Oklahoma Refinery Electrical Journeyman Practice Exam
Free Practice Exam
Test your knowledge with 10 questions from our pool of 20 free questions.
- 10 questions per attempt
- 30 minute time limit
- Unlimited attempts
- A new mix each time
- Instant results
Full Practice Exam
Complete exam simulation matching the real PSI test format.
- 100 questions (same as real exam)
- 240 minute time limit
- 12 topic areas covered
- 483 questions in pool
- Detailed explanations
Texts preferred · 9am–9pm Central
Oklahoma Refinery Electrical Journeyman Practice Exam Guide
What's on the exam
Questions per topic, out of 100This practice exam follows the official content outline for the Oklahoma Refinery Electrical Journeyman exam: General Electrical Knowledge, Electrical Installation Requirements, Services, Feeders, and Branch Circuits, Overcurrent Protection, Grounding and Bonding, Conductors and Cables, Raceways and Boxes, Low Voltage, Alarms, Signaling Systems, and Communications, Lighting and Signs, Safety, Motors and Transformers, Hazardous Locations.
You have two ways to practice. The free practice exam gives you 10 questions per attempt, and you can retake it as often as you like. The full practice exam gives you 100 questions on a 4 hours clock, with a new draw from our question bank every attempt.
General Electrical Knowledge 10 items
The outline lists: Permits and Inspections; Preservation of Structural Integrity; Needs Analysis and Estimate; Voltage, Current, and Resistance in Series, Parallel, and Combination Circuits; Power Used in a Circuit; Power lost (called Heat Lost) in Any Circuit; Fundamental AC Theory; Fundamental Three-phase AC Theory.
Electrical Installation Requirements 4 items
Our study plan for this topic: Approved Methods of Installation of Electrical Equipment; Approved Methods of Installation of Electrical Equipment in Excess of 600 volts; Branch-Circuit and Feeder Load Calculations and Demand Factors; GFCI and AFCI Protection Requirements; Working Space and Clearance Requirements for Electrical Equipment; Underground Installation and Minimum Cover Requirements; Conductor Sizing, Ampacity, and Overcurrent Protection for Branch Circuits and Feeders; Outside Branch Circuits and Feeders — Clearances, Supports, and Disconnecting Means.
Services, Feeders, and Branch Circuits 6 items
The outline lists: Services; Voltage Drop for Branch Circuits or Feeders; Services in Excess of 600 volts; Feeders; Outside Branch Circuits and Feeders; Branch Circuits; Space-heating, Snow-melting, and Pipe-heating Circuits; Air-conditioning and Refrigeration Equipment.
Overcurrent Protection 6 items
Our study plan for this topic: NEC Overcurrent Protection Requirements; Conductor overcurrent protection ratings and small conductor rules (AWG sizing limits); Standard ampere ratings for fuses and circuit breakers (Table 240.6(A)); Location of overcurrent protective devices (tap conductor rules, feeder taps, transformer secondary conductors); Circuit breaker requirements (marking, interrupting ratings, arc energy reduction for 1200A and above); Overcurrent protection for systems over 1000 volts (Article 245 devices, power fuses, circuit breakers); Motor branch-circuit protective device maximum ratings and running overload protection; Short-circuit current calculation methods (transformer let-through current, fault current at point of fault).
Grounding and Bonding 10 items
Our study plan for this topic: General Requirements; Required Sizes of Grounding Electrode Conductors; Required Sizes of Equipment Grounding Conductors; Grounding Electrode System and Electrode Types; Grounding Electrode Conductor Installation Methods; Main Bonding Jumper and System Bonding Jumper Requirements; Supply-Side Bonding Jumper Sizing and Installation; Bonding of Piping Systems and Structural Metal.
Conductors and Cables 6 items
The outline lists: Underground Conductors and Cables; Vertical Installations; Selecting Conductors; Armored Cable, Type AC; Metal-clad Cable, Type MC; Nonmetallic-sheathed Cable, Types NM, NMC, NMS; Service Entrance Cables, Types SE and USE; Underground Feeder and Branch Circuit Cable, Type UF.
Raceways and Boxes 6 items
The outline lists: General Raceway Requirements; General Box Requirements; Pull Boxes; Conduit Fittings; Type RMC (Rigid Metal Conduit); Type EMT (Electric Metallic Conduit); Type IMC (Intermediate Metal Conduit); Type RNC (Rigid Nonmetallic Conduit).
Low Voltage, Alarms, Signaling Systems, and Communications 4 items
The outline lists: Remote Control or Signaling Circuits; Communication Circuits; Equipment Operating at 50 volts or Less; Fiber Optics; Photovoltaics; Remote Controls; Fire Alarms; Circuit Wiring for an Emergency System.
