Louisiana Horizontal Directional Drilling
Practice at the real exam's pace
Every practice exam shows your time per question against the real exam's clock (2:30 here), and each topic lands in one of these:
What's on the exam
Questions per topic, out of 30Topics
Piles
Key Concepts
- Two classifications by use: (1) sheet piles and (2) load-bearing piles. Sheet piles create a rigid barrier for earth or water — cutoff walls under dams, cofferdams, bulkheads, trench support. By material, the major sheet pile types are steel, prestressed concrete, and timber. (Ch. 17, PILE TYPES — CLASSIFICATIONS OF PILES)
- Load transfer defines the pile: if load is transmitted through skin friction between the pile surface and the soil, it is a friction pile; if transmitted through the pile's lower tip, it is an end-bearing pile. Many piles depend on a combination of both. (Ch. 17, INTRODUCTION)
- Load-bearing pile material types: Timber (treated with a preservative / untreated); Concrete (precast-prestressed, cast-in-place with shells, augered cast-in-place); Steel (H section, steel pipe); Composite (concrete and steel, plastic with steel pipe core). (Ch. 17, CLASSIFICATIONS OF PILES)
- Treated timber service life: 50 years in northern marine waters; 20 years in southern waters, defined as south of Cape Hatteras on the East Coast and below San Francisco on the West Coast. (Ch. 17, TIMBER PILES — Treated Timber Piles)
- Timber pile acceptance: use ASTM D 25–12 Standard Specification for Round Timber Piles. Minimum nominal circumference is measured 3 ft from the butt and toe. A straight line from center of butt to center of tip must lie entirely within the body of the pile. Piles must be free…
Excavation and Grading
Louisiana Horizontal Directional Drilling | 6 questions (20% of exam)
Key Concepts
Volume states (bank / loose / compacted) - Solid rock will swell 20 to 40% from bank to placement in an embankment; between the bank and loose states, solid rock swells as much as 65% — a different measurement. (Construction Planning, Equipment, and Methods, 9th ed., Ch. 4 — Soil and Rock, Volumetric Measure) - Most cohesive soils shrink 10 to 30% from bank (in situ) to compacted; bank to loose, cohesive soils swell about 40%. (Same citation) - For asphalt and concrete slabs, always allow a swell factor of 1.7 from in-place (bank) volume to loose disturbed volume. (Pipe and Excavation Contracting, Page 138) - Haul-off is always figured in loose yards, and partial loads round up to the next whole truckload. (Pipe and Excavation Contracting — Ch. 9, Estimating Surface Excavation)
Earthwork volume sheet and mass diagram (CPEM 9th ed., Ch. 3) - Stripping over a cut is subtracted from the cut volume (organic material cannot be used as structural fill); stripping under a fill is added to the fill requirement. (Stripping / Earthwork Volume Sheet sections) - Sum of the absolute values of the mass diagram peaks and low points = material moved longitudinally; total cut within project limits minus that sum = crosshaul, commonly treated as dozer work. (Haul Distances section) - When machines work as…
Trenching and Boring
Exam: Louisiana Horizontal Directional Drilling · Weight: 3 questions (10%)
Key Concepts
Soil stability and classification - Some cemented soils are quite stable, but it is wise to consider all trench walls over 5 feet high to be dangerous — any trench can collapse (Pipe and Excavation Contracting, Page 171). - It is dangerous and illegal to have anyone working in a trench over 5 feet deep unless the trench is protected with some kind of cave-in deterrent (Page 171). - Factors beyond the angle-of-repose chart that affect stability (Page 171): damp or saturated soil is much less stable than dry earth; changing soil conditions can make a trench wall unsafe — a vertical wall may be safe in cemented gravel, but a pocket of loose sand or heavy loam makes it dangerous; disturbed earth can become unstable (another trench being dug nearby, or nearby vibratory compaction equipment); piling spoil near the edge of the ditch can destabilize the walls. - Wet sandy spoil from the bottom of a trench piled on the banks drains quickly; the water seeps into the bank and lubricates the soil, possibly causing an otherwise stable bank to slip. An experienced operator should foresee and avoid this (Page 164).
