California C-39 Roofing Contractor Exam
Practice at the real exam's pace
Every practice exam shows your time per question against the real exam's clock (1:49 here), and each topic lands in one of these:
What's on the exam
Questions per topic, out of 115Topics
Planning and Estimating
Key Concepts
Measuring and calculating area. Length and width must be measured accurately; an error in ridge, hip or valley length has far less effect on the bid. Recording 100' x 200' when the roof is actually 100'-6" x 200'-6" understates the job by 150 SF, or 1.5 squares (1 square = 100 SF) — Ch. 1, Measuring the Roof. Irregular level roofs may be taken off by the positive method (divide into rectangles and add) or the negative method (extend the roof lines into one rectangle and deduct the areas outside the roof) — Ch. 1, Level Roofs (Example 1-2).
Net vs. gross. Net roof area is the deck actually covered; gross is what you must buy, adding starter course, hip and ridge units, laps and cutting waste. The allowance factor is the ratio of the two — Ch. 1, Net Versus Gross Roof Area (Eq. 1-12).
Universal takeoff formula. Net Roof Area = Roof Plan Area x Roof-Slope Factor may be applied to a whole roof in one calculation only where all roof planes have the same slope and all hips and valleys are framed at 45 degrees to the eaves. Where slope changes from one section to another, a separate takeoff is required for each slope — Ch. 1, Calculating Total Net Roof Area (Eq. 1-13, Example 1-13).
Job Site Preparation for Roof Projects
Key Concepts
Reroofing terminology. Reroofing is the process of re-covering, or tearing off and replacing, an existing roof covering. Re-covering is installing an additional roof covering over a prepared existing roof covering without removing it; replacement is removing the existing covering, repairing damaged substrate and installing new (NRCA Steep-slope 2025, Chapter 6—Reroofing, Section 6.1—Definitions).
Code-required replacement. All layers of the previously installed roof system must be removed, with one exception: an existing water and ice-dam protection membrane adhered directly to the deck may remain and be covered with an additional layer of like membrane (Membrane 2023, Section 9.3—Building Code Requirements for Reroofing).
Deck inspection. Before roofing materials are applied, the contractor and the appropriate parties should visually inspect the deck surface: broom clean, reasonably smooth, free of voids or depressions, adequately attached, and rigid enough not to deflect excessively under live loads. Visible defects are noted, corrected, and a second inspection is held with the same parties. A roofing contractor can inspect only the deck surface and cannot assume responsibility for slope, structural integrity, attachment, or conduit/equipment below the deck (Steep-slope 2025, Chapter 2—Roof Decks).
Pre-job evaluation of existing systems. On metal decks, fasteners visible in the field of the roof area (distinct from deck sidelap screws and structural attachment) indicate the insulation is mechanically attached; absence of visible fasteners suggests an adhered or loose-laid/ballasted system (Membrane 2023, Section 9.2). Nondestructive moisture surveys (infrared thermography, neutron thermalization, electrical capacitance) give indirect readings; core cut results are used for calibration and verification, with enough cores to represent the area evaluated (Membrane 2023, Section 9.2—Moisture Within the Existing Roof Assembly). Base flashings built with roof cements and bituminous aluminum coatings may…
Low-Slope Roof Projects
Key Concepts
Slope and drainage. IBC 2021 requires a design minimum slope of ¼:12 for membrane roof systems (⅛:12 for coal tar BUR). NRCA's criterion for positive drainage is no ponding water 48 hours after a rain event in drying conditions (Section 5.1). Loose-laid, ballasted EPDM configurations list a minimum ¼:12 for new construction, positive drainage for replacement, and a maximum slope of 2:12 (Chapter 1).
Rigid board insulation. Flat stock joints must be staggered and offset from adjacent layers a minimum of 6 inches; tapered insulation joints need not be staggered (Section 4.1). Exception: with a heat-induction-welded single-ply system, top-layer flat stock boards are not staggered — joints run in continuous straight lines in both directions so the welded plate grid aligns (Sections 4.9, 5.4). Polyisocyanurate for low-slope membrane assemblies: minimum 20 psi (ASTM C1289 Type II, Class 1, Grade 2 or 3); high-density cover board (Type II, Class 4, Grade 1) is 80 psi (Section 4.9). XPS above the membrane in protected membrane roofs: ASTM C578 Type VI, 40 psi minimum (Section 4.4). EPS maximum recommended exposure temperature is 165 F (Section 4.3). Perlite cover board at 14.5 pcf, ½ inch thick, increased compressive/flexural strength = ASTM C728, Type 3 (Section 4.8).
