California General Building (B) Contractor Exam Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 115 questions
- 210 minute time limit
- 5 topic areas covered
- 499 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
California General Building (B) Contractor Practice Exam Guide
What's on the exam
Approximate share of the exam, by topicThis practice exam is laid out like the official content outline for the California General Building (B) Contractor exam: Planning and Estimating, Framing and Structural Components, Core Trades, Finish Trades, Safety.
Two ways to practice: the free practice exam gives you 10 questions per attempt, as often as you want. The full practice exam gives you 115 questions on a 210 minutes clock, with a new draw from our question bank every time.
Planning and Estimating — about 15% of the exam
The outline lists: Scope of work and code compliance; Design and construction error identification; Shop drawings, plans, and specifications; Field inspection performance; Coordination of project; Cost estimation for materials, equipment, and labor. Our study plan adds: Permit application requirements and construction document submittals; Building height, area, and type of construction limitations.
Framing and Structural Components — about 20% of the exam
The outline lists: Subfloor and wall framing; Roof framing; Seismic hardware requirements and installation; Siding and stucco; Decks and stairs. Our study plan adds: Lumber grading, species, and sizing for framing; Engineered wood products (I-joists, LVL, glulam, CLT, structural composite lumber); Wood structural panel sheathing (plywood and OSB) grades, span ratings, and fastening.
Core Trades — about 30% of the exam
The outline lists: Plumbing; Electrical; HVAC; Concrete; Earthwork and surveying; Insulation, acoustical, and weatherproofing; Roofing. Our study plan adds: Water heater installation, venting, and safety devices.
Finish Trades — about 20% of the exam
The outline lists: Painting, staining, coating, and interior wall covering; Tile and stone; Floor covering; Cabinetry and millwork; Plaster, drywall, and ceilings; Windows, skylights, and doors; Landscaping. Our study plan adds: Interior finish flame spread and smoke development classifications (CBC Chapter 8).
Safety — about 15% of the exam
The outline lists: Personnel safety; Transportation and traffic control; Environmental safety. Our study plan adds: Fall protection and guardrail systems; Excavation and trenching safety; Scaffolding requirements and use; Hazard communication and Safety Data Sheets (SDS); Fire protection and prevention during construction.
Sample 1 — Core Trades
Question: You are installing a domestic Type 1 clothes dryer exhaust duct of rigid metal. The routing requires four 90-degree elbows, no dryer exhaust duct power ventilator is used, and the dryer manufacturer's instructions give no greater length. What is the maximum permitted total combined horizontal and vertical duct length?
- A. 12 feet
- B. 8 feet
- C. 14 feet
- D. 10 feet
Correct Answer: D
Domestic dryer moisture exhaust ducts are limited to a total combined horizontal and vertical length of 14 feet including two 90-degree elbows, with 2 feet deducted for each 90-degree elbow in excess of two. With four elbows, two are in excess: 14 ft − (2 × 2 ft) = 10 feet. Only an approved power ventilator installation or dryer manufacturer instructions accepted by the AHJ permit a longer run.
Reference: California Mechanical Code 2025, Section 504.4.2.1
Sample 2 — Framing and Structural Components
Question: On a wood-framed building you propose fastening the sill plates with hardened steel studs driven by powder-actuated tools instead of 1/2 in. anchor bolts. These fasteners are not specifically covered by the international codes but may be accepted as an alternate, subject to ICC evaluation report requirements, EXCEPT:
- A. when the building is located in a high-wind region
- B. when the sill is anchored to unit masonry
- C. when the first floor acts as a diaphragm
- D. when earthquake design is required
Correct Answer: D
Hardened steel studs driven by powder-actuated tools are not specifically addressed in the international codes, but may be allowed as an alternate to anchor bolts except when earthquake design is required. Their spacing must not exceed that required by the applicable ICC evaluation report.
Reference: Olin's Construction, 9th Ed., Section 6.6.1.2 (Anchorage Recommendations)
Sample 3 — Finish Trades
Question: Inside a quality paint brush, completely surrounded by the bristles, is a plug made of wood, metal, fiber, or plastic. The plug's function is to ___.
- A. keep the bristle tips flagged
- B. taper the stock toward the tip
- C. lock the bristles into the ferrule
- D. create a reservoir that holds paint
Correct Answer: D
The plug set inside the bristle stock creates a reservoir that holds paint. Quality brushes also have a smooth taper from ferrule to tip, formed by varying bristle lengths, and flagged tips that hold paint by capillary action.
Reference: Modern Carpentry, 14th Ed., Ch. 24, Brushes
Your first attempt is an inspection, not a final grade. The results page breaks your score down by outline topic, so you can see which areas need work. Keep practicing until you pass consistently.
- On our practice exams, answer what you know first and bookmark the rest; you can come back to bookmarked questions.
- Work your bookmarks on the second pass.
- After each attempt, read the cited reference section for each question you missed.
| Questions | Not published by the board |
| Time limit | 210 minutes |
| Passing score | Not published by the board |
| Books in the exam room | Closed book (no books in the room) |
| Exam fee | $51.43 |
- You receive a printed score report at the test center at the end of the examination, and results are never given over the phone.
- You may retake the examination after waiting 21 calendar days, as many times as needed before your void date, paying PSI a fee for each attempt.
Source: Contractors State License Board Licensing Examination Information Guide — General Building (B). Check the bulletin before test day: fees and rules can change.