National · Pearson VUE

ICC F34 Journeyman Gas Pipe Fitter Exam (2015 IFGC) Practice Exam

55 questions 120 minutes 70% to pass 5 topics 2:10 per question Open book 260 questions in pool
Free Cheat Sheet Official Bulletin
Free

Free Practice Exam

$0

Test your knowledge with 10 questions from our pool of 20 free questions.

  • 10 questions per attempt
  • 30 minute time limit
  • Unlimited attempts
  • A new mix each time
  • Instant results
No account required.
Full Exam

Full Practice Exam

$9.95

Complete exam simulation matching the real Pearson VUE test format.

  • 55 questions (same as real exam)
  • 120 minute time limit
  • 5 topic areas covered
  • 260 questions in pool
  • Detailed explanations
Price per attempt. Never the same exam twice: each attempt draws a fresh set of questions.
Not sure which exam you need? Text us: (813) 582-5360
Texts preferred · 9am–9pm Central
Want a guided study plan? Study Course: topic briefs, 5 topic quizzes and this full exam. $59.95/month.
See the study course

ICC F34 Journeyman Gas Pipe Fitter (2015 IFGC) Practice Exam Guide

Built from the official Pearson VUE exam bulletin. View the bulletin

What's on the exam

Questions per topic, out of 55
General Requirements22
Appliances and Equipment13
Chimneys and Vents8
Combustion Air7
Fuel Supply System Sizing5

This practice exam follows the official content outline for the ICC F34 Journeyman Gas Pipe Fitter (2015 IFGC) exam: General Requirements, Appliances and Equipment, Fuel Supply System Sizing, Combustion Air, Chimneys and Vents.

  • Free practice exam: 10 questions per attempt, retake as often as you like.
  • Full practice exam: 55 questions on a 2 hours clock, a new draw from our bank every attempt.

5 topics

General Requirements 22 items

Our study plan for this topic: General Installation Requirements; Code Definitions and Terms; Plan Reading; Testing; Materials; Permits and Permit Requirements; Inspections and Inspection Types; Appliance Location and Prohibited Locations.

Appliances and Equipment 13 items

Our study plan for this topic: Requirements for Specific Appliances & Equipment; Clearance requirements for specific appliances; Clothes dryer exhaust duct installation and length limitations; Unvented room heater restrictions and oxygen-depletion safety systems; Vented wall furnace and floor furnace placement and access; Forced-air warm-air furnace return air prohibited sources; Testing standards and listing requirements by appliance type; Sauna heater combustion air, temperature controls, and safety notices.

Fuel Supply System Sizing 5 items

Our study plan for this topic: Service and Distribution Pipe Sizing; Maximum Gas Demand Calculation (Total Connected Load); Allowable Pressure Drop and Minimum Appliance Supply Pressure; Pipe Length Determination Methods (Longest Length, Branch Length, Hybrid Pressure); Sizing Tables and Equations for Different Pipe/Tubing Materials (Schedule 40 Steel, Copper, CSST, PE); Altitude Adjustment for Gas Demand Above 2,000 Feet Elevation; Maximum Design Operating Pressure Limits for Interior Piping Systems; Sizing for Existing System Modifications and Additional Appliances.

Combustion Air 7 items

Our study plan for this topic: Combustion Air Source, Size of Ducts/Openings; Indoor Combustion Air Volume Requirements (Standard and Known-ACH Methods); Outdoor Combustion Air Opening Methods (Two-Opening and One-Opening); Combination Indoor and Outdoor Combustion Air; Mechanical Combustion Air Supply Systems and Appliance Interlock; Louvers, Grilles, and Screen Free-Area Calculations; Combustion Air Duct Construction and Installation Requirements; Makeup Air Requirements for Exhaust Interference.

Chimneys and Vents 8 items

Our study plan for this topic: Venting, Vent Connector, and Chimneys; Appliance venting categories and vent type selection (Types B, BW, L, single-wall metal); Vent and chimney termination height and location requirements; Sizing of Category I venting systems using IFGC Section 504 tables; Vent connector materials, clearances, slope, and length limitations; Draft hoods and draft control devices installation requirements; Appliances not required to be vented and aggregate input limits; Masonry chimney inspection, lining, and cleanout requirements.

3 questions

Sample 1 — General Requirements

Question: A master fuel gas contractor sits on the jurisdiction's board of appeals. At an upcoming hearing one regular member must be disqualified because of a financial interest in the project. How many alternate members is the chief appointing authority required to appoint, and for what term?

  • A. One alternate, serving a 3-year term
  • B. Two alternates, serving 5-year terms
  • C. Two alternates, serving 3-year terms
  • D. One alternate, serving a 5-year term

Correct Answer: B

IFGC 2015, Section 109.2.2 requires the chief appointing authority to appoint two alternate members, called by the board chairman to hear appeals during the absence or disqualification of a member. Alternates must possess the qualifications required for board membership and are appointed for 5 years, or until a successor has been appointed. (Section 109.2.4 is the provision requiring a member with a personal, professional or financial interest not to hear the appeal.)

Reference: IFGC 2015 Section 109.2.2

Sample 2 — Appliances and Equipment

Question: Vented gas fireplace heaters are required to be tested in accordance with which standard?

  • A. ANSI Z21.60
  • B. ANSI Z21.50
  • C. ANSI Z21.88
  • D. ANSI Z21.84

Correct Answer: C

Per 2015 IFGC Section 605.1, vented gas fireplace heaters shall be tested in accordance with ANSI Z21.88. ANSI Z21.50 applies to vented gas fireplaces (Section 604.1), ANSI Z21.60 to decorative appliances for installation in solid fuel-burning fireplaces, and ANSI Z21.84 to manually lighted natural gas decorative appliances (Section 602.1).

Reference: IFGC 2015 Section 605.1

Sample 3 — Chimneys and Vents

Question: Rather than using the vent sizing tables, you elect to use the alternative area method to size a chimney venting system serving two draft-hood-equipped appliances. Under that method, the effective area of the chimney flue must be:

  • A. Not less than the sum of both draft hood outlet areas
  • B. Not less than twice the smaller draft hood outlet area
  • C. Not less than the larger outlet area plus 25 percent of the smaller
  • D. Not less than the larger outlet area plus 50 percent of the smaller

Correct Answer: D

Per IFGC 2015, Section 503.5.5, Item 3, for a chimney venting system connected to two appliances with draft hoods, the effective area of the chimney flue shall be not less than the area of the larger draft hood outlet plus 50 percent of the area of the smaller draft hood outlet, and not greater than seven times the smallest draft hood outlet area.

Reference: IFGC 2015 Section 503.5.5

  • Your results break the score down by outline topic.
  • The real exam's passing score: 70% correct.
  • Keep practicing until you pass consistently, not just once.

  • Answer what you know first and bookmark the rest. Our practice exams let you bookmark and come back.
  • Work your bookmarks on the second pass.
  • Real exam pace: about 2 minutes 11 seconds per question.
  • After each attempt, look up every miss in your book.

Questions 55 questions
Time limit 2 hours
Passing score 70% correct
Books in the exam room Open book
Exam fee $120
  • Results for examinations taken electronically are available immediately after the examination is completed.
  • You must wait 10 days before retaking a failed exam.

Source: National Contractor/Trades Examination Information Bulletin, PUBLISHED June 30, 2026; ICC Exam Catalog, checked October 6, 2026. Check the bulletin before test day: fees and rules can change.