Arkansas Concrete - Residential Exam Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 30 questions (same as real exam)
- 75 minute time limit
- 6 topic areas covered
- 136 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
Arkansas Concrete - Residential Practice Exam Guide
What's on the exam
Questions per topic, out of 30This practice exam follows the official content outline for the Arkansas Concrete - Residential exam: Estimating, Layout and Excavation, Formwork, Reinforcing Steel, General Concrete, OSHA Safety.
- Free practice exam: 10 questions per attempt, retake as often as you like.
- Full practice exam: 30 questions on a 75 minutes clock, a new draw from our bank every attempt.
Estimating 3 items
Layout and Excavation 6 items
Formwork 4 items
Our study plan for this topic: Formwork safety requirements and failure prevention; Lateral pressure of concrete on forms (temperature, rate of placement, unit weight); Types of formwork systems (job-built, gang, flying table, slipform, jump form, ICF, stay-in-place); Form materials and hardware (plywood grades, lumber, steel, form ties, anchors, liners); Form design considerations and load calculations; Form removal timing and concrete strength requirements; Shoring and reshoring procedures for multistory construction; Formwork tolerances and dimensional accuracy (ACI 117).
Reinforcing Steel 4 items
General Concrete 9 items
OSHA Safety 4 items
Sample 1 — General Concrete
Question: You are a remodeling carpenter preparing to pour a concrete sidewalk that will be exposed to freeze-thaw cycles but will not receive deicing chemicals. You need to determine the appropriate nominal maximum aggregate size. The forms are 4 inches deep, and the narrowest vertical concrete member is 12 inches wide. Based on standard guidelines for aggregate sizing, what is the maximum nominal aggregate size you should use for this slab?
- A. 1-1/3 inches
- B. 3/4 inch
- C. 1-1/2 inches
- D. 1 inch
Correct Answer: A
The nominal maximum size of aggregate should not exceed one-third the depth of a slab. For a 4-inch slab, one-third of 4 inches equals approximately 1-1/3 inches. It must also not exceed one-fifth the narrowest dimension of a vertical member (12 ÷ 5 = 2.4 inches), so the slab depth governs at 1-1/3 inches.
Reference: Design and Control of Concrete Mixtures, 17th ed., Chapter 13 - Specifying, Designing, and Proportioning Concrete Mixtures, Page 267 (16th ed.: Page 358)
Sample 2 — Layout and Excavation
Question: A unit masonry foundation wall enclosing a below-grade interior space is to be dampproofed. Unless a material approved for direct application to the masonry is used, the wall must first receive a portland cement parging of what minimum thickness?
- A. 1/8 inch
- B. 1/4 inch
- C. 1/2 inch
- D. 3/8 inch
Correct Answer: D
IRC 2015 Section R406.1 requires masonry walls to have not less than 3/8 inch portland cement parging applied to the exterior of the wall before dampproofing, except where a material is approved for direct application to the masonry.
Reference: IRC 2015 Section R406.1
Sample 3 — Formwork
Question: In addition to standard cylinder break tests, which of the following is a recognized method for gauging in-place concrete strength by measuring the concrete's temperature over a period of time?
- A. Pullout testing
- B. Penetration resistance testing
- C. Maturity meter testing
- D. Rebound hammer testing
Correct Answer: C
According to the Contractor's Guide to Quality Concrete Construction, Chapter 5, maturity meters measure the temperature of the concrete over a period of time to calculate the strength. The text identifies pullout, penetration, and maturity meters as alternative methods to cylinder testing, but only the maturity meter method specifically works by measuring temperature over time. A correlation between the measured property and strength of the actual concrete mixture must be established prior to field testing.
Reference: Contractor's Guide to Quality Concrete Construction (4th ed.), Page 81
- Your results break the score down by outline topic.
- The real exam's passing score: 21 correct answers out of 30 scored questions.
- Keep practicing until you pass consistently, not just once.
- Answer what you know first and bookmark the rest. Our practice exams let you bookmark and come back.
- Work your bookmarks on the second pass.
- Real exam pace: about 2 minutes 30 seconds per question.
- After each attempt, look up every miss in your book.
| Questions | 30 questions |
| Time limit | 75 minutes |
| Passing score | 21 correct answers out of 30 scored questions |
| Books in the exam room | Open book |
Source: Arkansas Contractors Licensing Board – Concrete Residential, 10/17/2220. Check the bulletin before test day: fees and rules can change.