ICC F14 Roofing Contractor Exam (2015 IBC/IRC/IPC) Practice Exam
ICC retires this exam on December 1, 2026: from that date it can no longer be registered through Pearson VUE (ICC Exam Catalog, checked November 10, 2026). If you are registering on or after December 1, take the version on the 2018 codes, ICC G14. It has no retirement date listed, and we have a practice test for it.
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real Pearson VUE test format.
- 60 questions (same as real exam)
- 180 minute time limit
- 4 topic areas covered
- 256 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
ICC F14 Roofing Contractor (2015 IBC/IRC/IPC) Practice Exam Guide
What's on the exam
Questions per topic, out of 60This practice exam follows the official content outline for the ICC F14 Roofing Contractor (2015 IBC/IRC/IPC) exam: Administration and General Requirements, Types of Roofing Material and Application, Fasteners, Flashings, Drainage, and Scuppers, Re-roofing.
You have two ways to practice. The free practice exam gives you 10 questions per attempt, and you can retake it as often as you like. The full practice exam gives you 60 questions on a 3 hours clock, with a new draw from our question bank every attempt.
Administration and General Requirements 15 items
Our study plan for this topic: Administration; Code Definitions and Terms; Job Planning and Setup; Permits and Permit Applications; Inspections and Required Inspection Types; Certificate of Occupancy; Building Official Authority and Enforcement Powers; Violations, Stop Work Orders, and Penalties.
Types of Roofing Material and Application 21 items
Our study plan for this topic: Shingle Roofing; Flat Roof; Hot Mopping and Other Membranes; Clay and Concrete Tile Roofing; Metal Roof Panels and Metal Roof Shingles; Wood Shingles and Wood Shakes; Slate Shingles; Single-Ply Membrane Roofing (Thermoset and Thermoplastic).
Fasteners, Flashings, Drainage, and Scuppers 17 items
Our study plan for this topic: Fasteners; Flashings and Accessory Materials; Roof Drains, Gutters, and Scupper; Drip edge installation requirements and fastening; Valley lining materials and installation methods; Crickets and saddles for chimneys and penetrations; Ice barriers and high-wind underlayment attachment; Primary roof drainage design and minimum slope requirements.
Re-roofing 7 items
Our study plan for this topic: Remove Roofing Materials or Add Additional Layers; Repair Roof Structure and Roof-Ceiling Assemblies; Roof recover vs. roof replacement distinctions and limitations; Conditions prohibiting roof re-cover (water-soaked deck, existing layer count, material type); Reinstallation and reuse of existing roofing materials (tile, slate, flashings, aggregate); Flashing reconstruction requirements during reroofing; Structural load capacity requirements during reroofing installation; Combustible concealed space treatment when recovering over wood shingles or shakes.
Sample 1 — Types of Roofing Material and Application
Question: You are replacing the membrane on an existing low-slope roof that is framed at one-eighth unit vertical in 12 units horizontal but that drains positively with no ponding. How does the minimum design slope of one-quarter unit vertical in 12 units horizontal apply to this reroofing work?
- A. Overflow scuppers must be added to the existing parapet
- B. The roof deck must be re-framed to the minimum slope
- C. The minimum design slope requirement need not be met
- D. Tapered insulation must be added to reach the minimum slope
Correct Answer: C
IRC 2015 Section R908.1, Exception 1, states that reroofing is not required to meet the minimum design slope requirement of one-quarter unit vertical in 12 units horizontal for roofs that provide positive roof drainage. Exception 2 likewise does not require secondary (emergency overflow) drains or scuppers to be added to such existing roofs.
Reference: IRC 2015 Section R908.1
Sample 2 — Fasteners, Flashings, Drainage, and Scuppers
Question: A cricket or saddle must be installed on the ridge side of a chimney or other roof penetration that exceeds what width, measured perpendicular to the slope?
- A. 48 inches
- B. 30 inches
- C. 24 inches
- D. 36 inches
Correct Answer: B
IBC 2015 Section 1503.6 requires a cricket or saddle on the ridge side of any chimney or penetration greater than 30 inches (762 mm) wide measured perpendicular to the slope. The covering must be sheet metal or the same material as the roof covering; properly flashed unit skylights are excepted.
Reference: IBC 2015 Chapter 15 — Section 1503.6
Sample 3 — Administration and General Requirements
Question: You are the roofing contractor on a new commercial building and are reviewing the schedule of inspections the building official is required to make upon notification. Which of the following is NOT one of the inspections specifically enumerated in the commercial code?
- A. Lath and gypsum board inspection
- B. Concrete slab and under-floor inspection
- C. Energy efficiency inspection
- D. Roof covering inspection
Correct Answer: D
IBC 2015 Section 110.3 states the building official shall make the inspections set forth in Sections 110.3.1 through 110.3.10: footing and foundation, concrete slab and under-floor, lowest floor elevation (flood hazard areas), frame, lath/gypsum board and gypsum panel products, fire- and smoke-resistant penetrations, energy efficiency, other inspections, special inspections, and final. A stand-alone roof covering inspection is not among the enumerated inspections, although Section 110.3.8 authorizes the building official to require other inspections to verify code compliance.
Reference: IBC 2015 Section 110.3 (Sections 110.3.1 through 110.3.10)
Treat your first attempt as a checkup, not a verdict. After every attempt, the results page breaks your score down by outline topic, so you can see which topics need work. Compare your score with the real exam's passing score, a minimum score of 70, and keep practicing until you pass consistently.
- Answer what you know first. Go through every question once, answer the ones you know, and bookmark the rest. Our practice exams let you bookmark and come back.
- Come back to your bookmarks. Work them out on your second pass.
- Watch your pace. The real exam works out to about 3 minutes per question.
- Look up every miss. After each attempt, find each missed question's reference in your book and read the section.
| Questions | 60 questions |
| Time limit | 3 hours |
| Passing score | a minimum score of 70 |
| Books in the exam room | Open book |
| Exam fee | $120 |
- Results for examinations taken electronically are available immediately after the examination is completed.
- You must wait 10 days before retaking a failed exam.
Source: National Contractor/Trades Examination Information Bulletin, PUBLISHED June 30, 2026. Check the bulletin before test day: fees and rules can change.