ICC G27 Master Plumber with Gas Exam (2018 IPC/IFGC) Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real Pearson VUE test format.
- 100 questions (same as real exam)
- 240 minute time limit
- 8 topic areas covered
- 433 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
ICC G27 Master Plumber with Gas (2018 IPC/IFGC) Practice Exam Guide
What's on the exam
Questions per topic, out of 100This practice exam is built around the official content outline for the ICC G27 Master Plumber with Gas (2018 IPC/IFGC) exam: Administration General Regulations, Plumbing Fixtures, Water Supply and Distribution, Sanitary Drainage, Plumbing Vent Requirements, Traps, Interceptors, and Separators, Storm Drainage, Gas Piping.
There are two ways to practice. The free practice exam gives you 10 questions per attempt, and you can take it as many times as you like. The full practice exam gives you 100 questions on a 4 hours clock, with a new draw from our question bank each time.
Administration General Regulations 36 items
Our study plan for this topic: General Installation Requirements; Code Definitions and Terms; Plan Reading; Testing; Materials; Permits and permit applications; Inspections and inspection types; Code official authority and duties.
Plumbing Fixtures 13 items
Our study plan for this topic: Water Heaters; Water Closets and Urinals; Specialty Fixtures; Bathtubs, Showers, Sinks, and Lavatories; Minimum Number of Required Plumbing Fixtures by Occupancy; Fixture Installation Requirements and Clearances; Faucets, Fixture Fittings, and Shower Valve Standards; Flushing Devices for Water Closets and Urinals.
Water Supply and Distribution 9 items
Our study plan for this topic: Service Distribution and Piping; Water Supply and Pressure; Protection of Potable Water Supply; Pipe Materials and Approved Standards for Water Service and Distribution; Joining Methods and Connection Requirements by Pipe Material; Fixture Supply Pipe Sizing and Flow Rate Requirements; Hot Water Supply System Requirements and Temperature Controls; Valve Installation Requirements and Locations.
Sanitary Drainage 8 items
Our study plan for this topic: Building Sanitary Drainage; Sumps and Ejectors; Indirect and Special Waste Systems; Drainage pipe materials and applicable standards (above-ground, underground, and building sewer); Pipe joints and connection methods by material type; Slope, sizing, and fixture unit load calculations for drainage systems; Cleanout requirements, placement, spacing, and access; Drainage fittings, changes in direction, and prohibited connections.
Plumbing Vent Requirements 6 items
Our study plan for this topic: Vent Connections and Grades; Vent Terminals; Vent Pipe Sizing and Developed Length; Types of Venting Methods (Individual, Common, Wet, Circuit, Combination, Island, Single-Stack); Air Admittance Valves; Trap Seal Protection and Fixture Trap Distance from Vent; Vent Stack and Stack Vent Requirements; Relief Vents for Multi-Story Stacks.
Traps, Interceptors, and Separators 5 items
Our study plan for this topic: Installation of Traps; Interceptors and Separators; Trap seal depth requirements and protection methods; Prohibited trap types; Trap sizing and dimensional limits; Grease interceptor sizing and capacity requirements; Oil separator design and capacity requirements; Sand interceptors and specialty interceptors (clothes washers, bottling, slaughterhouses).
Storm Drainage 2 items
Our study plan for this topic: Storm Drainage; Sizing of vertical conductors, leaders, and horizontal storm drains using 100-year rainfall rate tables; Primary and secondary (emergency overflow) roof drain requirements and scupper sizing; Prohibited connections and disposal requirements for storm water; Approved materials for inside conductors, underground storm drain pipe, building storm sewer pipe, and subsoil drain pipe; Roof drain installation requirements and flow rate calculations for system sizing; Storm drain traps: when required, sizing, material, and cleanout requirements; Siphonic roof drainage system design standards.
Gas Piping 21 items
Our study plan for this topic: Gas Piping for Service & Distribution Piping; Gas Piping Requirements, Specific Appliances Equipment; Source of Combustion Air & Duct Openings; Fuel-burning Appliance, Vent, Connector; CSST bonding and grounding requirements; Pipe sizing methods and sizing tables (longest length, branch length, hybrid pressure); Permitted piping materials, tubing standards, and fitting types; Pressure testing procedures, test medium, duration, and leak detection.
Sample 1 — Administration General Regulations
Question: Which vent is a pipe connecting upward from a soil or waste stack to a vent stack for the purpose of preventing pressure changes in the stacks?
- A. Relief vent
- B. Circuit vent
- C. Branch vent
- D. Yoke vent
Correct Answer: D
IPC Section 202 defines YOKE VENT as a pipe connecting upward from a soil or waste stack to a vent stack for the purpose of preventing pressure changes in the stacks. A relief vent provides circulation of air between drainage and vent systems; a branch vent connects individual vents to a vent stack or stack vent.
Reference: IPC 2018 Chapter 2 — Section 202, definitions of Yoke Vent, Relief Vent and Branch Vent
Sample 2 — Gas Piping
Question: What is the maximum input rating allowed for an unvented room heater?
- A. 20,000 Btu/h
- B. 50,000 Btu/h
- C. 30,000 Btu/h
- D. 40,000 Btu/h
Correct Answer: D
Per IFGC Section 621.3, unvented room heaters shall not have an input rating in excess of 40,000 Btu/h (11.7 kW).
Reference: IFGC 2018 Section 621.3
Sample 3 — Plumbing Fixtures
Question: Lavatories shall be provided with waste outlets having a diameter of not less than:
- A. 1 1/2 inches
- B. 1 1/4 inches
- C. 1 inch
- D. 2 inches
Correct Answer: B
Per IPC 2018 Section 419.3, lavatories shall have waste outlets not less than 1 1/4 inches in diameter, with a strainer, pop-up stopper, crossbar or other device to restrict the clear opening. The 1 1/2-inch minimum applies to sinks, laundry trays and showers.
Reference: IPC 2018 Chapter 4 — Section 419.3 Lavatory Waste Outlets
Your first score is just a starting point. After every attempt, the results page shows how you did on each outline topic, so you can see what to work on next. Compare your score with the real exam's passing score, 70% correct, and keep at it until you pass consistently.
- Start with the questions you know. Go through the whole exam once and bookmark anything you're unsure about. Our practice exams let you bookmark and come back.
- Circle back to your bookmarks on the second pass.
- Keep an eye on your pace. The real exam works out to about 2 minutes 24 seconds per question.
- Turn every miss into a lesson. After each attempt, look up each missed question's reference in your book and read the section.
| Questions | 100 questions |
| Time limit | 4 hours |
| Passing score | 70% correct |
| Books in the exam room | Open book |
| Exam fee | $120 |
- Results for examinations taken electronically are available immediately after the examination is completed.
- You must wait 10 days before retaking a failed exam.
Source: National Contractor/Trades Examination Information Bulletin, PUBLISHED June 30, 2026; ICC Exam Catalog, checked October 6, 2026. Check the bulletin before test day: fees and rules can change.