North Carolina Electrical Contractor - Single-Family Detached Residential Dwelling (SP-SFD) Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 40 questions (same as real exam)
- 180 minute time limit
- 11 topic areas covered
- 193 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
North Carolina Electrical Contractor - Single-Family Detached Residential Dwelling (SP-SFD) Practice Exam Guide
What's on the exam
Questions per topic, out of 40This practice exam follows the official content outline for the North Carolina Electrical Contractor - Single-Family Detached Residential Dwelling (SP-SFD) exam: Bonding and Grounding, Overcurrent Protection, Wiring Methods and Terminations, Boxes and Fittings, Service Entrance and Equipment, Motors and Control Wiring, Special Occupancies and Hazardous Locations, Load Calculations, Appliances, Equipment, and Lighting, General, Laws, Rules, Basic Business Practices, and Practical Applications.
You can practice two ways. The free practice exam gives you 10 questions per attempt, and you can retake it whenever you like. The full practice exam gives you 40 questions on a 3 hours clock, with a new draw from our question bank each attempt.
Bonding and Grounding 5 items
The outline lists: Systems and equipment requiring grounding and ground-fault protection; Location of connection and required interconnections; Conductor identification and color coding; Bonding jumpers; Grounding electrode conductors; Equipment grounding conductors; Grounding electrodes; Low-voltage specifications.
Overcurrent Protection 4 items
The outline lists: Location in circuit; Sizing requirements; Circuit breakers; Plug and cartridge fuses; Enclosures and locations.
Wiring Methods and Terminations 3 items
The outline lists: Permitted applications and usages; Characteristics; Conduit and wireway fill; Permitted applications and usages; Characteristics; Protection from damage; Permitted usages and ampacity ratings; Characteristics.
Boxes and Fittings 4 items
The outline lists: General information; Sizing requirements.
Service Entrance and Equipment 4 items
The outline lists: Installation requirements; Service equipment; General sizing requirements.
Motors and Control Wiring 2 items
The outline lists: General information; Branch circuit and feeder ampacity; Overload protection; Short-circuit and ground-fault protection; Disconnects/controllers; Size; Type; Location.
Special Occupancies and Hazardous Locations 1 item
The outline lists: Mobile homes and mobile home parks; Swimming pools; Underwater lighting fixtures.
Load Calculations 4 items
The outline lists: Branch circuits; Total computed load; Conductor ampacity requirements; Low-voltage.
Appliances, Equipment, and Lighting 3 items
The outline lists: Air conditioners; Residential, commercial, and industrial equipment; Lighting fixtures; Space heating equipment and boilers; Transformers.
General 2 items
The outline lists: Definitions; Installation requirements.
Laws, Rules, Basic Business Practices, and Practical Applications 8 items
The outline lists: Electrical Contractors Licensing Law (General Statutes Chapter 87, Article 4); Board’s Rules for the Implementation of the Electrical Contractors Licensing Law (Title 21, North Carolina Administrative Code, Chapter 18B); NASCLA Contractors’ Guide to Business, Law and Project Management - North Carolina Electrical Edition; National Fire Alarm Code.
Sample 1 — Laws, Rules, Basic Business Practices, and Practical Applications
Question: You applied and paid the examination application fee, passed the Single-Family Detached Dwelling (SP-SFD) examination, and the Board has reviewed your score. What non-refundable license fee must you now pay for this special restricted classification?
- A. $150.00
- B. $200.00
- C. $100.00
- D. $90.00
Correct Answer: C
Per the NASCLA Contractors' Guide (NC Electrical Edition), Chapter 3, Licensing Application: the non-refundable license fees are Limited $100, Intermediate $150, Unlimited $200, and All Special Restricted (which includes SP-SFD) $100. The $90 figure is the Application for Examination fee, not the license fee.
Reference: NASCLA Contractors' Guide to Business, Law and Project Management - North Carolina Electrical Edition, Chapter 3 — Licensing Application section
Sample 2 — Bonding and Grounding
Question: An insulated grounded conductor of 6 AWG or smaller shall be identified by which of the following means?
- A. A continuous white or gray outer finish
- B. A continuous red outer finish
- C. A continuous green outer finish
- D. A continuous blue outer finish
Correct Answer: A
Per NEC 200.6(A), an insulated grounded conductor of 6 AWG or smaller shall be identified by a continuous white outer finish, a continuous gray outer finish, or three continuous white or gray stripes on other than green insulation, among other methods.
Reference: NEC 2020 Section 200.6(A)
Sample 3 — Overcurrent Protection
Question: You are a master electrician installing a new 1,400-ampere circuit breaker for a main distribution panel. The building engineer asks you what additional requirements apply since the breaker is rated above a certain amperage threshold. According to the NEC, which of the following arc energy reduction methods would NOT be an acceptable option for this installation?
- A. Temporary adjustment of the instantaneous trip setting during maintenance
- B. An instantaneous trip setting that is permanently set
- C. Energy-reducing maintenance switching with local status indicator
- D. Zone-selective interlocking
Correct Answer: A
Per NEC 240.87, arc energy reduction requirements apply where the highest continuous current trip setting for which the actual overcurrent device installed in a circuit breaker is rated or can be adjusted is 1,200 A or higher. NEC 240.87(B) lists acceptable methods to reduce clearing time, including (1) zone-selective interlocking, (3) energy-reducing maintenance switching with local status indicator, and (5) an instantaneous trip setting. However, 240.87(B)(5) explicitly states: 'Temporary adjustment of the instantaneous trip setting to achieve arc energy reduction shall not be permitted.' Therefore, temporary adjustment of the instantaneous trip setting is NOT an acceptable method. The 1,400 A breaker in this scenario exceeds the 1,200 A threshold, so 240.87 applies.
Reference: NEC 2020 Section 240.87(B)
Your first attempt tells you where you're starting from. After every attempt, the results page shows your score for each outline topic, so you can see what to study next. Compare your score with the real exam's passing score, 70% correct, and keep going until you pass consistently.
- Answer the questions you know first, and bookmark the rest. Our practice exams let you bookmark and come back.
- Return to your bookmarks on the second pass.
- Keep a steady pace. The real exam works out to about 4 minutes 30 seconds per question.
- After each attempt, look up each missed question's reference and read the section.
| Questions | 40 questions |
| Time limit | 3 hours |
| Passing score | 70% correct |
| Books in the exam room | Open book |
| Exam fee | $125 |
- Results are given immediately at the test center, with a diagnostic report of strengths and weaknesses for candidates who do not pass.
- A candidate who fails must wait 3 months before retaking the same classification and must re-apply to the Board for each attempt.
Source: NCBEEC Examination Information Handbook (North Carolina Board of Examiners of Electrical Contractors), July 2026. Check the bulletin before test day: fees and rules can change.