Underground Piping including Pipe Welding, Concrete, Ductile Iron
Key Concepts
Pipe Joint Preparation & Fit-Up (Pipe Welding Procedures, Ch. 4)
- Groove angle: Welds completed uphill use a 75-degree included angle — a 37½-degree bevel on each pipe end. Downhill welding uses a narrower 60-degree groove angle (Modern Welding p. 23-6; Pipe Welding Procedures Ch. 4).
- Root face for heavy-wall pipe (SMAW): 3/32 to 1/8 inch (Fig. 4-2).
- Maximum misalignment between the inside surfaces of two fitted pipes: 1/16 inch, per the ASME Code. Inside and outside surfaces must blend smoothly (Fig. 4-4).
- Tack welding: four tack welds evenly spaced around the pipe in the root, each about ¾ inch long, using a 1/8-inch E6010 electrode on the practice joint. Tacks remain part of the root bead and must penetrate fully.
- Keyhole size: about 1½ times the diameter across the electrode coating. Correct keyhole produces a crown about 1/16 inch above the inside pipe surface (Ch. 4–5).
- Stopping the root bead: push the electrode through the keyhole with a quick stab, then withdraw quickly. This preserves a full-size keyhole for full penetration on restart/tie-in (Fig. 4-10).
Underground Electrical Cable Installation and Safety
Key Concepts
Minimum cover and depth - Direct-buried cable, conduit, or other raceways shall meet the minimum cover requirements of Table 300.5 [300.5(A)]. Rigid metal conduit and intermediate metal conduit require a minimum cover of 6 in. for 0–1000-volt circuits in most general locations [Table 300.5]. - Over 1000 volts, depths come from Table 300.50. In industrial establishments with qualified maintenance and supervision, cover (for other than RMC and IMC) may be reduced 6 in. for each 2 in. of concrete or equivalent placed entirely within the trench over the installation [Table 300.50, General Note 3].
Protection from damage - Conductors emerging from grade are protected by enclosures or raceways from the minimum cover depth to at least 2.5 m (8 ft) above finished grade; in no case is protection required to exceed 450 mm (18 in.) below finished grade [300.5(D)(1)]. Conductors entering a building are protected to the point of entrance [300.5(D)(2)]. - Underground service conductors not encased in concrete and buried 18 in. or more below grade must have a warning ribbon in the trench at least 300 mm (12 in.) above the installation [300.5(D)(3)]. - Where the enclosure or raceway is subject to physical damage: EMT, RMC, IMC, RTRC-XW, Schedule 80 PVC, or equivalent [300.5(D)(4)]. Over 1000 volts, raceways on poles are RMC, IMC, RTRC-XW, Schedule 80 PVC, or equivalent, from minimum cover depth to 8 ft above grade…
OSHA Safety
Key Concepts
Excavations (Subpart P) - Each employee in an excavation must be protected from cave-ins by an adequate protective system except when the excavation is made entirely in stable rock, or is less than 5 feet (1.52 m) deep and a competent person's examination of the ground gives no indication of a potential cave-in — §1926.652(a)(1). - Keep excavated material and equipment at least 2 feet (.61 m) from the edge, use sufficient retaining devices, or combine both — §1926.651(j)(2). - Deviation from a manufacturer's specifications, recommendations and limitations for a shield/shoring system is allowed only after the manufacturer issues specific written approval, and that approval must be in written form at the jobsite — §1926.652(c)(2)(ii). - Subpart AA (Confined Spaces) does not apply to construction work regulated by subpart P (Excavations), subpart S, or subpart Y — §1926.1201(b).
Confined Spaces (Subpart AA) - Oxygen enriched atmosphere: more than 23.5 percent oxygen by volume; oxygen deficient: less than 19.5 percent — §1926.1202. - Alternate-procedure entry testing order with a calibrated direct-reading instrument: oxygen, then flammable gases and vapors, then potential toxic air contaminants — §1926.1203(e)(2)(iii). - If purging/ventilating cannot bring the atmosphere below 10 percent of the LFL, entry is allowed only if the employer inerts the space so the entire atmosphere is non-combustible, employees use PPE for other atmospheric hazards, and all physical hazards are eliminated or isolated — §1926.1204(c)(4).…