EN ES
Missouri · Pearson VUE

Kansas City, MO Master Gas Pipe Fitter Exam (ICC G33, 2018 IFGC)

Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) exam study guide: the bulletin's key facts, the official outline, the reference books and sample questions with answers.

75 questions 180 minutes 70% to pass 6 topics 2:24 per question Open book 304 questions in pool Bulletin: November 2025
Full practice exam $9.95
  • 75 questions on a 180-minute clock, like the real exam
  • Every answer explained; code questions cite the book and section so you can find it in your own copy
  • A fresh draw from 304 questions each attempt
Try 10 free questions
Study Course $59.95/month
  • Unlimited full exams, topic quizzes and study briefs
  • Cancel anytime
See the study course
Not sure which exam you need? Text us: (813) 582-5360
Texts preferred · 9am–9pm Central
On this page

Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Exam Study Guide

This guide covers what you need for the Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) exam: the key facts from the official bulletin, the topics it tests, the reference books, sample questions with answers, and a plan to prepare. Pearson VUE gives the exam.

Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Exam at a Glance

Here are the exam's key facts from the official bulletin:

Questions 75 questions
Time limit 3 hours
Passing score a minimum score of 70
Books in the exam room Open book
Exam fee $115

On exam day

  • Questions are four-option multiple choice with one correct answer.

References you may bring

  • International Fuel Gas Code (2018)

Scheduling, changes and retakes

  • Exams are scheduled through Pearson VUE at www.pearsonvue.com/ICC.
  • Results for electronically administered examinations are available immediately after the exam is completed.
  • You must wait 10 days before retaking a failed exam.
  • After passing, contact the jurisdiction for any other requirements needed to become licensed.

Source: Kansas City, Missouri Examination Information Bulletin (ICC Contractor/Trades), PUBLISHED November 10, 2025. Check the bulletin before test day: fees and rules can change.

What the Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Exam Covers

The official content outline has 6 topics:

Topic Questions Share of the exam
General Requirements 37 49%
Water Heaters 4 5%
Appliances and Equipment 11 15%
Fuel Supply System Sizing 4 6%
Combustion Air 10 13%
Chimneys and Vents 9 12%

How to Prepare for the Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Exam

Start with the books. This is an open-book exam, so the references on the bulletin's list are your main study tool. Get the editions the bulletin names.

Learn where things are. Read the table of contents and the index of each book until you know where every major subject lives. On test day, finding an answer fast matters more than memorizing it.

Highlight the sections you use most. Check the bulletin's rules on tabs and markings before you add any.

Spend most of your time on the biggest topics. General Requirements and Appliances and Equipment make up 64% of the exam.

Take timed practice exams. The clock trains you to find answers at the pace the real exam needs: about 2 minutes 24 seconds per question.

Aim to pass more than once. One passing score can be luck. Several in a row means you're ready.

Reference Books for the Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Exam

The only reference listed for this open-book exam is the 2018 International Fuel Gas Code.

Where to get them:

On Test Day

  • Go through the whole exam first. Answer every question you know and bookmark the ones you don't. Every exam lets you come back to bookmarked questions, but some lock the questions you've seen once you take a break, so work your bookmarks before any break.
  • Then go back to your bookmarks and work them out.
  • Don't let one question eat your time. You have 3 hours for 75 questions, which is about 2 minutes 24 seconds per question.
  • Before you finish, answer anything you skipped. A blank can't earn a point.

Study Tips

On technical questions, don't get bogged down in unfamiliar terminology. If you don't recognize a term, you're unlikely to figure it out on the spot—acknowledge it quickly and move on. Use the surrounding context, answer choices, and familiar terms to guide your reasoning, but don't linger on any single difficult question.

Practicing against a ticking clock is the best way to beat exam-clock anxiety. Use these timed tests to build your pacing, so you learn to move steadily and never burn too long on a single question. By test day, the format feels routine.

If you're stuck on a problem, don't waste time—move on. Before you do, however, quickly eliminate any obviously wrong answer choices. Even ruling out one or two options significantly improves your odds of guessing correctly. Eliminate what you can, make your best guess, then move on.

You're given plenty of time, so use as much of it as you need. Don't get rattled when other people finish early — finishing first isn't a prize. Work at your own steady pace and review your answers before you submit.

Sample Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) Practice Questions

These questions come from our practice question bank, each with its answer and reference.

Sample 1 — Chimneys and Vents

Question: When sizing a chimney venting system connected to two draft-hood-equipped appliances, the effective area of the chimney flue shall not be greater than what multiple of the smallest draft hood outlet area?

  • A. Three times
  • B. Seven times
  • C. Ten times
  • D. Five times

Correct Answer: B

Per IFGC Section 503.5.5, Item 3, for sizing a chimney venting system connected to two appliances with draft hoods, the effective area of the chimney flue shall not be greater than seven times the smallest draft hood outlet area.

