Exam Cheat Sheet · Quick Reference
Alabama Drainage and Culvert Contractor
Alabama · PSI Services Contractor
Alabama State Portion 30 questions
Key Distinctions
Standard compacts the lab sample in three layers struck 25 times with a 5.5-lb, 2-in. hammer (12,400 ft-lb), while modified uses five layers struck 25 times with a 10-lb hammer (56,250 ft-lb per cubic foot) and is specified for high-design-load areas such as heavy-duty paving, concrete drives, federal highways and runways.
Pipe and Excavation Contracting, Pages 183 to 184A scraper can dump its payload in uniformly thick layers (improving compaction productivity on embankments), whereas trucks cannot.
Pipe and Excavation Contracting, Page 90A load factor converts loose cubic yards to bank cubic yards (bank volume ÷ (bank volume + swell percentage)), while a swell factor converts in-place bank volume up to loose disturbed volume (e.g., 1.7 for broken asphalt/concrete slab).
Pipe and Excavation Contracting, Page 66Always allow 1.7 bank-to-loose for asphalt and concrete slab material; factors of 1.3, 1.4 and 1.5 apply to soils such as loam, not broken slab.
Pipe and Excavation Contracting, Page 138Depending on soil type, heaped capacity is usually about 130 percent of struck capacity (e.g., a 2-ft hoe bucket struck at 5–6 LCF heaps about 6.5–8 LCF).
Pipe and Excavation Contracting, Pages 142-143Enriched means more than 23.5 percent oxygen by volume; deficient means less than 19.5 percent — either is a hazardous atmosphere under the confined spaces standard.
29 CFR 1926, §1926.1202Field-cured cylinders are cured alongside the structure to judge curing/protection adequacy; curing is adequate if their average strength at the age designated for f'c is at least 85% of the companion standard-cured strength (or field-cured strength exceeds f'c by more than 500 psi / 3.5 MPa).
Design and Control of Concrete Mixtures (17th ed.), Chapter 20 — Evaluation of Compression Test Results section, Page 440In transit with no load and boom lowered requires 4 ft under 50 kV, 10 ft over 50 kV up to and including 345 kV, and 16 ft up to and including 750 kV; working clearance is computed under §1926.600(a)(6)(ii) as 10 ft plus 0.4 in. per kV over 50 kV.
OSHA 29 CFR 1926, §1926.600(a)(6)(iii)A safety factor on computed theoretical capacity is especially important for a grate with no curb opening because a grate alone is prone to debris blockage and loss of capacity.
Design and Construction of Urban Storm Water Management Systems, Chapter 8, Page 245In certain soils, soil resistance is usually greater in undisturbed earth; the old ditch line digs easier and can be spotted visually as darker topsoil mixed into lighter-colored subsoil.
Pipe and Excavation Contracting, Page 148A vertical wall in cemented gravel may be quite safe, but a pocket of loose sand or heavy loam makes it dangerous — classification and protection must account for the weakest soil present.
Pipe and Excavation Contracting, Page 171Light utility dozers (blade capacity 1.25–2.25 cu yd) are listed for residential/commercial foundations, fine grading, trench backfill, landscaping, light logging and swamp dozing; mid-sized production dozers list 'logging' and tree and stump removal.
Pipe & Excavation Contracting, Chapter 2 – BulldozersConcrete with more than 3% entrained air should not be hard troweled (risk of delamination), so slabs at the 6% or more typical of exterior freeze-thaw exposure get float or broom finishes instead.
Design and Control of Concrete Mixtures (17th ed.), Chapter 15 — Finishing Flatwork / Bullfloating or Darbying section, Page 330Key Terms
Formulas to Know
LCY = BCY × 1.7 (example: 1,400 BCY × 1.7 = 2,380 LCY); soils such as loam use 1.3–1.5Load factor = bank volume ÷ (bank volume + swell percentage); multiply LCY by load factor to get BCYCut LCY = BCY × (bank-to-loose factor); Fill LCY = CCY × (compacted-to-loose factor); Import = Fill LCY − Cut LCY (example for dry common earth at 100% Standard Proctor, factors 1.32 LCY/BCY and 1.54 LCY/CCY: 4,000 × 1.32 = 5,280; 4,000 × 1.54 = 6,160; 6,160 − 5,280 = 880 LCY)Realistic = optimum × operator ability × job efficiency × site condition factor (example: 78 LCY/hr × 0.75 × 0.83 × 0.6 ≈ 29 LCY/hr)Production = (blade width × speed mph × 5,280 × job efficiency × operator ability) ÷ number of passes; hours = area ÷ production (example: (12 × 4 × 5,280 × 0.83 × 0.75) ÷ 5 = 31,553 SF/hr = 3,506 SY/hr; 30,000 ÷ 3,506 ≈ 8.6 hr)BCF/LF = width × depth; LCF/LF = BCF × (1 + swell); LCF per set = LCF/LF × set length; cycles per set = LCF per set ÷ bucket load; time per set = (cycles × cycle seconds) + move time; sets/hr = 60 min ÷ minutes per set; LF/hr = sets/hr × set length (example: 2×4=8 BCF; ×1.3=10.4 LCF; ×8 ft=83.2; ÷8=10.4 cycles; (10.4×12)+15=139.8 s=2.33 min; 60÷2.33=25.75 sets; ×8 = 206 LF/hr)Heaped ≈ 1.30 × struck capacityHI = rod reading on hub + cut − (pipe diameter plus wall thickness) (example: 4.78 + 12.66 − 1.25 = 16.19)Cu yd = length × width × depth (ft) ÷ 27; continuous footing length = outside perimeter = 2 × (L + W) (examples: 124 × 1.333 × 0.833 = 137.78 cu ft ÷ 27 = 5.10 cu yd; pier 2.5 × 2.5 × 1 = 6.25 cu ft, ×3 = 18.75 ÷ 27 = 0.69 cu yd)Slab: one cu yd covers 81 sq ft at 4 in., so cu yd = area ÷ 81, rounded up to whole yards (example: 960 ÷ 81 = 11.85 → 12 cu yd). 8-in. wall: cu yd = (wall area ÷ 100) × 2.47 (example: 1,088 ÷ 100 = 10.88 × 2.47 = 26.87 cu yd). Wall form contact area = 2 × perimeter × height. Footing orders are rounded UP to the next quarter yard; combined footing+pier+slab totals are rounded up to the next whole yard.