Estimating, Plan Reading
Tennessee BC-C Industrial Contractor | 8 questions (11% of exam)
Key Concepts
Civil drawing types. A complete set is likely to include three classifications of drawings; the reference names architectural (appearance and finish of the structure) and structural (foundations, footings, and other loadbearing structures). Highway plans include plan and profile sheets and cross-sections; building site drawings include site plans, foundation plans, elevation drawings, and soil reports; as-built drawings are a separate drawing type covered in the module (Module 22209, Objective 1). A title sheet is placed at the beginning of a set or of a major section and may provide an index, a list of abbreviations, and a list of symbols; use the title sheet that comes with that…
General Code
Key Concepts
Administration and permits - A permit application for proposed work is deemed abandoned 180 days after the date of filing, unless the application has been pursued in good faith or a permit has been issued (IBC 105.3.2).
Occupancy classification - A building or tenant space used for assembly purposes with an occupant load of less than 50 persons is classified as Group B (IBC 303.1.1).
Height and area definitions - Area, building: the area within surrounding exterior walls, or exterior walls and fire walls, exclusive of vent shafts and courts; unwalled areas are included if within the horizontal projection of the roof or floor above (IBC 202). - Story above grade plane: a story with its finished…
Sitework
Key Concepts
Excavation safety (OSHA 29 CFR 1926, Subpart P) - A competent person is "one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them" (§1926.650(b)). - Subpart P "applies to all open excavations made in the earth's surface. Excavations are defined to include trenches" (§1926.650(a)). - Soil classification (Subpart P, Appendix A, paragraph (b)): Type A = cohesive soil with unconfined compressive strength of 1.5 tsf (144 kPa) or greater; Type B = greater than 0.5 tsf but less than 1.5 tsf; Type C = 0.5 tsf or less. Even at 1.5…
Footings and Foundations
Tennessee BC-C Industrial Contractor — 3 questions (4% of exam) Source: 2021 International Building Code, Chapter 18 — Soils and Foundations
Key Concepts
Geotechnical investigations (Section 1803) - Soil materials shall be classified in accordance with ASTM D2487 (Section 1803.5.1). - Expansive soil — soils meeting all four provisions are considered expansive, except that tests for Items 1, 2 and 3 are not required if the Item 4 test is conducted (Section 1803.5.3): 1. Plasticity index (PI) of 15 or greater (ASTM D4318) 2. More than 10 percent of soil particles pass a No. 200 sieve (75 µm) (ASTM D422) 3. More than 10 percent of soil particles are less than 5 micrometers in size (ASTM D422) 4.…
Concrete and Concrete Reinforcement
Tennessee BC-C Industrial Contractor · 17 questions (24%)
Key Concepts
Code minimums (IBC) - Concrete floor slabs supported directly on the ground: thickness not less than 3½ in. (89 mm); a 6-mil polyethylene vapor retarder with joints lapped not less than 6 in. goes between base course/subgrade and slab (IBC §1907.1). - Plain concrete footings: for Group R-3 occupancies and buildings of other occupancies less than two stories above grade plane of light-frame construction, required footing thickness is permitted to be 6 in. (152 mm), provided the footing does not extend more than 4 in. on either side of the supported wall (IBC §1906.1). - Anchor bolts attaching wood sill plates of light-frame wood structures to foundations/stem walls: embedded…
Masonry
Tennessee BC-C Industrial Contractor (6 questions, 9%)
Key Concepts
Material standards (IBC 2021, Chapter 21) - Mortar for masonry construction conforms to Articles 2.1 and 2.6 A of TMS 602 (Sec. 2103.2.1); grout conforms to Article 2.2 of TMS 602 (Sec. 2103.3). - Mortar for adhered masonry veneer: ASTM C270 Type N or S, or ANSI A118.4 for latex-modified portland cement mortar (Sec. 2103.2.4). - Adhered manufactured stone masonry veneer units: ASTM C1670 (Sec. 2103.1). - Ceramic tile set and grouted with chemical-resistant epoxy: ANSI A118.3, installed per ANSI A108.6 (Sec. 2103.2.3.3). Water-resistant organic adhesives: ANSI A136.1, shear bond strength after water immersion not less than 40 psi for Type I and **not less than 20 psi for Type…
Carpentry
Tennessee BC-C Industrial Contractor · 3 questions (4% of exam)
Key Concepts
Design method and sizing basics - Wall framing (exterior and interior) shall be in accordance with Section 2308 unless a specific design is furnished (IBC 2021, Section 2304.3). - Where dimensions of lumber are specified in Chapter 23, they are nominal dimensions unless specifically designated as actual (Section 2301.2). Computations to determine required member sizes shall be based on net dimensions (actual sizes), not nominal sizes (Section 2304.2). - Studs shall have full bearing on a 2-inch-thick (actual 1½-inch) or larger plate or sill having a width not less than equal to the width of the studs (Section 2304.3.1).