Reference: IFGC 2018 Section 503.5.5

Sample 2 — Water Heaters

Question: The aggregate input rating of all unvented gas appliances installed in a room or space shall not exceed what maximum value per cubic foot of room volume?

  • A. 20 Btu/h per cubic foot
  • B. 30 Btu/h per cubic foot
  • C. 10 Btu/h per cubic foot
  • D. 40 Btu/h per cubic foot

Correct Answer: A

Per IFGC Section 621.5, the aggregate input rating of all unvented appliances installed in a room or space shall not exceed 20 Btu/h per cubic foot of volume of such room or space.

Reference: IFGC 2018 Section 621.5

Sample 3 — Fuel Supply System Sizing

Question: Steel tubing used in a fuel gas piping system must comply with which standard?

  • A. ASTM A106
  • B. ASTM A254
  • C. ASTM A53/A53M
  • D. ASTM A312

Correct Answer: B

Per IFGC Section 403.5.1, steel tubing shall comply with ASTM A254. Options A, B, and D are standards for steel pipe (not tubing), as listed in Section 403.4.2.

Reference: IFGC 2018 Section 403.5.1

Sample 4 — General Requirements

Question: As the master fitter on a commercial repair garage project, you are mounting a unit heater in an area frequented by motor vehicles, in a location where vehicles are capable of passing beneath it. The tallest vehicle garage door opening is 12 feet. Disregarding any greater clearance in the manufacturer's instructions, what is the minimum installation height above the floor?

  • A. 13 feet
  • B. 6 feet
  • C. 8 feet
  • D. 12 feet

Correct Answer: A

IFGC 305.4 requires appliances in public garages, repair garages and similar areas to be installed not less than 8 feet above the floor; however, where motor vehicles can pass under the appliance, it must be installed at the manufacturer's required clearances and not less than 1 foot higher than the tallest vehicle garage door opening — 12 ft + 1 ft = 13 feet. The 6-foot figure applies to private garages (305.5).

Reference: IFGC 2018 Sections 305.4, 305.5

Why Practice Online Instead of With a PDF

A PDF shows you questions. It doesn't show you the clock. Our practice exams are timed and on a screen, so you practice finding answers under time pressure, not just reading them. Each attempt draws a new set of questions from our bank, and your results break the score down by outline topic so you know what to study next.

Start Practicing

Take the free Kansas City, MO Master Gas Pipe Fitter (ICC G33, 2018 IFGC) practice exam to see where you stand, then work through the topics that need attention. For the official rules, read the exam bulletin, and see the licensing board's website.

Frequently Asked Questions

How much does the Kansas City, MO Master Gas Pipe Fitter exam (ICC G33) cost?
The exam fee is $115, paid through Pearson VUE when you register.
How many questions are on the Kansas City, MO G33 Master Gas Pipe Fitter exam, and how long do I have?
The exam has 75 multiple-choice questions and a 3-hour time limit. Each question has four answer choices with one correct answer.
What is the passing score for the Kansas City, MO G33 exam?
You need to answer 70% of questions correctly to pass.
Is the Kansas City, MO Master Gas Pipe Fitter exam (G33) open book?
Yes, it is open book. The only approved reference is the 2018 International Fuel Gas Code (IFGC). No other books are listed as approved for this exam.
Can I bring study guides or practice questions into the G33 exam?
The Kansas City bulletin does not address study guides or practice questions; it lists only the approved reference for this exam, the 2018 International Fuel Gas Code. Check the ICC Exam Catalog and Pearson VUE for current test-center rules before test day.
How do I register for the Kansas City, MO G33 Master Gas Pipe Fitter exam?
The exam is administered through Pearson VUE. Visit pearsonvue.com/ICC to create an account, schedule your exam, locate a test center, and purchase a test voucher.
When will I get my results after taking the G33 exam?
Results are available immediately after you complete the exam at the Pearson VUE test center.
How soon can I retake the Kansas City, MO G33 exam if I fail?
You must wait at least 10 days before retaking a failed exam. The bulletin recommends using that time to study the approved reference before scheduling again.
Does passing the Kansas City, MO G33 exam mean I am licensed as a Master Gas Pipe Fitter?
No. ICC is not a licensing agency. Passing the exam demonstrates your competency, but the Kansas City licensing authority determines whether to accept the exam result and sets all other requirements for licensure. Contact that authority directly to confirm their requirements.
What topics are covered on the Kansas City, MO G33 Master Gas Pipe Fitter exam?
The exam covers General Requirements (49%), Appliances and Equipment (15%), Combustion Air (13%), Chimneys and Vents (12%), Water Heaters (5%), and Fuel Supply System Sizing (6%), all based on the 2018 International Fuel Gas Code.

Reference books

1 book on the bulletin
As an Amazon Associate we earn from qualifying purchases.
Took this practice exam? Tell other candidates how it went.
10 free questions30 min · no account
Start Free Exam