South Carolina - NASCLA-Accredited Trade Examination for Electrical Contractor
South Carolina
· PSI Services Contractor
Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
100
Passing score
75%
Exam time
270 min
Administered by
PSI Services Contractor
Format
Reference materials allowed
South Carolina State Portion
100 questions
Project Design & Management8 Q · 8%
Electrical load calculations and service sizingBlueprint and schematic reading for electrical systemsProject scheduling and sequencing of electrical workMaterial takeoffs and quantity estimationElectrical system design compliance with NEC requirementsJob cost estimating and biddingCoordination with other trades and project stakeholdersPermit and inspection processes for electrical projectsContract types and payment structures for electrical projects (lump sum, unit price, cost-plus, retainage)Risk management and insurance requirements for electrical contractors (builder's risk, liability, bonding)Subcontractor qualification, selection, and site coordination requirementsProject scheduling methods (bar chart, critical path method, calendar scheduling) for electrical work+7 more
Safety9 Q · 9%
Personal protective equipment (PPE) requirements for electrical workLockout/tagout procedures for electrical energy controlElectrical hazard identification and arc flash safetyOSHA regulations applicable to electrical contractorsSafe work practices for energized and de-energized electrical systemsLadder and scaffold safety for electrical installationsConfined space entry proceduresFire prevention and extinguisher use on job sitesEnergized electrical work permit requirements and documentationElectric shock physiology and effects of current on the human bodyElectrical safety program responsibilities of employers and employeesSafety-related maintenance of electrical equipment and protective devices+7 more
Electrical Theory and Principles11 Q · 11%
Ohm's Law and voltage, current, resistance relationshipsSeries and parallel circuit analysisPower and energy calculations (watts, kilowatts, horsepower conversions)AC vs DC fundamentals and waveform characteristicsCapacitance and inductance in AC circuitsPower factor and reactive power conceptsElectromagnetism and transformer principlesThree-phase power calculations and configurationsAtomic structure, electron theory, and conductor/insulator propertiesKirchhoff's Voltage and Current Laws applicationsImpedance calculations in AC circuits (Z from R, XL, and XC)Harmonic currents and nonlinear load effects on waveforms+8 more
General Code Requirements17 Q · 17%
NEC Article 90 purpose, scope, enforcement, and arrangement of the CodeArticle 100 definitions used across the Code (accessible, readily accessible, approved, listed, labeled, bonding, grounded, etc.)110.2-110.3 approval, listing, and use of equipment per instructions110.4-110.7 voltages, conductor material, insulation integrity110.9-110.10 interrupting rating and short-circuit current ratings110.11-110.13 deteriorating agents, workmanship, mounting and cooling of equipment110.14 electrical connections, terminal temperature ratings, and torque110.15-110.16 high-leg marking and arc-flash hazard warning labels110.21-110.25 equipment marking, disconnect identification, available fault current marking, lockable disconnecting means110.26 working space depth, width, height, entrance, and dedicated equipment space (600 V and below)110.27-110.28 guarding of live parts and enclosure types110.30-110.34 working space and guarding for installations over 1000 volts+3 more
Wiring and Protection17 Q · 17%
Grounding and bonding requirements for electrical systemsOvercurrent protection sizing and device selectionBranch circuit ratings and conductor ampacityGround fault circuit interrupter (GFCI) protection requirementsArc fault circuit interrupter (AFCI) protection requirementsSurge protection device requirementsConductor insulation types and wiring methodsService entrance and feeder protection requirementsVoltage drop calculations for branch circuits and feedersAmpacity correction and adjustment factors for conductorsLoad calculations and demand factors for feeders and servicesMultiwire branch circuit requirements and neutral conductor sizing+5 more
Wiring Methods & Materials16 Q · 16%
Cable and conduit types and their permitted usesConduit fill calculations and conductor allowancesInstallation requirements for NM, MC, and AC cableRaceway installation and support requirementsWiring methods in specific occupancies and environmentsConductor sizing, insulation types, and temperature ratingsProtection requirements for wiring methods (physical damage, wet locations)Boxes, fittings, and enclosure requirements for wiring systemsUnderground installation requirements including minimum cover depths and direct-burial methodsConductor grouping, continuity, and same-circuit requirements in racewaysConduit bending techniques including 90-degree, offset, saddle, and back-to-back bendsCorrosion protection and material suitability requirements for raceways and enclosures+5 more
General Equipment Use13 Q · 13%
