California General Building (B) Contractor Exam
Practice at the real exam's pace
Every practice exam shows your time per question against the real exam's clock (1:49 here), and each topic lands in one of these:
What's on the exam
Questions per topic, out of 115Topics
Planning and Estimating
Key Concepts
Plans, scale, and drawing conventions - Residential plan views are generally drawn at 1/4" = 1'-0"; each 1/4" on the drawing equals 1'-0" of building (Modern Carpentry, 14th Ed., Ch. 7 — Scale). - Schedules (window schedule, door schedule) list quantity, rough opening sizes, descriptions, and sometimes the manufacturer, keyed by marks to the plans and elevations (Ch. 7 — Schedules). - On a cutting-plane line, the top number is the drawing number and the lower designation is the sheet; arrowheads show the direction of view (Ch. 7 — Section and Detail Drawings). - Footings on a foundation plan are shown with thin dashed hidden lines, because grade/slab conceals them (Ch. 7 — Floor, Foundation, and Plot Plans / Alphabet of Lines). - Plot plans express boundaries and elevations in feet and decimals of a foot, read with an engineer's scale (Ch. 7 — Scale / Plot Plans). "S4S" means surfaced four sides (Appendix B — Standard Abbreviations).
Documents, delivery, and administration - Bidding requirements (advertisement/invitation, instructions to bidders, bid forms, bid bond forms) are not part of the contract for construction; the agreement, bonds, certificates, general and supplementary conditions, and addenda issued before acceptance of bids do become part of it (Olin's 9th Ed., 1.6.3.3). - A bid bond guarantees the bidder will sign an agreement based on the submitted bid or forfeit the bond (Olin's 1.7.2.1). - In CSI's three-part section format, Part 3 — Execution covers examination, preparation, installation, field quality control and testing, cleaning, protection, and coordination (Olin's 1.6.3.4). - Uniformat organizes by systems and assemblies for preliminary cost estimates and cost models; MasterFormat is organized by materials and uses; MasterFormat Division 07…
Framing and Structural Components
California General Building (B) Contractor Exam — 23 questions / 20%
Key Concepts
Sills, girders, posts (Modern Carpentry Ch. 10) - Sill anchor bolts: maximum spacing 6' OC, one bolt within 12" of each end, at least two bolts in each sill board (Sec. 10.3). Anchoring to unit masonry: 1/2" bolts extending at least 15 in. into filled cores; 7 in. is the embedment for concrete walls (Olin's 6.6.1.2). - Girder in a foundation pocket: minimum 4" bearing, with 1/2" clearance at sides and end (Sec. 10.2). - Wood posts shorter than 9': greater post dimension equals girder width — a 6" girder takes a 6x6; an 8" girder requires a 6x8 or 8x8 (Sec. 10.2).
Joists and subfloor - I-joists: flanges may never be cut; leave at least 1/8" of web above and below each hole; between two holes, uncut web must be at least twice the longest dimension of the largest adjacent hole; a 1 1/2" hole may be made anywhere in the web (Sec. 10.5). Bearing nailing: two 8d nails, one each side, no closer than 1 1/2" from the joist end (Sec. 10.4). - OSB subfloor: fasteners 6" at supported panel ends, 12" in the field, penetrating the joist 1". Plywood subfloor uses 6" along edges, 10" at intermediate members (Sec. 10.7). - Solid lumber joists deeper than nominal 12 in.: bridging at intervals not exceeding 8 feet (Fundamentals of Building Construction, 6th Ed., Ch. 5).
Core Trades
Key Concepts
Drainage, waste & vent (CPC) - Horizontal drainage piping slopes not less than 1/4 in. per foot; where the depth of the street sewer, structural features, or building arrangement make that impractical, building drain piping 4 inches and larger may slope not less than 1/8 in. per foot when first approved by the AHJ (CPC §708.1). - Vents may not be flagpoled except where the roof is used for assembly or parking; vents within 10 ft of such an area extend not less than 7 feet above the roof and are securely stayed (CPC §906.3). - Fixtures on a floor level lower than the next upstream manhole cover must be protected by a backwater valve; fixtures above that elevation shall not discharge through it. Cleanouts on drains through the valve are labeled "backwater valve downstream" (CPC §710.1). - Other than single-dwelling units, an ejector receiving water closets/urinals must pass a 2 in. solid ball, discharge piping not less than 3 in. with backwater valve and gate valve, capacity not less than 20 gpm. Single dwelling units: 1-1/2 in. ball, 2 in. piping (CPC §710.3).