Lighting and Signs 4 items
The outline lists: Fixture Installation; Fixture Grounding; Fixture Wiring; Fluorescent Fixtures; Fixture Construction Requirements; Recessed Fixtures; Lighting Systems that Operate at Less Than 30 volts; Neon Lighting and Electric Signs.
Safety 5 items
The outline lists: Job Site Sanitation; Responsibility for Providing Personal Protective Equipment; Excavation Safety; Emergency Action Plans; Safety Training Requirements; Ventilation; First Aid Kit Requirements; Use of Personal Protective Equipment.
Motors and Transformers 4 items
Our study plan for this topic: Motors Used in Dwellings; Motor Branch Circuits in Industrial and Commercial Locations; Feeder Transformers; Use of Transformers; Motor Controller Requirements and Ratings; Motor Disconnecting Means Types and Location; Motor Overload Protection Methods and Sizing; Full-Load Current Tables for DC, Single-Phase, and Three-Phase Motors.
Hazardous Locations 35 items
The outline lists: Hazardous Location Classifications; Hazardous Materials; Equipment used in Hazardous Locations; Ventilation and Seals; Underground Wiring; Fuel Dispensing Location Requirements.
Sample 1 — Hazardous Locations
Question: A journeyman needs to run intrinsically safe circuit conductors in the same cable tray as nonintrinsically safe circuit conductors. Where no grounded metal partition, insulating partition, or metal-clad cable is used, what is the minimum separation distance required between the two groups of conductors, with the conductors secured?
- A. 25 mm (1 in.)
- B. 150 mm (6 in.)
- C. 50 mm (2 in.)
- D. 75 mm (3 in.)
Correct Answer: C
Per NEC 504.30(A)(1), intrinsically safe conductors may share a raceway, cable tray, or cable with nonintrinsically safe conductors only where separated by at least 50 mm (2 in.) and secured, by a grounded metal partition 0.91 mm (0.0359 in.) or thicker, by an approved insulating partition, or where one set of conductors is in Type MC/MI or other approved grounded metal-clad cable.
Reference: NEC 2023 Section 504.30(A)(1)
Sample 2 — General Electrical Knowledge
Question: A worker stands in the working space between two 480-volt switchboards that face each other, and both have exposed live parts. What is the minimum depth of working space required?
- A. 3 ft
- B. 4 ft
- C. 5 ft
- D. 6 ft
Correct Answer: B
Exposed live parts on both sides of the working space = Condition 3. Table 110.26(A)(1), 151-600 volts nominal to ground, Condition 3 = 4 ft (1.2 m).
Reference: NEC 2023 Table 110.26(A)(1)
Sample 3 — Grounding and Bonding
Question: You are installing a grounded separately derived system where the source and the first disconnecting means are in separate enclosures. The system bonding jumper is installed at the source. Where must the supply-side bonding jumper be installed?
- A. From the source enclosure to the first disconnecting means enclosure, with the circuit conductors
- B. From the load-side equipment back to the transformer neutral
- C. From the panelboard to the nearest grounding electrode
- D. From the grounding electrode to the first disconnecting means only
Correct Answer: A
Per NEC 250.30(A)(2), if the source of a separately derived system and the first disconnecting means are located in separate enclosures, a supply-side bonding jumper shall be installed with the circuit conductors from the source enclosure to the first disconnecting means enclosure.
Reference: NEC 2023 Section 250.30(A)(2)
Treat your first attempt as a checkup, not a verdict. After every attempt, the results page breaks your score down by outline topic, so you can see which topics need work. Compare your score with the real exam's passing score, 70% correct, and keep practicing until you pass consistently.
- Answer what you know first. Go through every question once, answer the ones you know, and bookmark the rest. Our practice exams let you bookmark and come back.
- Come back to your bookmarks. Work them out on your second pass.
- Watch your pace. The real exam works out to about 2 minutes 24 seconds per question.
- Look up every miss. After each attempt, find each missed question's reference in your book and read the section.
| Questions | 100 questions |
| Time limit | 4 hours |
| Passing score | 70% correct |
| Books in the exam room | Open book |
| Exam fee | $92 |
- Results are given immediately on screen, with a diagnostic strengths-and-weaknesses report for candidates who do not pass and an unofficial printed score report at the site.
- After a first failure you must wait 30 days to retest; electrical exam retests continue to require 30 days, while all other exams require 90 days from the second failure onward.
Source: State of Oklahoma Electrical, Mechanical, Roofing, and Plumbing Examinations Candidate Information Bulletin, Effective 12/18/2025. Check the bulletin before test day: fees and rules can change.