Structural Steel
Key Concepts
Pre-erection and site readiness - The steel erector must receive written notification that the concrete or mortar has attained either 75 percent of the intended minimum compressive design strength (based on an appropriate ASTM field-cured sample test method) or sufficient strength to support the loads imposed during steel erection — 29 CFR 1926.752(a)(1) and (b). - Job planning rests with the owner's designated representative for design (ODRD), who works with the owner's designated representative for construction (ODRC) — the party responsible to the owner for overall construction, planning, quality and completion, usually the general contractor or construction manager on site (Study Guide, Structural Ironworking Two, Sec. 2.3.1). - A competent person must determine the erection sequence before…
Roofing, Siding, and Insulation
Key Concepts
Roof slope limits and underlayment - Asphalt shingles shall only be used on roof slopes of 2 units vertical in 12 units horizontal (2:12) or greater; slopes from 2:12 to less than 4:12 require double underlayment (IBC 2021, Section 1507.2.2). - Asphalt shingles shall be tested in accordance with ASTM D7158 and meet the classification requirements of Table 1504.2 for the appropriate maximum basic wind speed; packaging must bear a label showing compliance. Shingles outside the scope of ASTM D7158 are tested and labeled to ASTM D3161 (IBC 1504.2). - Ballasted low-slope (roof slope < 2:12) single-ply roof system coverings installed per Section 1507.12 shall be designed in accordance with ANSI/SPRI RP-4 (IBC 1504.5).
Plumbing Concepts
Tennessee BC-C Industrial Contractor · 1 question (1% of exam) Source material: 2021 IBC, Chapter 29 (Plumbing Systems).
Key Concepts
- Scope. Chapter 29 and the International Plumbing Code govern design, construction, erection and installation of plumbing components, appliances, equipment and systems. Toilet and bathing rooms are constructed per Section 1210. (IBC 2021, Section 2901.1)
- Minimum fixtures. Fixtures shall be provided in the minimum number shown in Table 2902.1 based on the actual use of the building or space. Uses not shown in the table are considered individually by the code official. (Section 2902.1)
- Fixture calculations. To determine the occupant load of each sex, the total occupant load is divided in half; the fixture ratio(s) for each…
HVAC Concepts
The verified questions for this topic all come from one place: IBC 2021, Chapter 28 (Mechanical Systems), Section 2801.1. That single scope section is the highest-yield text available in the SOURCE.
Key Concepts
Chapter 28 is a linking chapter. The user note on page 652 of the 2021 International Building Code states: "Mechanical systems are a key element of any building. Chapter 28 regulates such systems by linking to the International Mechanical Code® and International Fuel Gas Code®, where details of mechanical system requirements are provided." Chapter 28 itself contains Section 2801, General, and Section 2801.1, Scope — the detailed technical rules live in the referenced codes.
Electrical Concepts
Emergency and Standby Power Systems (IBC Chapter 27)
The SOURCE for this topic is IBC 2021 Chapter 27, Electrical. It covers only Section 2701 (Scope) and Section 2702 (Emergency and Standby Power Systems). Nothing in the SOURCE addresses GFCI/AFCI protection, service sizing, grounding and bonding, branch circuits, receptacle spacing, wiring methods/conduit fill or panelboard clearances, so this brief is limited to the chapter's emergency and standby power provisions. The most efficient preparation is memorizing the numbered durations, capacities and ratings in Section 2702.
Key Concepts
OSHA Safety
Key Concepts
Fall protection - Employees engaged in residential construction 6 feet or more above lower levels must be protected by guardrail systems, scaffolding, a safety net system, or a personal fall arrest system — §1926.501(b)(13) (also BCSI B11 Fall Protection & Trusses, Page 89). - Employees on a walking/working surface with an unprotected side or edge 6 feet (1.8 m) or more above a lower level must be protected by guardrail, safety net, or personal fall arrest systems — §1926.501(b)(1). - Guardrail top rails must withstand, without failure, a force of at least 200 pounds (890 N) applied within 2 inches of the top edge, in any outward or downward direction, at any point along the top edge…