Safe use and handling of electrical tools and equipmentEquipment ratings and selection for electrical applicationsGrounding and bonding of electrical equipmentOvercurrent protection requirements for equipmentEquipment installation and mounting requirementsDisconnecting means for electrical equipmentEquipment listing and labeling requirementsWorking clearances and access around electrical equipmentMotor full-load current tables and nameplate data interpretationMotor overload protection sizing and placementMotor branch-circuit conductor sizing requirementsTransformer sizing, turns ratios, and primary/secondary current calculations+6 more
Special Occupancies, Special Equipment, and Special Conditions8 Q · 8%
Hazardous locations classification (Class I, II, III; Divisions 1 and 2)Wiring methods and equipment permitted in hazardous locationsHealth care facilities electrical requirements (hospitals, nursing homes)Places of assembly occupancy wiring requirementsAgricultural buildings and structures electrical installationsElectric signs, outline lighting, and associated wiringSwimming pools, fountains, and similar installationsTemporary installations and construction site wiring requirementsSolar PV system disconnecting means and rapid shutdown requirementsEmergency and legally required standby system power sources and transfer equipmentEquipotential bonding requirements for swimming pools and similar installationsZone 0, 1, and 2 hazardous location classification and protection techniques+4 more
Communication Systems1 Q · 1%
Installation requirements for communication wiring and cablesArticle 800 telephone and telegraph systemsCoaxial cable installation and groundingNetwork-powered broadband communications systemsOptical fiber cables and racewaysBonding and grounding of communication systemsSeparation from power conductorsCommunication circuit protectors and surge protectionCable listing requirements and cable type substitutions (CMP, CMR, CMG, CMX, CATV, BM, BL types)Fire and smoke rating requirements for plenum, riser, and general-purpose cablesAbandoned cable removal requirementsOverhead aerial wire clearances and routing requirements above roofs and between buildings+5 more
Key Distinctions
Unit price method of estimatingvsQuantity take-off method
The unit price method bundles all cost factors (labor, materials, equipment, subcontractors) into a single price for the entire task, while the quantity take-off method estimates each component individually.
NASCLA Contractors Guide, Bidding and Estimating chapter — Other Methods of Estimating section
Capacitors at service equipment/panelsvsCapacitors at the individual loads
Capacitors at service equipment or electrical panels are primarily intended to reduce utility power factor penalties, while capacitors at the individual loads are what reduce circuit current, voltage drop, and wire power losses.
Mike Holt's Understanding Electrical Theory for NEC Applications, Page 153
MediationvsArbitration / judge
In mediation an independent third-party mediator only facilitates dialogue and the parties themselves set the conditions of any agreement, whereas an arbitrator or judge sets forth the terms of the agreement.
BuswayvsCable tray system / lighting track / multioutlet assembly
Article 100 defines a busway as a raceway (metal enclosure with factory-mounted bare or insulated conductors); a cable tray system is a structural support system for cables and raceways, lighting track is an assembly that supports and energizes luminaires, and a multioutlet assembly contains a raceway but is not itself defined as one.
NEC 2023 Article 100 — Definitions of Raceway, Busway, Cable Tray System, Lighting Track, and Multioutlet Assembly
Dwelling, MultifamilyvsTwo-family dwelling
A multifamily dwelling is a building containing three or more dwelling units; a building consisting solely of two dwelling units is a two-family dwelling (NEC 2023 Article 100).
NEC 2023 Article 100 — definition of Dwelling, Multifamily
Cable, Medium Voltage (Type MV)vsPortable power feeder cable
Type MV is a single or multiconductor solid dielectric insulated cable rated 2001 volts up to and including 35,000 volts nominal, while the 2001 to 25,000 volt range belongs to the separate definition of portable power feeder cable.
NEC 2023 Article 100 — Definition of 'Cable, Medium Voltage (Type MV)'
Energized electrical work permit, Part I (requester)vsEnergized electrical work permit, Part II (electrically qualified persons)
On the NFPA 70E 2024 Annex J Figure J.1 sample permit, Part I is completed by the requester (circuit/equipment description, job location, work to be done, justification for not de-energizing), while Part II items — risk assessment results, safe work practices, and means of restricting access — are completed by the electrically qualified persons.
NFPA 70E 2024, Informative Annex J, Figure J.1
Direct-buried cables/conductors — minimum covervsRigid metal conduit or intermediate metal conduit — minimum cover
In all locations not specified elsewhere in NEC Table 300.5(A), direct-buried cables or conductors require a minimum cover of 600 mm (24 in.) while RMC or IMC requires a minimum cover of 150 mm (6 in.).