Tapered insulation (Section 4.15). Saddle/cricket material is sloped twice the adjacent field slope, with 1/2:12 the maximum. Raised curbs must stand high enough above the tapered insulation for a minimum 8-inch flashing height. Where adjoining drainage patterns do not meet at a common uniform thickness, an area divider that does not dam runoff provides the transition.
Steep-Slope Roof Projects
Key Concepts
Deck and slope - Plywood for steep-slope coverings: minimum four-ply, ⅝-inch nominal (19/32-inch actual) at 16-inch rafter spacing; minimum four-ply, ¾-inch nominal (23/32-inch actual) at 24-inch rafter spacing (Steep-slope 2025, Asphalt Shingle, Ch. 2—Roof Decks, Sec. 2.1). - NRCA recommends specifying deck slopes of 4:12 or greater for asphalt shingle (Ch. 2), metal shingle (Ch. 2), wood shake/shingle (Ch. 2) and tile (Ch. 2) systems. Architectural metal panel systems perform well at 3:12 or greater; structural metal panel minimum is ½ inch per foot, and where valleys occur the panels should be sloped so the valley itself achieves ½ inch per foot (Metal Panel 2024, Ch. 5, Sec. 5.1). - Counter-battens: not more than 16 inches on center with nominal 1-by-2 battens; not more than 24 inches on center with nominal 2-by-2 battens (Tile, Ch. 2, Sec. 2.3). - IBC 2021: metal roof panel = interlocking sheet with minimum installed weather exposure of 3 sq. ft.; metal roof shingle = less than 3 sq. ft. (Metal Panel 2024, Ch. 5, Sec. 5.1).
Underlayment - Water and ice-dam protection membrane starts at the eave and extends upslope to a minimum of 24 inches, measured in the level plane, inside the exterior wall line (Metal Shingle, Ch. 3, Sec. 3.2). - Synthetic sheet underlayment is "impermeable" at less than 0.1 perm; not recommended over unvented or inadequately ventilated attics (Metal Shingle, Ch. 3, Sec. 3.1). - Tile: asphalt felt should comply with ASTM D4869, Type IV (#26) (Tile, Ch. 3, Sec. 3.1). Single-layer mechanically attached underlayment: side laps minimum 2 inches, end laps minimum 6 inches (Sec. 3.2). Felt turned down over the rake minimum 1 inch unless rake…
Safety
Key Concepts
IIPP (§1509, §3203) - Supervisory employees must conduct "toolbox"/"tailgate" safety meetings, or the equivalent, with their crews at least every 10 working days (§1509(e)); the employer must also establish an effective IIPP (§1509(a)) and a written Code of Safe Practices (§1509(b)). - Training documentation must include employee name or other identifier, training dates, type(s) of training, and training providers, kept at least one year (§3203(b)(2)). - Exception to §3203(a)(3): employers having fewer than 10 employees may communicate and instruct orally in general safe work practices, with specific instructions on hazards unique to the job assignment. - A labor/management committee is presumed in substantial compliance if it meets regularly, but not less than quarterly, keeps written records at least one year, reviews inspections and accident investigations, and verifies abatement on Division request (§3203(c)).
PPE (§§3380–3385) - Protective equipment must be distinctly marked to identify the manufacturer; exception for employer-manufactured shields, barriers, etc. (§3380(b)). - The hazard assessment certification identifies: the workplace evaluated, the person certifying, the date(s), and that the document is a certification of hazard assessment (§3380(f)(2)). Employee names belong to the separate training certification (§3380(f)(7)). - Helmet markings: manufacturer, ANSI designated standard number and date, and ANSI designated class and impact type (§3381(d)). Contact risk with conductors less than 600 volts → Class E or G; over 600 volts → Class E; Class C only where there is no electrical contact risk (§3381(c)(2)(B)). - Eye protection for vision correction: safety spectacles with corrected lenses; goggles over spectacles; or goggles with corrective lenses behind protective lenses (§3382(c)). Welding filter shades are a guide — a shade more dense than listed may be used (§3382(b)). - Hand protection…