Traps & interceptors - Tailpiece (fixture outlet to trap weir) shall not exceed 24 inches (CPC §1001.2). - Trap seal not less than 2 in. and not more than 4 in., unless the AHJ finds a deeper seal necessary (CPC §1005.1). - "S" traps, bell traps, and crown-vented traps are prohibited; drum and bottle traps are for special conditions only (CPC §1004.1). - Fixture capacity discharging to a hydromechanical grease interceptor shall not exceed 2.5 × the certified gpm (CPC §1014.2.1).
Finish Trades
California General Building (B) Contractor Exam — Finish Trades
Key Concepts
Floor covering — wood - Blind nail succeeding strips through the tongue at about 50°, countersinking the fastener; only the starter strip (and the last few strips) is face nailed (Modern Carpentry 14th Ed., Ch. 20, Installing Wood Strip Flooring—Nailing). - Installation moisture content: about 6% in the dry southwestern states, about 10% in the more humid southern states, 7%–8% elsewhere (Ch. 20, Installing Wood Strip Flooring). Flooring stock is kiln-dried to 6% to 9% before milling (Olin's 9th Ed., 9.10.2.1). - Sleepers in mastic over slab: lap at least 3" with 2 1/4" flooring, 4" with 3 1/4" flooring; sleeper centers normally 12"–16" (Ch. 20, Wood Flooring over Concrete). - Plywood subfloor over slab: 3/4" spacing at walls, 1/4"–1/2" between panels, at least nine concrete nails per panel (Ch. 20). - Parquet/unit block: mastic spread 3/32" thick; about 1/2" expansion space at the wall (Ch. 20, Wood Block (Parquet) Flooring). - Laminate plank: end joints in adjacent rows offset at least 8"; don't start a row with a cutoff shorter than 8" (Ch. 20, Installing Laminate Flooring). - Board subfloor joists: not more than 16 in. o.c. when 3/4 in. strip/plank runs parallel to joists; 24 in. o.c. applies only when finish flooring runs at right angles (Olin's 9.10.1.3). - MFMA edge grain (quarter-sawn): annual rings at over 30 degrees to the face (Olin's 9.10.3.2).
Safety
Key Concepts
Personnel safety / PPE - Protective equipment must be distinctly marked to identify the manufacturer; exception for employer-manufactured shields, barriers, etc. (§3380(b)). - The written hazard-assessment certification must identify the workplace evaluated, the person certifying, the date(s), and identify the document as a certification of hazard assessment (§3380(f)(2)). PPE selection is a separate duty under §3380(f)(1)(A). - §3380(f) does not apply to workplace operations regulated by the Construction Safety Orders or Mine Safety Orders (§3380(f)(8)). - Hard hats: permanent marking identifies manufacturer, ANSI standard number and date, and ANSI class and impact type (§3381(d)). - Hand protection for cuts/lacerations/abrasions is not required only when the §3380(f) assessment finds the risk infrequent and superficial (§3384(a) Exception). - Footwear purchased after 1/26/2007: ASTM F2412-05 and F2413-05 (§3385(c)(1)). Purchased on or before that date: ANSI Z41-1999 or the ASTM standards (§3385(c)(2)). - Hearing protection required at 85 decibels or above for eight hours (Modern Carpentry Sec. 2.3).
Electrical — GFCI vs. assured grounding program (§2405.4) - GFCIs required on all 120-volt, single-phase, 15- and 20-ampere construction site receptacles not part of permanent wiring; exemption for two-wire single-phase portable/vehicle-mounted generators rated not more than 5 KW with conductors insulated from the frame and grounded surfaces (§2405.4(c)). - Daily visual inspection before each day's use, except cord sets and receptacles that are fixed and not exposed to damage (§2405.4(d)(3)). - Continuity/terminal tests at intervals not to exceed 3 months; fixed, undamaged-exposure cord sets and receptacles not exceeding 6 months; also before first use, after repairs, and after a suspected damaging incident (§2405.4(d)(5)). - Identification must indicate the last test date or the interval tested (§2405.4(d)(7)).