NEC 2023 Table 300.5(A)
RMC under a one- and two-family dwelling drivewayvsRMC in 'all locations not specified' in Table 300.5(A)
A dwelling driveway/outdoor parking area used only for dwelling-related purposes is a specified location requiring 450 mm (18 in.) minimum cover for RMC, whereas the 150 mm (6 in.) RMC figure applies only to locations not specified (general streets, highways, roads, alleys, driveways and parking lots require 600 mm / 24 in. for all wiring methods).
NEC 2023 Table 300.5(A)
Commercial garage area up to 450 mm (18 in.) above floor WITH proper ventilationvsSame area WITHOUT adequate ventilation
Per Table 511.3(C) the area up to 450 mm (18 in.) above floor level is unclassified when mechanical ventilation of at least 0.3 m³/min/m² (1 cfm/ft²) of floor area is provided with exhaust taken within 300 mm (12 in.) of the floor, but is a Class I, Division 2 location when adequate ventilation is not provided.
A 12 AWG copper conductor with 90°C insulation such as THWN-2 has a 30-ampere ampacity in raceway with not more than three current-carrying conductors at 30°C, while 12 AWG flexible cord has a 20-ampere ampacity under Column A (three-conductor cords).
NEC 2023 Table 310.16
Overhead service conductor clearance over public streets/alleysvsOverhead service conductor clearance over residential property and driveways
Per 230.24(B), service conductors not over 1000 volts need a minimum 5.5 m (18 ft) over public streets, alleys, roads, parking areas subject to truck traffic and non-residential driveways, but only 3.7 m (12 ft) over residential property and driveways and commercial areas not subject to truck traffic where voltage does not exceed 300 volts to ground.
NEC 2023 Section 230.24(B)
Key Terms
Busway NEC 2023 Article 100 — Definitions of Raceway, Busway, Cable Tray System, Lighting Track, and Multioutlet Assembly
Article 100 defines a busway as a raceway consisting of a metal enclosure containing factory-mounted bare or insulated conductors.
Cable tray system NEC 2023 Article 100 — Definitions of Raceway, Busway, Cable Tray System, Lighting Track, and Multioutlet Assembly
A structural support system for cables and raceways; it is not itself defined by the Code as a raceway.
Lighting track NEC 2023 Article 100 — Definitions of Raceway, Busway, Cable Tray System, Lighting Track, and Multioutlet Assembly
An assembly that supports and energizes luminaires (not a raceway); track conductors shall be a minimum 12 AWG or equal and shall be copper.
Multioutlet assembly NEC 2023 Article 100 — Definitions of Raceway, Busway, Cable Tray System, Lighting Track, and Multioutlet Assembly
An assemblage that contains a raceway but is not itself defined by the Code as a raceway.
Cable, Medium Voltage (Type MV) NEC 2023 Article 100 — Definition of 'Cable, Medium Voltage (Type MV)'
A single or multiconductor solid dielectric insulated cable rated 2001 volts up to and including 35,000 volts, nominal (NEC 2023 Article 100).
Splash pad NEC 2023 Article 100 — definition of Splash Pad
A fountain intended for recreational use by pedestrians and designed to contain no more than 25 mm (1 in.) of water depth; the definition excludes showers intended for hygienic rinsing prior to use of a pool, spa, or other water feature.
Dwelling, Multifamily NEC 2023 Article 100 — definition of Dwelling, Multifamily
A building that contains three or more dwelling units (NEC 2023 Article 100).
Pull point NEC 2023 Section 358.24(B)
A point such as a conduit body that terminates a run for bend-counting purposes, so that each section between pull points may have up to 360° of bends (EMT, 358.24(B) in NEC 2023/2026; 358.26 in NEC 2017/2020).
Array boundary (PV rapid shutdown) NEC 2023 Section 690.12(B)
For rapid shutdown purposes the array boundary is 305 mm (1 ft) from the array in all directions; controlled conductors outside this boundary and more than 1 m (3 ft) from the array, or inside a building, must be limited to not more than 30 volts within 30 seconds of rapid shutdown initiation (690.12(B)).
Optional calculation for a dwelling unit (220.82(A)) NEC 2023 Section 220.82(A)
Applies to a dwelling unit having the total connected load served by a single 120/240-volt or 208Y/120-volt set of 3-wire service or feeder conductors with an ampacity of 100 or greater.
Indefinite delivery indefinite quantity (IDIQ) contract A Guide to the Project Management Body of Knowledge (PMBOK Guide), Section 4.6.8, Page 191
A contract providing for an indefinite quantity of goods or services, with a stated lower and upper limit, within a fixed time period (PMBOK Guide 4.6.8), commonly used for architectural, engineering, or IT engagements.
