interchangeability used in applying the code's terms?
- A. Masculine terms apply only to the masculine gender
- B. Words in the singular include only the singular
- C. Undefined terms carry only their legal-dictionary meaning
- D. Words used in the present tense include the future
Correct Answer: D
Per 2015 IBC Section 201.2, words used in the present tense include the future; words stated in the masculine gender include the feminine and neuter; and the singular includes the plural and the plural the singular. Section 201.4 further states that terms not defined through the authorized methods take ordinarily accepted meanings as the context implies, not a legal-dictionary-only meaning.
Reference: IBC 2015 Chapter 2 — Section 201.2 Interchangeability
Your first attempt tells you where you're starting from. After every attempt, the results page shows your score for each outline topic, so you can see what to study next. Compare your score with the real exam's passing score, 70% correct, and keep going until you pass consistently.
- Answer the questions you know first, and bookmark the rest. Our practice exams let you bookmark and come back.
- Return to your bookmarks on the second pass.
- Keep a steady pace. The real exam works out to about 3 minutes per question.
- After each attempt, look up each missed question's reference and read the section.
| Questions | 80 questions |
| Time limit | 4 hours |
| Passing score | 70% correct |
| Books in the exam room | Open book |
| Exam fee | $120 |
- Results for examinations taken electronically are available immediately after the examination is completed.
- You must wait 10 days before retaking a failed exam.
Source: National Contractor/Trades Examination Information Bulletin, PUBLISHED June 30, 2026; ICC Exam Catalog, checked October 2, 2026. Check the bulletin before test day: fees and rules can change.