Exam Cheat Sheet · Quick Reference
South Carolina Water and Sewer Lines
South Carolina · PSI Services Contractor
South Carolina State Portion 50 questions
Key Distinctions
With a laser level and direct-reading rod, a cut is subtracted from the rod reading while a fill is ADDED to the rod reading before the road section is subtracted.
Excavation and Grading Handbook, Page 97 (Chapter 5 — Using a Laser Level on a Road Project section)Subgrade is rod reading ± cut/fill minus the full road section, while the aggregate base elevation adds the thickness of aggregate to be placed back onto that subgrade figure (e.g., 3.85 + 0.60 = 4.45).
Excavation and Grading Handbook, Page 97 (Chapter 5 — Using a Laser Level on a Road Project section)Bank yards are the in-place excavated volume, while loose yards are bank yards increased by the printed swell percentage, and haul-off (truck loads) is figured in loose yards, not bank yards.
Pipe and Excavation Contracting — Ch. 9, Estimating Surface Excavation (bank vs loose yards)Bell-and-spigot pipe for a 48-inch poured manhole is set 48 inches apart so a 4-foot form fits between the pipe ends, but for large pipe using precast rings there must be less than 48 inches between pipes so the pipe sides fall inside the ring.
Excavation and Grading Handbook, Page 419With a poured bottom the pipe is normally laid through the manhole, but pipe larger than 14 inches is stopped at the inside face of the manhole on each side.
Excavation and Grading Handbook, Page 444 (Chapter 24 — Manhole Bottoms)V-Bio (offered beginning in 2013) uses co-extrusion to infuse a corrosion inhibitor and an anti-microbial component into the innermost surface of the film and is the recommended film for ductile iron pipe in corrosive soils, installed per ANSI/AWWA C105/A21.5.
DIPRA Installation Guide for Ductile Iron Pipe, Pages 29 to 30 (Section 2.16 V-Bio Enhanced Polyethylene)The 10-point system addresses the likelihood of corrosion, while the DDM is a two-dimensional risk-based extension that also weighs the consequences of a pipeline failure in selecting a mitigation strategy (it extends but does not invalidate the 10-point system).
DIPRA Installation Guide for Ductile Iron Pipe, Pages 28 to 29 (Section 2.15 Corrosive Soil)Enriched means more than 23.5 percent oxygen by volume; deficient means less than 19.5 percent — either is a hazardous atmosphere under the confined spaces standard.
29 CFR 1926, §1926.1202Before being covered, enclosed, or placed in use, piping is hydrostatically tested to 150 percent of maximum anticipated pressure, or pneumatically tested to 110 percent of maximum anticipated pressure but not less than 5 psig at the highest point.
29 CFR 1926, §1926.152(j)(7)42 inches is the nominal installed top rail height, while 39 inches is the height below which the top edge may not deflect when the 200-pound downward load is applied within 2 inches of the top edge.
OSHA 29 CFR 1926, §1926.502(b)(4)A positioning device anchorage must support at least twice the potential impact load or 3,000 pounds, whichever is greater; personal fall arrest anchorage is 5,000 pounds per employee.
29 CFR 1926, §1926.502(e)(2)Type 3 is pipe bedded in 4-inch minimum loose soil with backfill lightly consolidated to the top of the pipe, whereas Type 2 is a flat-bottom trench consolidated only to pipe centerline, Type 4 is granular bedding to 1/8 pipe diameter with backfill at about 80 percent Standard Proctor, and Type 5 is compacted granular bedding to centerline with backfill at about 90 percent Standard Proctor.
DIPRA Installation Guide for Ductile Iron Pipe, Page 43 (Section 3.1 Standard Laying Conditions)Rule of thumb for subdivision fills: a Cat 815 when daily fill hauled is 4,500 cubic yards or less, and a Cat 825 for 4,500 to 8,000 cubic yards per day.
Excavation and Grading Handbook, Page 160 (Chapter 9 — Compactors section)Heaters other than integral heater-container units must be located at least 6 feet from any LP-Gas container, while blower and radiant type heaters shall not be directed toward any LP-Gas container within 20 feet.
OSHA 29 CFR 1926, §1926.153(h)(13)Key Terms
Formulas to Know
Subgrade = rod reading on hub + fill − road section thickness (e.g., 3.50 + 0.70 − 0.75 = 3.45; 4.20 + 0.50 − 0.85 = 3.85). Aggregate base = subgrade + thickness of aggregate to be placed (3.85 + 0.60 = 4.45). On a cut, the cut is subtracted instead of added.On a cut: boot height − cut (5.00 − 2.45 = 2.55 ft; a 4-ft boot on the same stake = 1.55 ft). On a fill: boot height + fill (2.45 + 5.00 = 7.45 ft).Thrust = tabulated 100-psi thrust × (operating pressure ÷ 100); e.g., 19,353 lb × (150/100) = 29,030 lb for a 12-in. 90-degree bend (the guide's own example at 125 psi gives 24,191 lb).Length = 2 × (long side + short side); Bank cu yd = length × width × depth ÷ 27. Example: 2 × (40 + 28) = 136 ft × 2.5 ft × 2 ft = 680 cu ft ÷ 27 = 25.19 cu yd; 2 × (40 + 24) = 128 ft × 2.5 × 2 = 640 ÷ 27 = 23.70 cu yd.Loose cu yd = bank cu yd × (1 + swell%). Examples: 25.19 × 1.30 = 32.74; 23.70 × 1.25 = 29.63; 512.00 × 1.20 = 614.40; 388.89 × 1.20 = 466.67; 456.00 × 1.20 = 547.20.Loads = loose cu yd ÷ truck capacity, rounded UP to the next whole load. Examples: 32.74 ÷ 12 = 2.73 → 3; 29.63 ÷ 14 = 2.12 → 3; 614.40 ÷ 10 = 61.44 → 62; 466.67 ÷ 12 = 38.89 → 39; 547.20 ÷ 14 = 39.09 → 40. Dividing bank volume by truck size under-counts loads.Additional loose cu yd = bank cu yd × 0.10. Examples: 25.19 × 0.10 = 2.52; 23.70 × 0.10 = 2.37; 512.00 × 0.10 = 51.20; 388.89 × 0.10 = 38.89; 456.00 × 0.10 = 45.60.Footprint = (length + 2 × overdig) × (width + 2 × overdig); Bank cu yd = footprint × depth ÷ 27. Examples: (44+4) × (28+4) = 1,536 sq ft × 9 ft = 13,824 ÷ 27 = 512.00 cu yd; (44+6) × (24+6) = 1,500 sq ft × 7 ft = 10,500 ÷ 27 = 388.89 cu yd; (32+6) × (30+6) = 1,368 sq ft × 9 ft = 12,312 ÷ 27 = 456.00 cu yd.Average elevation = sum of the four corner spot elevations ÷ 4 (e.g., (4.00+3.00+2.00+3.00) ÷ 4 = +3.00'); maximum elevation difference = highest corner − lowest corner (4.00 − 2.00 = 2.00'); Fill cu yd = lot area × (finished elev − average existing elev) ÷ 27 (6,000 sf × 1.00' = 6,000 cf ÷ 27 = 222.2 cy).Equal side setback = (lot dimension − house dimension) ÷ 2 (e.g., (78 − 42) ÷ 2 = 18'-0"); Rear yard = lot depth − front setback − house depth (110 − 24 − 30 = 56'-0"); Diagonal = √(front setback² + side setback²) = √(24² + 18²) = √900 = 30'-0".