A form of alternative dispute resolution in which the parties themselves set the conditions of any agreement, with dialogue facilitated by a trained, independent third-party mediator.
A type of property insurance that can be purchased to protect tools and equipment and that covers goods in transit and projects under construction (an equipment floater is one type of inland marine policy).
Unit price method NASCLA Contractors Guide, Bidding and Estimating chapter — Other Methods of Estimating section
An estimating method that bundles all cost factors — labor, materials, equipment, and subcontractors — into a single unit price for the entire task.
THHN (insulation designation) Conductor insulation type letters (THHN)
T = thermoplastic insulation, HH = high heat resistance (90 degrees C dry), and N = a nylon outer jacket adding abrasion and gasoline/oil resistance.
kcmil Conductor sizing units (kcmil)
A conductor sizing unit where the prefix k stands for 1,000, so 1 kcmil = 1,000 circular mils; sizes larger than 4/0 AWG are expressed in kcmil.
Formulas to Know
Continuous-load sizing (feeder conductors and branch-circuit OCPD)Feeder conductor minimum ampacity = noncontinuous load + 125% of continuous load (215.2(A)(1)); e.g., 80 A + (60 A × 1.25) = 155 A. Branch-circuit overcurrent device rating shall not be less than 125% of the continuous load (210.20(A)); e.g., 16 A × 1.25 = 20 A.
Motor branch-circuit conductor ampacityMinimum ampacity = 125% × motor full-load current from the NEC motor FLC tables (430.22); example: 5 HP, 230 V, single-phase = 28 A (Table 430.248) × 1.25 = 35 A. For a wye-start, delta-run motor, conductors between controller and motor = not less than 72% of motor FLC (58% × 1.25) per 430.22(C).
Motor feeder conductor ampacityMinimum ampacity = (125% × FLC of largest motor) + sum of FLCs of all other motors (430.24); examples: (1.25 × 65 A) + 40 A = 121.25 A; three 15.2 A motors = (1.25 × 15.2) + 15.2 + 15.2 = 49.4 A.
Motor feeder overcurrent protective device maximumNot greater than largest branch-circuit short-circuit/ground-fault device rating + sum of FLCs of the other motors (430.62(A)); example: 90 A + 14 A + 10 A = 114 A, and since this is a maximum and 114 A is not standard per 240.6(A), select the next LOWER standard size, 110 A.
Motor branch-circuit short-circuit/ground-fault protection maximumsNontime delay fuse ≤ 300% of FLC for AC polyphase motors (e.g., 50 HP, 460 V = 65 A × 3.00 = 195 A; next standard size 200 A permitted by 430.52(C)(1) Ex. 1). Inverse time circuit breaker ≤ 250% of FLC (50 A × 2.5 = 125 A); if the motor will not start, 430.52(C)(1) Ex. 2 permits increase but in no case exceeding 400% of FLC for motors 100 A or less (50 A × 4 = 200 A) or 300% for motors above 100 A.
Non-dwelling receptacle load demand (Table 220.47)First 10 kVA at 100% + remainder over 10 kVA at 50%; example: 18 kVA → 10,000 VA + (8,000 × 0.50 = 4,000) = 14,000 VA.
Dwelling general lighting plus small-appliance and laundry loads (before demand factors)(Living area sq ft × 3 VA/sq ft) + (number of small-appliance circuits × 1,500 VA) + (number of laundry circuits × 1,500 VA); examples: 2,000 sq ft, 2 appliance + 1 laundry = 6,000 + 3,000 + 1,500 = 10,500 VA; 1,800 sq ft, 3 appliance + 2 laundry = 5,400 + 4,500 + 3,000 = 12,900 VA; four 1,200 sq ft units at 8,100 VA each = 32,400 VA.
Retail/store general lighting plus receptacle outlets (2020 or later NEC, before demand factors)(Area sq ft × 1.9 VA/sq ft for retail occupancy) + (number of receptacle outlets × 180 VA per yoke); example: 3,500 × 1.9 = 6,650 VA plus 20 × 180 = 3,600 VA → 10,250 VA. (3 VA/sq ft was the NEC 2017 store unit load; 1,500 VA per circuit applies only to dwelling small-appliance circuits.)
Junction box minimum dimension for an angle pull (314.28(A)(2))Distance to opposite wall = (6 × trade size of largest raceway) + sum of diameters of all other raceway entries in the same row on the same wall; example: (6 × 3 in. = 18) + 2 in. = 20 in.
Ohm's law and terminal power lossI = E / R (example: 240 V / 48 Ω = 5 A); power loss at a connection P = I² × R (example: 25 A × 25 A × 0.20 Ω = 125 W).